VUIS CONSULTING PTY LTD.
PROJECT PLAN [INSERT VERSION NUMBER]
[IMPLEMENTATION OF SAP SYSTEMS]
[INSERT DATE HERE]
[INSERT AUTHOR NAME HERE]
[INSERT AUTHOR JOB TITLE HERE]
[INSERT AUTHOR EMAIL HERE]
The following template is for educational purposes only.
PROJECT PLAN [INSERT VERSION NUMBER]
[IMPLEMENTATION OF SAP SYSTEMS]
[INSERT DATE HERE]
[INSERT AUTHOR NAME HERE]
[INSERT AUTHOR JOB TITLE HERE]
[INSERT AUTHOR EMAIL HERE]
The following template is for educational purposes only.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
CONTENTS
Glossary............................................................................................................................. 2
Introduction......................................................................................................................... 3
Project scope......................................................................................................................3
Business case..................................................................................................................... 3
Project Schedule and Approach (Rollout strategy)..............................................................4
Resources.......................................................................................................................... 4
Budget................................................................................................................................ 5
Risk..................................................................................................................................... 5
Communication................................................................................................................... 6
Summary............................................................................................................................ 6
Bibliography........................................................................................................................ 7
Glossary
Term Definition
VUIS Consulting Project Plan Page 2
[Insert Author name here]
Glossary............................................................................................................................. 2
Introduction......................................................................................................................... 3
Project scope......................................................................................................................3
Business case..................................................................................................................... 3
Project Schedule and Approach (Rollout strategy)..............................................................4
Resources.......................................................................................................................... 4
Budget................................................................................................................................ 5
Risk..................................................................................................................................... 5
Communication................................................................................................................... 6
Summary............................................................................................................................ 6
Bibliography........................................................................................................................ 7
Glossary
Term Definition
VUIS Consulting Project Plan Page 2
[Insert Author name here]
Introduction
The description of this project is based on the different kind of important factors that would
be in relation to implementing of SAP system in Yes Chemist Pty Ltd. The company has
plans for implementing the SAP systems in the recent times in order to bring in massive
forms of changes within the business processes of the organisation.
The plan developed for the project would be able to outline the major form of deliverables
that would be made over the project. The project scope of the report would be outlined in
detail. This report would also outline the different processes of business that would be
benefited with the outcome of the implementation of SAP systems. Thus the project would
also cover the planned schedule that would be determined for the project. The budget and
risks involved within the project would also be discussed widey in the report. The
communication
Project scope
The project is focused on developing of SAP systems within Yes Chemist Pty Ltd that would
be performed by VUISC Pty Ltd. The aim of the project is based on discussing the
fundamentals of SAP implementation and discuss the various costs, number of resources,
develop a risk plan and discuss communication plan for the concerned project.
The objectives of the project are:
1. To determine the costs and other factors in relation to the project.
2. To determine the activities that could be implemented within the project based on the SAP
Implementation.
3. To understand risks and maintain a communication plan for the project.
Business case
The project discusses the different implementation aspects in relation to the SAP
implementation project. The project is highly needed for Yes Chemist Pty Ltd for improving
the business processes and improve the efficiency of business in their sector.
Benefits from the Project Current Status and Process for Assessing Benefit
Realisation
Efficiency development The project is currently being developed and the processes
are being addressed.
Increase in competition The aspects chosen by other businesses are being analysed
and further steps are taken.
Better forecasting of
processes
The SAP systems are being developed.
Better collaboration with
business processes
This system is in current development
Cost savings The costs accumulated would be considered.
VUIS Consulting Project Plan Page 3
[Insert Author name here]
The description of this project is based on the different kind of important factors that would
be in relation to implementing of SAP system in Yes Chemist Pty Ltd. The company has
plans for implementing the SAP systems in the recent times in order to bring in massive
forms of changes within the business processes of the organisation.
