Managing a Successful Business Project on Workplace Transformation in Retail Industry
VerifiedAdded on  2023/06/10
|27
|5988
|119
AI Summary
This project management plan includes research aim and objectives, quality, deliverables, risk, communication resources along with the research methods for a successful business project on workplace transformation in retail industry.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Unit 6 Managing a
Successful Business
Project
(To identify the need of workplace
transformation in the digital age to
improve workforce satisfaction and
organisational performance within retail
industry)
Successful Business
Project
(To identify the need of workplace
transformation in the digital age to
improve workforce satisfaction and
organisational performance within retail
industry)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Contents
INTRODUCTION...........................................................................................................................1
MAIN BODY...................................................................................................................................1
PART 1............................................................................................................................................1
P1 Determining the different stages of Project Lifecycle along with its significance for the
success of project ........................................................................................................................1
P2 Identifying the factors which is required for complaining a project management plan.........2
P3 Analysing a extent of research strategies and methods as well as their significance in
project management.....................................................................................................................3
P4 Making a project management plan that includes research aim and objectives, quality,
deliverables, risk, communication resources along with the research methods..........................5
P5 Developing a work breakdown structure along with a schedule for providing stages and
time-frames to complete the project successfully........................................................................7
LOGBOOK......................................................................................................................................9
PART 2..........................................................................................................................................13
P6 Conducting a business project as stated within the PMP and communicating findings.......13
Frequency Distribution Table....................................................................................................13
Data Interpretation.....................................................................................................................14
P7 Presenting the data to draw a valid and meaningful conclusions and recommendation from
data analysis...............................................................................................................................19
P8 Reflect on the value of undertaking the business project to meet stated objectives and own
learning and performance..........................................................................................................19
REFERENCES..............................................................................................................................21
APPENDIX....................................................................................................................................23
Questionnaire.............................................................................................................................23
INTRODUCTION...........................................................................................................................1
MAIN BODY...................................................................................................................................1
PART 1............................................................................................................................................1
P1 Determining the different stages of Project Lifecycle along with its significance for the
success of project ........................................................................................................................1
P2 Identifying the factors which is required for complaining a project management plan.........2
P3 Analysing a extent of research strategies and methods as well as their significance in
project management.....................................................................................................................3
P4 Making a project management plan that includes research aim and objectives, quality,
deliverables, risk, communication resources along with the research methods..........................5
P5 Developing a work breakdown structure along with a schedule for providing stages and
time-frames to complete the project successfully........................................................................7
LOGBOOK......................................................................................................................................9
PART 2..........................................................................................................................................13
P6 Conducting a business project as stated within the PMP and communicating findings.......13
Frequency Distribution Table....................................................................................................13
Data Interpretation.....................................................................................................................14
P7 Presenting the data to draw a valid and meaningful conclusions and recommendation from
data analysis...............................................................................................................................19
P8 Reflect on the value of undertaking the business project to meet stated objectives and own
learning and performance..........................................................................................................19
REFERENCES..............................................................................................................................21
APPENDIX....................................................................................................................................23
Questionnaire.............................................................................................................................23
INTRODUCTION
Execution of the project in successful manner is essential for every project manager for
producing the effective outcome from it. It is important for project manager to design, arrange
and oversees the operation in better manner for accomplishing the desired objectives and
increasing the growth of the business (LONG, 2022). The current research is conducted to find
the need of workplace transformation in the digital age for improving their workforce
satisfaction as well as organisational performance. Selected organisation of the following
research is Next Plc, a multinational retail organisation of United Kingdom. The company is
focus on enhancing the experience as well as satisfaction level of their customers through their
effective products and service.
MAIN BODY
PART 1
P1 Determining the different stages of Project Lifecycle along with its significance for the
success of project
The project management lifecycle is used to describes the high level processes in order
to deliver a successful project. Effective project management help companies to get prevent from
the waste of money as well as resources because most of the unsuccessful projects fails due to
breakdown in communication (Galli, 2018). In the stage of the project management lifecycle, the
project manager come up with the idea for a project, defining its goals, conduct planning for its
execution as well as provide guidance for its completion. There mainly four stages within project
management lifecycle that are defined as initiation, planning, execution as well as closure. In
relation to current research project, these stages are described below:
Initiation- It refers to the first stage that project manager to identify the problem, need or
opportunity as well as insight ways that help team to meet this need, seize this opportunity or
solve this problem (Beagley, 2022). In this step, project manager need to identify the objective of
the project, determine its feasibility as well as deliverables for the project. The initiation stage is
considered as the important stage for the success of the project. The project proposal, RACI chart
and project charter are some tools which is used in this stage.
Planning- In this stage of project management life cycle, the project manager need to
break down the whole project into smaller tasks, develop an effective as well as prepare a
1
Execution of the project in successful manner is essential for every project manager for
producing the effective outcome from it. It is important for project manager to design, arrange
and oversees the operation in better manner for accomplishing the desired objectives and
increasing the growth of the business (LONG, 2022). The current research is conducted to find
the need of workplace transformation in the digital age for improving their workforce
satisfaction as well as organisational performance. Selected organisation of the following
research is Next Plc, a multinational retail organisation of United Kingdom. The company is
focus on enhancing the experience as well as satisfaction level of their customers through their
effective products and service.
MAIN BODY
PART 1
P1 Determining the different stages of Project Lifecycle along with its significance for the
success of project
The project management lifecycle is used to describes the high level processes in order
to deliver a successful project. Effective project management help companies to get prevent from
the waste of money as well as resources because most of the unsuccessful projects fails due to
breakdown in communication (Galli, 2018). In the stage of the project management lifecycle, the
project manager come up with the idea for a project, defining its goals, conduct planning for its
execution as well as provide guidance for its completion. There mainly four stages within project
management lifecycle that are defined as initiation, planning, execution as well as closure. In
relation to current research project, these stages are described below:
Initiation- It refers to the first stage that project manager to identify the problem, need or
opportunity as well as insight ways that help team to meet this need, seize this opportunity or
solve this problem (Beagley, 2022). In this step, project manager need to identify the objective of
the project, determine its feasibility as well as deliverables for the project. The initiation stage is
considered as the important stage for the success of the project. The project proposal, RACI chart
and project charter are some tools which is used in this stage.