The plan developed for the project would be able to outline the major form of deliverables
that would be made over the project. The project scope of the report would be outlined in
detail. This report would also outline the different processes of business that would be
benefited with the outcome of the implementation of SAP systems. Thus the project would
also cover the planned schedule that would be determined for the project. The budget and
risks involved within the project would also be discussed widey in the report. The
communication
Project scope
The project is focused on developing of SAP systems within Yes Chemist Pty Ltd that would
be performed by VUISC Pty Ltd. The aim of the project is based on discussing the
fundamentals of SAP implementation and discuss the various costs, number of resources,
develop a risk plan and discuss communication plan for the concerned project.
The objectives of the project are:
1. To determine the costs and other factors in relation to the project.
2. To determine the activities that could be implemented within the project based on the SAP
Implementation.
3. To understand risks and maintain a communication plan for the project.
Business case
The project discusses the different implementation aspects in relation to the SAP
implementation project. The project is highly needed for Yes Chemist Pty Ltd for improving
the business processes and improve the efficiency of business in their sector.
Benefits from the Project Current Status and Process for Assessing Benefit
Realisation
Efficiency development The project is currently being developed and the processes
are being addressed.
Increase in competition The aspects chosen by other businesses are being analysed
and further steps are taken.
Better forecasting of
processes
The SAP systems are being developed.
Better collaboration with
business processes
This system is in current development
Cost savings The costs accumulated would be considered.
VUIS Consulting Project Plan Page 3
[Insert Author name here]
The dis-benefits that would be incurred by the company with the implementation of the
project are:
Dis-Benefits from the
Project
Projected Negative Outcomes
Increasing software cost The costs incurred during the project
Customization Time-consuming process
Complexity The software that would be used might be too complex for
the people to understand.
High costs of implementation The costs for implementation is high
VUIS Consulting Project Plan Page 4
[Insert Author name here]
project are:
Dis-Benefits from the
Project
Projected Negative Outcomes
Increasing software cost The costs incurred during the project
Customization Time-consuming process
Complexity The software that would be used might be too complex for
the people to understand.
High costs of implementation The costs for implementation is high
VUIS Consulting Project Plan Page 4
[Insert Author name here]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Schedule and Approach (Rollout strategy)
ID Outline
Number
Task
Mode
Task Name Duration Start
0 0 Implementation of a SAP Project227 days Mon 27-05-19
1 1 Start project 0 days Mon 27-05-19
2 2 Initial Planning and
Development of Ideas
20 days Mon 27-05-19
3 2.1 Gathering a brief analysis of
requirements from Yes Chemist
Pty Ltd.
8 days Mon 27-05-19
4 2.2 Understanding the requirements
of the company
3 days Thu 06-06-19
5 2.3 Developing a project plan 9 days Tue 11-06-19
6 2.4 Approval of a project plan 0 days Fri 21-06-19
7 2.5 Developing of financial plan 5 days Tue 11-06-19
8 2.6 Approval of financial plan 0 days Mon 17-06-19
9 2.7 Completion of the phase 0 days Fri 21-06-19
10 3 Procurement Planning Phase 15 days Mon 24-06-19
11 3.1 Developing ideas of requirement 3 days Mon 24-06-19
12 3.2 Identifying the proper technical
service provider
5 days Thu 27-06-19
13 3.3 Procuring the hardware and
software
7 days Thu 04-07-19
14 3.4 Completion of the Phase 0 days Fri 12-07-19
15 4 Recruitment of Staff from
VUISC Pty Ltd.
6 days Mon 15-07-19
16 4.1 Conducting of interviews for
qualified people
6 days Mon 15-07-19
17 4.2 Conducting a technical test over
employees
4 days Mon 15-07-19
18 4.3 Gaining approval for the
permission grant over project
progress
0 days Mon 22-07-19
19 4.4 Completion of the phase 0 days Mon 22-07-19
20 5 Execution of the SAP Project 84 days Tue 23-07-19
21 5.1 Developing the technical aspect
of the project
6 days Tue 23-07-19
22 5.2 Developing the technical plan 11 days Wed 31-07-19
23 5.3 Approval of the technical plan 0 days Wed 14-08-19
24 5.4 Development works over the
SAP Project
27 days Thu 15-08-19
25 5.5 Enabling a intial quality test
over the initial project phase
10 days Mon 23-09-19
26 5.6 Development works over next
project phase
30 days Mon 07-10-19
27 5.7 Approval of the project progress 0 days Fri 15-11-19
28 5.8 Completion of the phase 0 days Fri 15-11-19
29 6 Testing of the SAP Environment 48 days Mon 18-11-19
30 6.1 Performing Alpha testing 15 days Mon 18-11-19
31 6.2 Performing Beta testing 20 days Mon 09-12-19
32 6.3 Gathering the test results 3 days Mon 06-01-20
33 6.4 Performing analysis over the
results
10 days Thu 09-01-20
34 6.5 Deriving a result 0 days Wed 22-01-20
35 6.6 Completion of the phase 0 days Wed 22-01-20
36 7 Performing Quality Assurance
Testing
31 days Thu 23-01-20
37 7.1 Testing by quality assurance
experts
15 days Thu 23-01-20
38 7.2 Preparing the test results over
the system
6 days Thu 13-02-20
39 7.3 Documentation of the test result
plan
10 days Fri 21-02-20
40 7.4 Completion of the Phase 0 days Thu 05-03-20
41 8 Installation of the SAP systems 4 days Fri 06-03-20
42 8.1 Installation of the software
systems within the computers
2 days Fri 06-03-20
43 8.2 Final check based on proper
working of systems
2 days Tue 10-03-20
44 8.3 Final approval of project success0 days Wed 11-03-20
45 9 Project Closure Phase 19 days Thu 12-03-20
46 9.1 Presentation of the usefulness
of the system
7 days Thu 12-03-20
47 9.2 Documentation of the entire
project scheduling and
cost-planning
11 days Mon 23-03-20
48 9.3 Payment to the stakeholders 1 day Tue 07-04-20
49 9.4 Project Signing off 0 days Tue 07-04-20
50 9.5 Approval for project close 0 days Tue 07-04-20
51 10 End Project 0 days Tue 07-04-20
27-05
Project Manager,VUISC Owner,Yes Chemist Owners
Project Manager,Subject Matter Expert
21-06
Project Sponsor,Subject Matter Expert
17-06
21-06
Hardware[1],Software[1]
12-07
Project Manager
Project Manager
22-07
22-07
Project Manager,Software developers
Software developers
14-08
Software developers
Software testers
Software developers
15-11
15-11
Software testers
Software testers
22-01
22-01
Quality Assurance Experts
Quality Assurance Experts
Subject Matter Expert
05-03
Software developers
Project Manager
11-03
Project Sponsor
07-04
07-04
07-04
M T W T F S S M T W T F S S M T W T F S S M T W
13 May '19 17 Jun '19 22 Jul '19 26 Aug '19 30 Sep '19 04 Nov '19 09 Dec '19 13 Jan '20 17 Feb '20 23 Mar '20 27 Apr '20
(Figure 1: The Gantt chart for the Project)
(Source: Created by author)
VUIS Consulting Project Plan Page 5
[Insert Author name here]
ID Outline
Number
Task
Mode
Task Name Duration Start
0 0 Implementation of a SAP Project227 days Mon 27-05-19
1 1 Start project 0 days Mon 27-05-19
2 2 Initial Planning and
Development of Ideas
20 days Mon 27-05-19
3 2.1 Gathering a brief analysis of
requirements from Yes Chemist
Pty Ltd.