Planning- In this stage of project management life cycle, the project manager need to
break down the whole project into smaller tasks, develop an effective as well as prepare a
1
schedule for the completion of assignments (Kim, Lee and Kim, 2020). By creating smaller goals
for the larger projects, project manager need to ensure that each goals should achieve within the
time-frame. Gantt chart and risk register are some tools that are used in this stage that helps in
making project successful.
Execution- This stage of project management lifecycle help project manager to convert
its project plan into action. In the stage, the project manager need to focus on that the all the
tasks are on track, team members are organised properly, timelines are managed as well as
ensure that the all the tasks are completed in accordance with original plan (Lin and Cheung,
2020). Change requests and Burn-down chart are some tools which may used by the project
manager in order to accomplish the whole project in better manner.
Closure- It refers to the final stage of project management lifecycle when all the tasks of
the project are completed then project enter in its closure stage. In the closure stage, the project
manager need to provide final deliverables, release project resources as well as determining the
success of the project (Klünder, Dörseln and Steven, 2019). The project manager also need to
evaluate what is going to be good and what wrong in the project in order to improved them for
the success of next project. In this stage, the Impact report and Project close out report are tools
which is used by the project manager in order to evaluate the project performance.
P2 Identifying the factors which is required for complaining a project management plan
Project management plan is a kind of approved and formal document that helps project
managers in order to define the monitor, execution as well as controlling of project (Rahman,
2020). While compiling the project management plan the project manager need to consider
certain factors that helps in making the project successful. It involves goals, scope, budget,
timelines and deliverables of a project. In relation to the current conducted research, factors that
are need to be considered for making it successful are described below:
Deliverables- It is used to describes how the large projects will be break down into
different measurable deliverables. It helps in clarifying the different project objectives along with
the activities which is required to complete the whole project (Roy, 2021). It is a most important
factors for project management plan as it allows project managers, clients and other stakeholders
to know about the progress make by the team.
Quality- It describe the factors that helps project manager to determine the ability of their
plan that provide success of the project. The project manager need to identify that what kind of
2
for the larger projects, project manager need to ensure that each goals should achieve within the
time-frame. Gantt chart and risk register are some tools that are used in this stage that helps in
making project successful.
Execution- This stage of project management lifecycle help project manager to convert
its project plan into action. In the stage, the project manager need to focus on that the all the
tasks are on track, team members are organised properly, timelines are managed as well as
ensure that the all the tasks are completed in accordance with original plan (Lin and Cheung,
2020). Change requests and Burn-down chart are some tools which may used by the project
manager in order to accomplish the whole project in better manner.
Closure- It refers to the final stage of project management lifecycle when all the tasks of
the project are completed then project enter in its closure stage. In the closure stage, the project
manager need to provide final deliverables, release project resources as well as determining the
success of the project (Klünder, Dörseln and Steven, 2019). The project manager also need to
evaluate what is going to be good and what wrong in the project in order to improved them for
the success of next project. In this stage, the Impact report and Project close out report are tools
which is used by the project manager in order to evaluate the project performance.
P2 Identifying the factors which is required for complaining a project management plan
Project management plan is a kind of approved and formal document that helps project
managers in order to define the monitor, execution as well as controlling of project (Rahman,
2020). While compiling the project management plan the project manager need to consider
certain factors that helps in making the project successful. It involves goals, scope, budget,
timelines and deliverables of a project. In relation to the current conducted research, factors that
are need to be considered for making it successful are described below:
Deliverables- It is used to describes how the large projects will be break down into
different measurable deliverables. It helps in clarifying the different project objectives along with
the activities which is required to complete the whole project (Roy, 2021). It is a most important
factors for project management plan as it allows project managers, clients and other stakeholders
to know about the progress make by the team.
Quality- It describe the factors that helps project manager to determine the ability of their
plan that provide success of the project. The project manager need to identify that what kind of
2
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
information is to gather for making the quality of project (Munyaneza, 2020). In case of current
research, the researcher identify that quantitative data and information is required to collect for
making it high quality.
Risk- It refers to the those factors that help project manager in order identify, address and
control issues that may occur while conducting the project. It is also important for completing the
project on time as well as making it successful (Tolla, 2020). In case of present research project,
there are many risk factors that create problem for the researcher in order to complete it in proper
many. It involves low cost, less time, insufficient resources as well as security risk.
Communication- It refers to a process through which project manager interact with the
stakeholders for the completion of the project (Ravelomanalina, 2020). There are many methods
through which project managers can communicate with their stakeholders in proper manner
such as survey, interview, emails and many more. In respect of current research project, survey
strategy and emails are used by the researcher to complete the whole research properly.
Resources- It refers to a thing which is to conduct the whole project in better manner.
There are many resources which can be used by the researcher to collect the information for the
following research such as books, journals and questionnaire (Ndayambaje, 2021). These
resources helps in attaining the aim and objectives of the research project in better manner.
P3 Analysing a extent of research strategies and methods as well as their significance in project
management
Research methodologies is describe the way that explain how a researcher intends to
conduct the research project in better manner. It can also be considered as systematic plan that
help in resolving the research problem in better manner (Hechter, 2019). The research onion is
an effective framework that classify the research methodology in different methods and
techniques in order to make easier for the researcher to complete the whole research in better
manner. In context of current research project, the methods and strategies are used to complete it
successfully are described below:
Research Approach- Inductive and deductive positivism research philosophyare two
types of research approach that helps in collecting and analysing the data for the research. The
researcher selected deductive research approach in the current research project as it helps in
gathering and examining the quantitative data related to research topic (Humble, 2020). The
3
research, the researcher identify that quantitative data and information is required to collect for
making it high quality.
Risk- It refers to the those factors that help project manager in order identify, address and
control issues that may occur while conducting the project. It is also important for completing the
project on time as well as making it successful (Tolla, 2020). In case of present research project,
there are many risk factors that create problem for the researcher in order to complete it in proper
many. It involves low cost, less time, insufficient resources as well as security risk.
Communication- It refers to a process through which project manager interact with the
stakeholders for the completion of the project (Ravelomanalina, 2020). There are many methods
through which project managers can communicate with their stakeholders in proper manner
such as survey, interview, emails and many more. In respect of current research project, survey
strategy and emails are used by the researcher to complete the whole research properly.