8 days Mon 27-05-19
4 2.2 Understanding the requirements
of the company
3 days Thu 06-06-19
5 2.3 Developing a project plan 9 days Tue 11-06-19
6 2.4 Approval of a project plan 0 days Fri 21-06-19
7 2.5 Developing of financial plan 5 days Tue 11-06-19
8 2.6 Approval of financial plan 0 days Mon 17-06-19
9 2.7 Completion of the phase 0 days Fri 21-06-19
10 3 Procurement Planning Phase 15 days Mon 24-06-19
11 3.1 Developing ideas of requirement 3 days Mon 24-06-19
12 3.2 Identifying the proper technical
service provider
5 days Thu 27-06-19
13 3.3 Procuring the hardware and
software
7 days Thu 04-07-19
14 3.4 Completion of the Phase 0 days Fri 12-07-19
15 4 Recruitment of Staff from
VUISC Pty Ltd.
6 days Mon 15-07-19
16 4.1 Conducting of interviews for
qualified people
6 days Mon 15-07-19
17 4.2 Conducting a technical test over
employees
4 days Mon 15-07-19
18 4.3 Gaining approval for the
permission grant over project
progress
0 days Mon 22-07-19
19 4.4 Completion of the phase 0 days Mon 22-07-19
20 5 Execution of the SAP Project 84 days Tue 23-07-19
21 5.1 Developing the technical aspect
of the project
6 days Tue 23-07-19
22 5.2 Developing the technical plan 11 days Wed 31-07-19
23 5.3 Approval of the technical plan 0 days Wed 14-08-19
24 5.4 Development works over the
SAP Project
27 days Thu 15-08-19
25 5.5 Enabling a intial quality test
over the initial project phase
10 days Mon 23-09-19
26 5.6 Development works over next
project phase
30 days Mon 07-10-19
27 5.7 Approval of the project progress 0 days Fri 15-11-19
28 5.8 Completion of the phase 0 days Fri 15-11-19
29 6 Testing of the SAP Environment 48 days Mon 18-11-19
30 6.1 Performing Alpha testing 15 days Mon 18-11-19
31 6.2 Performing Beta testing 20 days Mon 09-12-19
32 6.3 Gathering the test results 3 days Mon 06-01-20
33 6.4 Performing analysis over the
results
10 days Thu 09-01-20
34 6.5 Deriving a result 0 days Wed 22-01-20
35 6.6 Completion of the phase 0 days Wed 22-01-20
36 7 Performing Quality Assurance
Testing
31 days Thu 23-01-20
37 7.1 Testing by quality assurance
experts
15 days Thu 23-01-20
38 7.2 Preparing the test results over
the system
6 days Thu 13-02-20
39 7.3 Documentation of the test result
plan
10 days Fri 21-02-20
40 7.4 Completion of the Phase 0 days Thu 05-03-20
41 8 Installation of the SAP systems 4 days Fri 06-03-20
42 8.1 Installation of the software
systems within the computers
2 days Fri 06-03-20
43 8.2 Final check based on proper
working of systems
2 days Tue 10-03-20
44 8.3 Final approval of project success0 days Wed 11-03-20
45 9 Project Closure Phase 19 days Thu 12-03-20
46 9.1 Presentation of the usefulness
of the system
7 days Thu 12-03-20
47 9.2 Documentation of the entire
project scheduling and
cost-planning
11 days Mon 23-03-20
48 9.3 Payment to the stakeholders 1 day Tue 07-04-20
49 9.4 Project Signing off 0 days Tue 07-04-20
50 9.5 Approval for project close 0 days Tue 07-04-20
51 10 End Project 0 days Tue 07-04-20
27-05
Project Manager,VUISC Owner,Yes Chemist Owners
Project Manager,Subject Matter Expert
21-06
Project Sponsor,Subject Matter Expert
17-06
21-06
Hardware[1],Software[1]
12-07
Project Manager
Project Manager
22-07
22-07
Project Manager,Software developers
Software developers
14-08
Software developers
Software testers
Software developers
15-11
15-11
Software testers
Software testers
22-01
22-01
Quality Assurance Experts
Quality Assurance Experts
Subject Matter Expert
05-03
Software developers
Project Manager
11-03
Project Sponsor
07-04
07-04
07-04
M T W T F S S M T W T F S S M T W T F S S M T W
13 May '19 17 Jun '19 22 Jul '19 26 Aug '19 30 Sep '19 04 Nov '19 09 Dec '19 13 Jan '20 17 Feb '20 23 Mar '20 27 Apr '20
(Figure 1: The Gantt chart for the Project)
(Source: Created by author)
VUIS Consulting Project Plan Page 5
[Insert Author name here]
Resources
ROLES
Project Sponsor
VUISC
Project
Manager
Developer
Testers
Quality
Assurance
SMEs
Deliverable or Task Status
Initiation of the Project
Initial project planning A R C R I
Developing a project plan A C I A
Procurement Planning Phase
Identifying the proper technical service provider C I R I
Procuring the hardware and software I A C R A
Execution of the SAP Project
Developing the technical aspect of the project A I R
Enabling a intial quality test over the initial project phase I C R A
Testing of the SAP Environment
Gathering the test results I R A
Documentation of the test result plan C A R R A
Installation of the SAP systems
Installation of the software systems within the computers I R A
Sponsor Project Team Other Resources
(Figure 2: The RACI Matrix for the Project)
(Source: Created by author)
In this matrix, the different resources are listed who would be working over the project. The
owners of VUISC would be concerned over the developmental aspects of the SAP systems.
The initial planning phase of the project would be performed by the project managers at the
company and who have a good knowledge over the systems.
On the other hand, the software developers, testers and quality assurance testers would be
highly be required during the developmental aspects of the project. These teams would be
responsible for developing the SAP systems. The Subject Matter Experts would be
responsible for documenting the entire project aspects.
VUIS Consulting Project Plan Page 6
[Insert Author name here]
ROLES
Project Sponsor
VUISC
Project
Manager
Developer
Testers
Quality
Assurance
SMEs
Deliverable or Task Status
Initiation of the Project
Initial project planning A R C R I
Developing a project plan A C I A
Procurement Planning Phase
Identifying the proper technical service provider C I R I
Procuring the hardware and software I A C R A
Execution of the SAP Project
Developing the technical aspect of the project A I R
Enabling a intial quality test over the initial project phase I C R A
Testing of the SAP Environment
Gathering the test results I R A
Documentation of the test result plan C A R R A
Installation of the SAP systems
Installation of the software systems within the computers I R A
Sponsor Project Team Other Resources
(Figure 2: The RACI Matrix for the Project)
(Source: Created by author)
In this matrix, the different resources are listed who would be working over the project. The
owners of VUISC would be concerned over the developmental aspects of the SAP systems.
The initial planning phase of the project would be performed by the project managers at the
company and who have a good knowledge over the systems.
On the other hand, the software developers, testers and quality assurance testers would be
highly be required during the developmental aspects of the project. These teams would be
responsible for developing the SAP systems. The Subject Matter Experts would be
responsible for documenting the entire project aspects.
VUIS Consulting Project Plan Page 6
[Insert Author name here]
Budget
Initial Planning and Development of Ideas 74800
Procurement Planning Phase 10000
Recruitment of Staff from VUISC Pty Ltd. 28000
Execution of the SAP Project 115200
Testing of the SAP Environment 33600
Performing Quality Assurance Testing 26480
Installation of the SAP systems 8000
Project Closure Phase 3200
Total Cost for the project 299280
Total Cost for the project
The most expensive cost had been incurred during the phase of execution of the project.
During this phase, the software developers and testers had performed rigorous work over
the implementation of the SAP project.
The other expensive cost incurred is during the Initial Planning Phase of the project. During
the conduction of the phase, the project managers would conduct deep research into the
requirements that need to be included within the project.
Risk
Risk
Number
Type of Risks Risk Description Mitigation Strategy
1 Technical Failure
of systems
The systems might create some
problems during the execution phase.