Resources- It refers to a thing which is to conduct the whole project in better manner.
There are many resources which can be used by the researcher to collect the information for the
following research such as books, journals and questionnaire (Ndayambaje, 2021). These
resources helps in attaining the aim and objectives of the research project in better manner.
P3 Analysing a extent of research strategies and methods as well as their significance in project
management
Research methodologies is describe the way that explain how a researcher intends to
conduct the research project in better manner. It can also be considered as systematic plan that
help in resolving the research problem in better manner (Hechter, 2019). The research onion is
an effective framework that classify the research methodology in different methods and
techniques in order to make easier for the researcher to complete the whole research in better
manner. In context of current research project, the methods and strategies are used to complete it
successfully are described below:
Research Approach- Inductive and deductive positivism research philosophyare two
types of research approach that helps in collecting and analysing the data for the research. The
researcher selected deductive research approach in the current research project as it helps in
gathering and examining the quantitative data related to research topic (Humble, 2020). The
3
primary motive for the selection of this research topic is it allows researcher to use their logic to
justify work related decision in the research.
Research philosophy- It is classified in two parts that are defined as interpretivism and
positivism. In context of present research project, positivism research philosophy is used as it
helps researcher to take large scale surveys for getting an overview about the whole society as
well as uncover the social trends (Zhang, 2019). The primary reason for the selection of this
research philosophy is to obtain accurate and reliable information related to the research topic.
Research Strategy- Different kinds of research strategies are available in research
methodology like case study, action research, survey, interview, observation and many more.
Survey research strategy has been selected by the researcher in order to collect large amount of
information from the large population (Conway, 2019). This main motive for the selection of this
research strategy is it is an convenient method in order to collect data for the research.
Research choice- Qualitative and quantitative are two major form of research choice that
helps in collecting and analysing the specific kind of information. Quantitative research choice is
used by the researcher for collecting and analysing the numerical information related to the
research topic (Patel, Shah and Shah, 2020). The primary reason for the selection of this research
choice to attain greater knowledge and understanding related to the social world for conducting
the research in well manner.
Time horizon- It is classified in two parts that are defined as longitudinal and cross-
sectional time horizon. In case of current research project, cross-sectional time horizon is
selected in order to conduct the whole research in less time (Facchin, Buggio and Saita, 2020).
The main motive for the selection of this research topic is it helps in comparing the many
different variables in similar time.
Data collection- It is classified in two categories that are primary and secondary data
collection method. Both the data collection methods used in current research project as it helps
in collecting information directly from the participants along with the several sources (Liang,
Leung and Ahmed, 2021). The primary reason for the selection of these data collection method is
it is a cost and time effective method that helps researcher to gain reliable information related to
the research topic.
Data analysis- Different kind of data analysis methods are available in research
methodology such as thematic, frequency distribution , etc. The researcher selected frequency
4
justify work related decision in the research.
Research philosophy- It is classified in two parts that are defined as interpretivism and
positivism. In context of present research project, positivism research philosophy is used as it
helps researcher to take large scale surveys for getting an overview about the whole society as
well as uncover the social trends (Zhang, 2019). The primary reason for the selection of this
research philosophy is to obtain accurate and reliable information related to the research topic.
Research Strategy- Different kinds of research strategies are available in research
methodology like case study, action research, survey, interview, observation and many more.
Survey research strategy has been selected by the researcher in order to collect large amount of
information from the large population (Conway, 2019). This main motive for the selection of this
research strategy is it is an convenient method in order to collect data for the research.
Research choice- Qualitative and quantitative are two major form of research choice that
helps in collecting and analysing the specific kind of information. Quantitative research choice is
used by the researcher for collecting and analysing the numerical information related to the
research topic (Patel, Shah and Shah, 2020). The primary reason for the selection of this research
choice to attain greater knowledge and understanding related to the social world for conducting
the research in well manner.
Time horizon- It is classified in two parts that are defined as longitudinal and cross-
sectional time horizon. In case of current research project, cross-sectional time horizon is
selected in order to conduct the whole research in less time (Facchin, Buggio and Saita, 2020).
The main motive for the selection of this research topic is it helps in comparing the many
different variables in similar time.
Data collection- It is classified in two categories that are primary and secondary data
collection method. Both the data collection methods used in current research project as it helps
in collecting information directly from the participants along with the several sources (Liang,
Leung and Ahmed, 2021). The primary reason for the selection of these data collection method is
it is a cost and time effective method that helps researcher to gain reliable information related to
the research topic.
Data analysis- Different kind of data analysis methods are available in research
methodology such as thematic, frequency distribution , etc. The researcher selected frequency
4
distribution data analysis techniques in order to calculate and evaluate numerical information
related to the research topic (Hou and Wen, 2020). The basic reason for the selection of this
research is it helps in summarizing and organising the raw data in tabular format.
Sampling- Probability and non-probability are two kinds of sampling methods that helps
in selecting samples from the large population. In context of current conducted research,
probability sampling used for collecting the information from the equal number of respondents.
In the following research researcher selects 30 respondents through random sampling (Ahmed,
and Ali, 2022).
P4 Making a project management plan that includes research aim and objectives, quality,
deliverables, risk, communication resources along with the research methods
Research Aim:
To identify the need of workplace transformation in the digital age to improve workforce
satisfaction and organisational performance. “A study on Next Plc”
Research Objectives:
ď‚· To develop understanding and need of workplace transformation within retail industry
ď‚· To investigate the advanced technologies of workplace transformation used by Next Plc
for employees to carry out their roles and collaborate
ď‚· To examine the impact of workplace transformation on workforce satisfaction and
organisational performance within Next Plc
Research Questions:
ď‚· Explain the concept and need of workplace transformation within retail industry?
ď‚· What are the advanced technologies of workplace transformation used by Next Plc for
employees to carry out their roles and collaborate?
ď‚· What is the impact of workplace transformation on workforce satisfaction and
organisational performance within Next Plc?
Deliverables:
5
related to the research topic (Hou and Wen, 2020). The basic reason for the selection of this
research is it helps in summarizing and organising the raw data in tabular format.
Sampling- Probability and non-probability are two kinds of sampling methods that helps
in selecting samples from the large population. In context of current conducted research,
probability sampling used for collecting the information from the equal number of respondents.