Hence, the developers might
experience problems during work
scenarios.
Proper development of
code for the programs
2 Improper
estimation of
budget
Improper estimation of budget might
lead to cost overruns for the project.
This might create problems based on
estimating the hardware and software
costs during the procurement phase.
Proper estimation of
each aspects required
during the project.
3 Missing of
deadlines for
project completion
Due to poor estimation of schedules of
the project plan, deadlines might get
missed for the project.
Planning of project plan
in proper manner.
4 Error during
installation phase
There might be some kind of problems
during the installation of the software
within the computers during the
installation phase of the SAP software
The developers should
check the SAP
implementation project.
After a proper check,
the developers should
install the software
within the systems.
VUIS Consulting Project Plan Page 7
[Insert Author name here]
Initial Planning and Development of Ideas 74800
Procurement Planning Phase 10000
Recruitment of Staff from VUISC Pty Ltd. 28000
Execution of the SAP Project 115200
Testing of the SAP Environment 33600
Performing Quality Assurance Testing 26480
Installation of the SAP systems 8000
Project Closure Phase 3200
Total Cost for the project 299280
Total Cost for the project
The most expensive cost had been incurred during the phase of execution of the project.
During this phase, the software developers and testers had performed rigorous work over
the implementation of the SAP project.
The other expensive cost incurred is during the Initial Planning Phase of the project. During
the conduction of the phase, the project managers would conduct deep research into the
requirements that need to be included within the project.
Risk
Risk
Number
Type of Risks Risk Description Mitigation Strategy
1 Technical Failure
of systems
The systems might create some
problems during the execution phase.
Hence, the developers might
experience problems during work
scenarios.
Proper development of
code for the programs
2 Improper
estimation of
budget
Improper estimation of budget might
lead to cost overruns for the project.
This might create problems based on
estimating the hardware and software
costs during the procurement phase.
Proper estimation of
each aspects required
during the project.
3 Missing of
deadlines for
project completion
Due to poor estimation of schedules of
the project plan, deadlines might get
missed for the project.
Planning of project plan
in proper manner.
4 Error during
installation phase
There might be some kind of problems
during the installation of the software
within the computers during the
installation phase of the SAP software
The developers should
check the SAP
implementation project.
After a proper check,
the developers should
install the software
within the systems.
VUIS Consulting Project Plan Page 7
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Communication
Communication made Responsible person Frequency Mode of
Communication
Discussion of the project plan Project Manager Monthly Email, Face-to-
face
communication
Updating the financial plan Project Sponsor Weekly Face-to-face
communication
Developmental activities Software Developers Daily Face-to-face
communication
Updating test status Quality Assurance Testers Weekly Face-to-face
communication
Updating risk assessment
status
Project Manager Weekly Email, Face-to-
face
communication
Summary
Based on the discussed aspects of the project, it could be concluded that with the
development of the SAP implementation project, it would be highly helpful for Yes Chemist
Pty Ltd. to ensure the benefits of the systems. This project discusses about the brief of the
implementation for the SAP systems within the organisation.
The project thus helps in discussing about the scheduled activities in relation with the
project. With the help of the SAP systems, the organisation would gain a high amount of
success. The project thus discusses about the risks occurred during the project and the
communication that need to be made during the project. Hence, from the discussion, it can
be concluded that the plans for implementation of the SAP system would be highly helpful
for Yes Chemist Pty Ltd.
.
VUIS Consulting Project Plan Page 8
[Insert Author name here]
Communication made Responsible person Frequency Mode of
Communication
Discussion of the project plan Project Manager Monthly Email, Face-to-
face
communication
Updating the financial plan Project Sponsor Weekly Face-to-face
communication
Developmental activities Software Developers Daily Face-to-face
communication
Updating test status Quality Assurance Testers Weekly Face-to-face
communication
Updating risk assessment
status
Project Manager Weekly Email, Face-to-
face
communication
Summary
Based on the discussed aspects of the project, it could be concluded that with the
development of the SAP implementation project, it would be highly helpful for Yes Chemist
Pty Ltd. to ensure the benefits of the systems. This project discusses about the brief of the
implementation for the SAP systems within the organisation.