In the following research researcher selects 30 respondents through random sampling (Ahmed,
and Ali, 2022).
P4 Making a project management plan that includes research aim and objectives, quality,
deliverables, risk, communication resources along with the research methods
Research Aim:
To identify the need of workplace transformation in the digital age to improve workforce
satisfaction and organisational performance. “A study on Next Plc”
Research Objectives:
ď‚· To develop understanding and need of workplace transformation within retail industry
ď‚· To investigate the advanced technologies of workplace transformation used by Next Plc
for employees to carry out their roles and collaborate
ď‚· To examine the impact of workplace transformation on workforce satisfaction and
organisational performance within Next Plc
Research Questions:
ď‚· Explain the concept and need of workplace transformation within retail industry?
ď‚· What are the advanced technologies of workplace transformation used by Next Plc for
employees to carry out their roles and collaborate?
ď‚· What is the impact of workplace transformation on workforce satisfaction and
organisational performance within Next Plc?
Deliverables:
5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
The deliverables allows researcher in order to classify the whole project into several tasks
along with the various measurable variables. In case of current research project, the whole
research projects is divide in different tasks and each tasks is allotted in different measurable
deliverable within 28 weeks (Rasoarimalalanarivo, 2020). The different tasks of the whole
research projects involves introduction, aims and objectives, literature review, research
methodology, data collection, data analysis, conclusion and recommendation, reflection as well
as submission of the final report.
Quality:
In case of current conducted research, the quality of the research is very high as the
researcher collects data and information through quantitative research methods as it helps in
making the whole research more reliable and valuable (Kibangula, 2020). It helps in making the
whole research project successful. The researcher collected information by directly asking
questions from the respondents that helps researcher to collect accurate and up-to-date
information for the research. It also helps in making the quality of the research project high to
make it successful.
Risk:
The researcher need to identify the risk along with the method to mitigate it in order to
make the whole project successful. In context of current research, there are many risk factors that
create problem for the researcher in order to complete the whole research in successful manner.
Low cost is one of the risk in the current research project and the respondents used questionnaire
in order to collects information in less cost (de Oliveira, 2021). Time is another risk where the
researcher used Gantt Chart to mitigate limited time risk. Limited resources are also a risk for the
researcher where the researcher collected information the different sources such as books,
journals and scholarly articles. Security risk is another risk that create problem for the researcher
to complete the research properly. By protecting privacy and confidentiality of the respondents
the researcher mitigate security risk.
Resources:
The researcher uses different resources to collect valuable information and data for the
current research project (El Kabbag, 2019). It involves questionnaire, books, journal, scholarly
6
along with the various measurable variables. In case of current research project, the whole
research projects is divide in different tasks and each tasks is allotted in different measurable
deliverable within 28 weeks (Rasoarimalalanarivo, 2020). The different tasks of the whole
research projects involves introduction, aims and objectives, literature review, research
methodology, data collection, data analysis, conclusion and recommendation, reflection as well
as submission of the final report.
Quality:
In case of current conducted research, the quality of the research is very high as the
researcher collects data and information through quantitative research methods as it helps in
making the whole research more reliable and valuable (Kibangula, 2020). It helps in making the
whole research project successful. The researcher collected information by directly asking
questions from the respondents that helps researcher to collect accurate and up-to-date
information for the research. It also helps in making the quality of the research project high to
make it successful.
Risk:
The researcher need to identify the risk along with the method to mitigate it in order to
make the whole project successful. In context of current research, there are many risk factors that
create problem for the researcher in order to complete the whole research in successful manner.
Low cost is one of the risk in the current research project and the respondents used questionnaire
in order to collects information in less cost (de Oliveira, 2021). Time is another risk where the
researcher used Gantt Chart to mitigate limited time risk. Limited resources are also a risk for the
researcher where the researcher collected information the different sources such as books,
journals and scholarly articles. Security risk is another risk that create problem for the researcher
to complete the research properly. By protecting privacy and confidentiality of the respondents
the researcher mitigate security risk.
Resources:
The researcher uses different resources to collect valuable information and data for the
current research project (El Kabbag, 2019). It involves questionnaire, books, journal, scholarly
6
articles and many more. These resources are helpful in making whole research project
successful.
Research methods
It refers to the method or techniques which is used to complete the whole research project
in better manner. In context of present research project, the researcher uses quantitative research
methods as it allows them to collect numerical information about the facts and figures of
research topic in effective manner (Mohamoud, 2019).
P5 Developing a work breakdown structure along with a schedule for providing stages and time-
frames to complete the project successfully
Work breakdown structure is described the project management tool that involves step-
by-step approach in order to complete the large projects through several moving pieces. In
context of current research project, Gantt chart is used in order to breakdown and schedule the
whole research project for providing different stages and time-frames. Gantt chart is mainly
described the project management tool that help project manager to analyse the schedule
planning of different project tasks (Joshi and Goyal, 2019). It is display in the form of bar chart
that helps in illustrating the schedule of the research project. It provides graphical illustration of
project schedules that help project managers in order to make a plan, analyse as well as
coordinate the task in better manner. Gantt chart makes the things easier and simpler that help
researcher in orders to complete the research project successfully.
7
successful.
Research methods
It refers to the method or techniques which is used to complete the whole research project
in better manner. In context of present research project, the researcher uses quantitative research
methods as it allows them to collect numerical information about the facts and figures of
research topic in effective manner (Mohamoud, 2019).
P5 Developing a work breakdown structure along with a schedule for providing stages and time-
frames to complete the project successfully
Work breakdown structure is described the project management tool that involves step-
by-step approach in order to complete the large projects through several moving pieces. In
context of current research project, Gantt chart is used in order to breakdown and schedule the
whole research project for providing different stages and time-frames. Gantt chart is mainly
described the project management tool that help project manager to analyse the schedule
planning of different project tasks (Joshi and Goyal, 2019). It is display in the form of bar chart
that helps in illustrating the schedule of the research project. It provides graphical illustration of
project schedules that help project managers in order to make a plan, analyse as well as
coordinate the task in better manner. Gantt chart makes the things easier and simpler that help
researcher in orders to complete the research project successfully.
7
8
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
LOGBOOK
9
9
Project Log Book
Project Logbook For MSBP
Learning Week No: (Project Week no. )
Date:
No. Planned Activities Action Plan
1 Update your last week’s work Data Collection and Data Analysis
2 Problem encountered and how did you
handle the problem?
Points to consider:
What barriers did you face?
Time management
How did you overcome them?
By using Gantt chart
3 Task for this week What have I learnt about myself this
week?
Points to consider:
How did you feel when you had to deal with
tasks/problems? Did you find it useful to
complete the tasks?
I am get frustrated in order to deal with
the tasks or problems. Yes I found that it
is useful to complete the tasks.
How well have you perform? What did you
contribute? What can you improve on next
week?
According to my opinion I perform very
well. I have collected in-depth
information about the research topic. I
can improve time management on next
week.
10
Project Logbook For MSBP
Learning Week No: (Project Week no. )
Date:
No. Planned Activities Action Plan
1 Update your last week’s work Data Collection and Data Analysis
2 Problem encountered and how did you
handle the problem?
Points to consider:
What barriers did you face?
Time management
How did you overcome them?
By using Gantt chart
3 Task for this week What have I learnt about myself this
week?
Points to consider:
How did you feel when you had to deal with
tasks/problems? Did you find it useful to
complete the tasks?
I am get frustrated in order to deal with
the tasks or problems. Yes I found that it
is useful to complete the tasks.
How well have you perform? What did you
contribute? What can you improve on next
week?
According to my opinion I perform very
well. I have collected in-depth
information about the research topic. I
can improve time management on next
week.
10
How might this learning apply in the future?
By completing given tasks on time, I will
apply my this learning in the future.
4 Risk issues identified. Points to consider:
Did you identify risks/issues with a lack of
skills required for undertaking
research/tasks?
Yes, I found risks with a lack of skilled is
that I faced problem of in complete
research.
was there any project issue which were
highlighted in front of you while you're
performing the project management plan?
No
5 Plan your tasks for next week Points to consider:
Which tasks are priorities?
Data Collection and interpretation
Have you set aside adequate time for pass
completion?
Yes
6 Project plan status till date (on/ahead /
behind)
If behind, why?
Till now, I have completed my all tasks on
time. And I already conduct my data
analyses and findings.
7 Remarks by the lecturer if any
Student Full Name, Registration No.
11
By completing given tasks on time, I will
apply my this learning in the future.
4 Risk issues identified. Points to consider:
Did you identify risks/issues with a lack of
skills required for undertaking
research/tasks?
Yes, I found risks with a lack of skilled is
that I faced problem of in complete
research.
was there any project issue which were
highlighted in front of you while you're
performing the project management plan?
No
5 Plan your tasks for next week Points to consider:
Which tasks are priorities?
Data Collection and interpretation
Have you set aside adequate time for pass
completion?
Yes
6 Project plan status till date (on/ahead /
behind)
If behind, why?
Till now, I have completed my all tasks on
time. And I already conduct my data
analyses and findings.
7 Remarks by the lecturer if any
Student Full Name, Registration No.
11
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Student Signature and Date
Lecturer’s Name, Signature, and Date
12
Lecturer’s Name, Signature, and Date
12
PART 2
P6 Conducting a business project as stated within the PMP and communicating findings
Frequency Distribution Table
Q1) Do you think workplace transformation is necessary in this
digital world?
Frequency
a) Yes 25
b) No 5
Q2) As per your opinion, what is the requirement of workplace
transformation within retail industry?
Frequency
a) To make workforce work independently 4
b) To reskill and build the apt talent pool 6
c) To build new business model expertise 8
d) To increase social interaction and collaboration 5
e) To integrate several business dimensions systematically 7
Q3) According to your knowledge, which advanced technology is
the best adopted by Next Plc for employees to carry out their roles
and collaborate?
Frequency
a) Chatbots 6
b) Virtual assistants 8
c) IoT 5
d) Sentiment analysis 7
e) Data analytics 4
Q4) As per your knowledge, what is the impact of workplace
transformation on workforce satisfaction within Next PLc?
Frequency
a) Positive impact 21
13
P6 Conducting a business project as stated within the PMP and communicating findings
Frequency Distribution Table
Q1) Do you think workplace transformation is necessary in this
digital world?
Frequency
a) Yes 25
b) No 5
Q2) As per your opinion, what is the requirement of workplace
transformation within retail industry?
Frequency
a) To make workforce work independently 4
b) To reskill and build the apt talent pool 6
c) To build new business model expertise 8
d) To increase social interaction and collaboration 5
e) To integrate several business dimensions systematically 7
Q3) According to your knowledge, which advanced technology is
the best adopted by Next Plc for employees to carry out their roles
and collaborate?
Frequency
a) Chatbots 6
b) Virtual assistants 8
c) IoT 5
d) Sentiment analysis 7
e) Data analytics 4
Q4) As per your knowledge, what is the impact of workplace
transformation on workforce satisfaction within Next PLc?
Frequency
a) Positive impact 21
13
b) Negative impact 5
c) Neutral impact 4
Q5) What is the major benefit experienced by Next Plc through
workplace transformation on organisational performance?
Frequency
a) Empowered and encouraged employees 5
b) Better communication and collaboration 7
c) Recruitment of top candidates 9
d) Increased flexibility 4
e) Decreased operational costs 5
Data Interpretation
Table 1: Workplace transformation is necessary in this digital world
Q1) Do you think workplace transformation is necessary in this
digital world?
Frequency
a) Yes 25
b) No 5
14
c) Neutral impact 4
Q5) What is the major benefit experienced by Next Plc through
workplace transformation on organisational performance?
Frequency
a) Empowered and encouraged employees 5
b) Better communication and collaboration 7
c) Recruitment of top candidates 9
d) Increased flexibility 4
e) Decreased operational costs 5
Data Interpretation
Table 1: Workplace transformation is necessary in this digital world
Q1) Do you think workplace transformation is necessary in this
digital world?
Frequency
a) Yes 25
b) No 5
14
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
a) Yes b) No
0
5
10
15
20
25
25
5
Figure 1: Workplace transformation is necessary in this digital world
Interpretation: As per the above assembled information, it is carried out that 25 respondents
have given response yes that workplace transformation is necessary in this digital world because
it helps in transforming the whole organisation in such a way that employees get satisfied and
operations could be improved. The rest 5 respondents have answered no that workplace
transformation is not necessary in this digital world because there are many other elements which
hold more importance in the organisation.