The project thus helps in discussing about the scheduled activities in relation with the
project. With the help of the SAP systems, the organisation would gain a high amount of
success. The project thus discusses about the risks occurred during the project and the
communication that need to be made during the project. Hence, from the discussion, it can
be concluded that the plans for implementation of the SAP system would be highly helpful
for Yes Chemist Pty Ltd.
.
VUIS Consulting Project Plan Page 8
[Insert Author name here]
Bibliography
Alles, M., Brennan, G., Kogan, A., & Vasarhelyi, M. A. (2018). Continuous monitoring of
business process controls: A pilot implementation of a continuous auditing system at
Siemens. In Continuous Auditing: Theory and Application (pp. 219-246). Emerald Publishing
Limited.
Boillat, T., & Legner, C. (2014, July). Why do companies migrate towards cloud enterprise
systems? A post-implementation perspective. In 2014 IEEE 16th conference on business
informatics (Vol. 1, pp. 102-109). IEEE.
Esteves, J. M. (2014). An empirical identification and categorisation of training best practices
for ERP implementation projects. Enterprise Information Systems, 8(6), 665-683.
Ha, Y. M., & Ahn, H. J. (2014). Factors affecting the performance of Enterprise Resource
Planning (ERP) systems in the post-implementation stage. Behaviour & Information
Technology, 33(10), 1065-1081.
Heinzelmann, R. (2017). Accounting logics as a challenge for ERP system implementation:
A field study of SAP. Journal of Accounting & Organizational Change, 13(2), 162-187.
Kale, V. (2014). Implementing SAPĀ® CRM: The guide for business and technology
managers. Auerbach Publications.
Milan, R., Milan, B., Marko, C., Jovanovic, V., Dalibor, B., Bojic, Z., & Avramovic, N. (2014).
Implementation of business process reengineering in Human Resource
Management. Engineering Economics, 25(2), 211-222.
VUIS Consulting Project Plan Page 9
[Insert Author name here]
Alles, M., Brennan, G., Kogan, A., & Vasarhelyi, M. A. (2018). Continuous monitoring of
business process controls: A pilot implementation of a continuous auditing system at
Siemens. In Continuous Auditing: Theory and Application (pp. 219-246). Emerald Publishing
Limited.
Boillat, T., & Legner, C. (2014, July). Why do companies migrate towards cloud enterprise
systems? A post-implementation perspective. In 2014 IEEE 16th conference on business
informatics (Vol. 1, pp. 102-109). IEEE.
Esteves, J. M. (2014). An empirical identification and categorisation of training best practices
for ERP implementation projects. Enterprise Information Systems, 8(6), 665-683.
Ha, Y. M., & Ahn, H. J. (2014). Factors affecting the performance of Enterprise Resource
Planning (ERP) systems in the post-implementation stage. Behaviour & Information
Technology, 33(10), 1065-1081.
Heinzelmann, R. (2017). Accounting logics as a challenge for ERP system implementation:
A field study of SAP. Journal of Accounting & Organizational Change, 13(2), 162-187.
Kale, V. (2014). Implementing SAPĀ® CRM: The guide for business and technology
managers. Auerbach Publications.
Milan, R., Milan, B., Marko, C., Jovanovic, V., Dalibor, B., Bojic, Z., & Avramovic, N. (2014).
Implementation of business process reengineering in Human Resource
Management. Engineering Economics, 25(2), 211-222.
VUIS Consulting Project Plan Page 9
[Insert Author name here]
1 out of 9
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
Ā +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Ā© 2024 Ā | Ā Zucol Services PVT LTD Ā | Ā All rights reserved.