Table 2: Requirement of workplace transformation within retail industry
Q2) As per your opinion, what is the requirement of workplace
transformation within retail industry?
Frequency
a) To make workforce work independently 4
b) To reskill and build the apt talent pool 6
c) To build new business model expertise 8
d) To increase social interaction and collaboration 5
e) To integrate several business dimensions systematically 7
15
0
5
10
15
20
25
25
5
Figure 1: Workplace transformation is necessary in this digital world
Interpretation: As per the above assembled information, it is carried out that 25 respondents
have given response yes that workplace transformation is necessary in this digital world because
it helps in transforming the whole organisation in such a way that employees get satisfied and
operations could be improved. The rest 5 respondents have answered no that workplace
transformation is not necessary in this digital world because there are many other elements which
hold more importance in the organisation.
Table 2: Requirement of workplace transformation within retail industry
Q2) As per your opinion, what is the requirement of workplace
transformation within retail industry?
Frequency
a) To make workforce work independently 4
b) To reskill and build the apt talent pool 6
c) To build new business model expertise 8
d) To increase social interaction and collaboration 5
e) To integrate several business dimensions systematically 7
15
0
2
4
6
8
4
6
8
5
7
Figure 2: Requirement of workplace transformation within retail industry
Interpretation: According to the given data, it is observed that 8 participants have answered that
building new business model expertise is the major requirement of workplace transformation
within retail industry because it assists in operating with the model that can yield more profit and
revenue. Another 7 participants have answered that integrating several business dimensions
systematically is the other need of workplace transformation because it makes each department
to work in the same direction. Another 6 participants have said that reskilling and building the
apt talent pool is another need to adopt strategies of workplace transformation.
Table 3: Advanced technology is the best adopted by Next Plc for employees to carry out their
roles and collaborate
Q3) According to your knowledge, which advanced technology is
the best adopted by Next Plc for employees to carry out their roles
and collaborate?
Frequency
a) Chatbots 6
b) Virtual assistants 8
c) IoT 5
16
2
4
6
8
4
6
8
5
7
Figure 2: Requirement of workplace transformation within retail industry
Interpretation: According to the given data, it is observed that 8 participants have answered that
building new business model expertise is the major requirement of workplace transformation
within retail industry because it assists in operating with the model that can yield more profit and
revenue. Another 7 participants have answered that integrating several business dimensions
systematically is the other need of workplace transformation because it makes each department
to work in the same direction. Another 6 participants have said that reskilling and building the
apt talent pool is another need to adopt strategies of workplace transformation.
Table 3: Advanced technology is the best adopted by Next Plc for employees to carry out their
roles and collaborate
Q3) According to your knowledge, which advanced technology is
the best adopted by Next Plc for employees to carry out their roles
and collaborate?
Frequency
a) Chatbots 6
b) Virtual assistants 8
c) IoT 5
16
d) Sentiment analysis 7
e) Data analytics 4
a) Chatbots
b) Virtual assistants
c) IoT
d) Sentiment analysis
e) Data analytics
0
1
2
3
4
5
6
7
8
6
8
5
7
4
Figure 3: Advanced technology is the best adopted by Next Plc for employees to carry out
their roles and collaborate
Interpretation: With the above gathered data, it is evaluated that virtual assistants is the
advanced technology which is mainly adopted by Next Plc for employees to carry out their roles
and collaborate. Virtual assistants provide great help to the employees so that they easily perform
their roles and collaborate with other employees of the organisation.
Table 4: Impact of workplace transformation on workforce satisfaction
Q4) As per your knowledge, what is the impact of workplace
transformation on workforce satisfaction within Next PLc?
Frequency
a) Positive impact 21
b) Negative impact 5
17
e) Data analytics 4
a) Chatbots
b) Virtual assistants
c) IoT
d) Sentiment analysis
e) Data analytics
0
1
2
3
4
5
6
7
8
6
8
5
7
4
Figure 3: Advanced technology is the best adopted by Next Plc for employees to carry out
their roles and collaborate
Interpretation: With the above gathered data, it is evaluated that virtual assistants is the
advanced technology which is mainly adopted by Next Plc for employees to carry out their roles
and collaborate. Virtual assistants provide great help to the employees so that they easily perform
their roles and collaborate with other employees of the organisation.
Table 4: Impact of workplace transformation on workforce satisfaction
Q4) As per your knowledge, what is the impact of workplace
transformation on workforce satisfaction within Next PLc?
Frequency
a) Positive impact 21
b) Negative impact 5
17
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
c) Neutral impact 4
a) Positive impact b) Negative impact c) Neutral impact
0
5
10
15
20
25
21
5 4
Figure 4: Impact of workplace transformation on workforce satisfaction
Interpretation: As per the above assembled information, it is analysed that 21 respondents have
answered that there is positive impact of workplace transformation on workforce satisfaction
within Next Plc. There is positive impact because it allows employees to work with greater
efficiency with the help of advanced technology. The other 5 respondents have said that there is
negative impact of workplace transformation on the satisfaction of workforce because some
employee resist the process of transforming the workplace. The rest 4 participants have said that
there is neutral impact of workplace transformation because it has not created any additional
benefits.
Table 5: Benefit experienced by Next Plc through workplace transformation on organisational
performance
Q5) What is the major benefit experienced by Next Plc through
workplace transformation on organisational performance?
Frequency
a) Empowered and encouraged employees 5
b) Better communication and collaboration 7
18
a) Positive impact b) Negative impact c) Neutral impact
0
5
10
15
20
25
21
5 4
Figure 4: Impact of workplace transformation on workforce satisfaction
Interpretation: As per the above assembled information, it is analysed that 21 respondents have
answered that there is positive impact of workplace transformation on workforce satisfaction
within Next Plc. There is positive impact because it allows employees to work with greater
efficiency with the help of advanced technology. The other 5 respondents have said that there is
negative impact of workplace transformation on the satisfaction of workforce because some
employee resist the process of transforming the workplace. The rest 4 participants have said that
there is neutral impact of workplace transformation because it has not created any additional
benefits.
Table 5: Benefit experienced by Next Plc through workplace transformation on organisational
performance
Q5) What is the major benefit experienced by Next Plc through
workplace transformation on organisational performance?
Frequency
a) Empowered and encouraged employees 5
b) Better communication and collaboration 7
18
c) Recruitment of top candidates 9
d) Increased flexibility 4
e) Decreased operational costs 5
0
2
4
6
8
5
7
9
4 5
Figure 5: Benefit experienced by Next Plc through workplace transformation on
organisational performance
Interpretation: As per the above collected information, it is determined that 9 respondents have
answered that recruiting top candidates is the major benefit experienced by the company through
workplace transformation on organisational performance. It is understood that with this they get
employees who are talented and skilled.
P7 Presenting the data to draw a valid and meaningful conclusions and recommendation from
data analysis
Conclusion
From the above discussion, it has been analysed that workplace transformation in the
digital age plays a very important for improving the workforce satisfaction as well as
19
d) Increased flexibility 4
e) Decreased operational costs 5
0
2
4
6
8
5
7
9
4 5
Figure 5: Benefit experienced by Next Plc through workplace transformation on
organisational performance
Interpretation: As per the above collected information, it is determined that 9 respondents have
answered that recruiting top candidates is the major benefit experienced by the company through
workplace transformation on organisational performance. It is understood that with this they get
employees who are talented and skilled.
P7 Presenting the data to draw a valid and meaningful conclusions and recommendation from
data analysis
Conclusion
From the above discussion, it has been analysed that workplace transformation in the
digital age plays a very important for improving the workforce satisfaction as well as
19
organisational performance in order to achieve the organisational goals and objectives in
effective manner. There are many factors that shows that workplace transformation within an
organisation is necessary. It involve making workforce work independently, building new
business model expertise, reskilling and building the apt talent pool, integrating several business
dimensions systematically as well as increasing social interaction and collaboration. It is
important for the company to adopt advanced technology that helps their employees to carry out
their roles and collaborate in better manner. Chatbots, IoT, Data analytics, virtual assistants, as
well as sentiment analysis are some advanced technologies that help company to transforms their
workplace. The research analysed that workplace transformation provide positive impact on
workforce satisfaction. There are many benefits that an organisation gain through workplace
transformation such as better communication and collaboration, empowered and encouraged
employees, increased flexibility, recruitment of top candidates as well as decreased operational
costs.
Recommendation
From the above analysis, it has been analysed that workplace transformation is necessary
for improving the organisation performance and workforce satisfaction. It is recommended to
Next Plc to focus on providing proper learning and training sessions for their employees that
help in improving their skills and knowledge that helps them to give their best efforts in their
performance. It helps company to achieve their organisational goals and objectives in effective
manner. The learning and training programs helps in providing the opportunity to employees in
order to learn something new as well as create within the workplace.
P8 Reflect on the value of undertaking the business project to meet stated objectives and own
learning and performance.
I am thankful that I got learning opportunity through conducting an investigation. With
the help of conducting current investigation I have learnt that workplace transformation is one of
the concepts that assist an organisation to make changes in the atmosphere of the company as per
the changes taking place in the external environment. I have understood that it is necessary to
have patience while doing any work because it helps in facing any challenge without any
difficulty or frustration. I have also learnt that an organisation uses several types of advanced
technology to transform the workplace such as using online communication channels for
interacting and communicating with the higher authorities as well as other employees. I have
20
effective manner. There are many factors that shows that workplace transformation within an
organisation is necessary. It involve making workforce work independently, building new
business model expertise, reskilling and building the apt talent pool, integrating several business
dimensions systematically as well as increasing social interaction and collaboration. It is
important for the company to adopt advanced technology that helps their employees to carry out
their roles and collaborate in better manner. Chatbots, IoT, Data analytics, virtual assistants, as
well as sentiment analysis are some advanced technologies that help company to transforms their
workplace. The research analysed that workplace transformation provide positive impact on
workforce satisfaction. There are many benefits that an organisation gain through workplace
transformation such as better communication and collaboration, empowered and encouraged
employees, increased flexibility, recruitment of top candidates as well as decreased operational
costs.
Recommendation
From the above analysis, it has been analysed that workplace transformation is necessary
for improving the organisation performance and workforce satisfaction. It is recommended to
Next Plc to focus on providing proper learning and training sessions for their employees that
help in improving their skills and knowledge that helps them to give their best efforts in their
performance. It helps company to achieve their organisational goals and objectives in effective
manner. The learning and training programs helps in providing the opportunity to employees in
order to learn something new as well as create within the workplace.
P8 Reflect on the value of undertaking the business project to meet stated objectives and own
learning and performance.
I am thankful that I got learning opportunity through conducting an investigation. With
the help of conducting current investigation I have learnt that workplace transformation is one of
the concepts that assist an organisation to make changes in the atmosphere of the company as per
the changes taking place in the external environment. I have understood that it is necessary to
have patience while doing any work because it helps in facing any challenge without any
difficulty or frustration. I have also learnt that an organisation uses several types of advanced
technology to transform the workplace such as using online communication channels for
interacting and communicating with the higher authorities as well as other employees. I have
20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
taken assistance of several research methods to record and analyse information. I have taken help
of quantitative research methods because they helped in the accumulation of numerical and
statistical piece of information. With the assistance of numerical information I have got the
results which can be easily compared and measured. With the current study, I have determined
my certain strengths and weaknesses. The major strength which is identified by me is that I am
great in communication skill and I was able to assemble great piece of information from the
respondents due to my great interaction skills. The other important strength carried out by me is
that I am great at solving problems. I learn about the in-depth of problem and all the possible
alternatives to solve the issue. The weakness identified by me in the current study is that I am not
great at working as per the defined time duration.
21
of quantitative research methods because they helped in the accumulation of numerical and
statistical piece of information. With the assistance of numerical information I have got the
results which can be easily compared and measured. With the current study, I have determined
my certain strengths and weaknesses. The major strength which is identified by me is that I am
great in communication skill and I was able to assemble great piece of information from the
respondents due to my great interaction skills. The other important strength carried out by me is
that I am great at solving problems. I learn about the in-depth of problem and all the possible
alternatives to solve the issue. The weakness identified by me in the current study is that I am not
great at working as per the defined time duration.
21
REFERENCES
Books and Journals:
Galli, B.J., 2018. Can project management help improve lean six sigma?. IEEE Engineering
Management Review, 46(2), pp.55-64.
Beagley, B., 2022. A Lifecycle Approach to Operation and Maintenance on the Toowoomba
Second Range Crossing Project.
Kim, K., Lee, G. and Kim, S., 2020. A study on the application of blockchain technology in the
construction industry. KSCE journal of civil engineering, 24(9), pp.2561-2571.
Lin, Y.C. and Cheung, W.F., 2020. Developing WSN/BIM-based environmental monitoring
management system for parking garages in smart cities. Journal of Management in
Engineering, 36(3), p.04020012.
Klünder, T., Dörseln, J.N. and Steven, M., 2019. Managing Uncertainties in the Project 4.0
Lifecycle. In Agile Approaches for Successfully Managing and Executing Projects in the
Fourth Industrial Revolution (pp. 119-140). IGI Global.
LONG, B., 2022. FIRE SAFETY MANAGEMENT PLAN FOR SOUTH TEXAS PROJECT
TURBINE GENERATOR BUILDING.
Rahman, M., 2020. Bangladesh-SOUTH ASIA-P128276-Coastal Embankment Improvement
Project-Phase I (CEIP-I)-Procurement Plan.
Roy, G., 2021. Bangladesh-SOUTH ASIA-P161996-Sustainable Forests and Livelihoods
(SUFAL) Project-Procurement Plan.
Munyaneza, G., 2020. Rwanda-AFRICA EAST-P150844-Rwanda Urban Development Project-
Procurement Plan.
Tolla, L., 2020. Ethiopia-AFRICA EAST-P157716-Promoting young women? s livelihoods and
nutrition project-Procurement Plan.
Ravelomanalina, R.M., 2020. Madagascar-AFRICA-P159756-Integrated Urban Development
and Resilience Project for Greater Antananarivo-Procurement Plan.
Ndayambaje, A., 2021. Burundi-AFRICA EAST-P169315-Burundi Integrated Community
Development Project-Procurement Plan.
Rasoarimalalanarivo, S., 2020. Madagascar-AFRICA-P159756-Integrated Urban Development
and Resilience Project for Greater Antananarivo-Procurement Plan.
Kibangula, A.A., 2020. Eastern Africa-AFRICA EAST-P143307-AFR RI-Regional Great Lakes
Integrated Agriculture Development Project-Procurement Plan.
de Oliveira, F.C.C., 2021. Brazil-LATIN AMERICA AND CARIBBEAN-P147157-BRAZIL
BAHIA SUSTAINABLE RURAL DEVELOPMENT PROJECT-Procurement Plan.
El Kabbag, N.N.R., 2019. Egypt, Arab Republic of-MIDDLE EAST AND NORTH AFRICA-
P145699-Strengthening Social Safety Net Project-Procurement Plan.
Mohamoud, F.A., 2019. Somalia-AFRICA-P154875-Somalia Recurrent Cost and Reform
Financing Project-Phase 2-Procurement Plan.
Ahmed, A. and Ali, S., 2022. Lessons learned from adapting a quantitative to an emergent mixed
methods research design in Pakistan during COVID-19. International Journal of
Research & Method in Education, pp.1-17.
Liang, Q., Leung, M.Y. and Ahmed, K., 2021. How adoption of coping behaviors determines
construction workers’ safety: A quantitative and qualitative investigation. Safety
Science, 133, p.105035.
22
Books and Journals:
Galli, B.J., 2018. Can project management help improve lean six sigma?. IEEE Engineering
Management Review, 46(2), pp.55-64.
Beagley, B., 2022. A Lifecycle Approach to Operation and Maintenance on the Toowoomba
Second Range Crossing Project.
Kim, K., Lee, G. and Kim, S., 2020. A study on the application of blockchain technology in the
construction industry. KSCE journal of civil engineering, 24(9), pp.2561-2571.
Lin, Y.C. and Cheung, W.F., 2020. Developing WSN/BIM-based environmental monitoring
management system for parking garages in smart cities. Journal of Management in
Engineering, 36(3), p.04020012.
Klünder, T., Dörseln, J.N. and Steven, M., 2019. Managing Uncertainties in the Project 4.0
Lifecycle. In Agile Approaches for Successfully Managing and Executing Projects in the
Fourth Industrial Revolution (pp. 119-140). IGI Global.
LONG, B., 2022. FIRE SAFETY MANAGEMENT PLAN FOR SOUTH TEXAS PROJECT
TURBINE GENERATOR BUILDING.
Rahman, M., 2020. Bangladesh-SOUTH ASIA-P128276-Coastal Embankment Improvement
Project-Phase I (CEIP-I)-Procurement Plan.
Roy, G., 2021. Bangladesh-SOUTH ASIA-P161996-Sustainable Forests and Livelihoods
(SUFAL) Project-Procurement Plan.
Munyaneza, G., 2020. Rwanda-AFRICA EAST-P150844-Rwanda Urban Development Project-
Procurement Plan.
Tolla, L., 2020. Ethiopia-AFRICA EAST-P157716-Promoting young women? s livelihoods and
nutrition project-Procurement Plan.
Ravelomanalina, R.M., 2020. Madagascar-AFRICA-P159756-Integrated Urban Development
and Resilience Project for Greater Antananarivo-Procurement Plan.
Ndayambaje, A., 2021. Burundi-AFRICA EAST-P169315-Burundi Integrated Community
Development Project-Procurement Plan.
Rasoarimalalanarivo, S., 2020. Madagascar-AFRICA-P159756-Integrated Urban Development
and Resilience Project for Greater Antananarivo-Procurement Plan.
Kibangula, A.A., 2020. Eastern Africa-AFRICA EAST-P143307-AFR RI-Regional Great Lakes
Integrated Agriculture Development Project-Procurement Plan.
de Oliveira, F.C.C., 2021. Brazil-LATIN AMERICA AND CARIBBEAN-P147157-BRAZIL
BAHIA SUSTAINABLE RURAL DEVELOPMENT PROJECT-Procurement Plan.
El Kabbag, N.N.R., 2019. Egypt, Arab Republic of-MIDDLE EAST AND NORTH AFRICA-
P145699-Strengthening Social Safety Net Project-Procurement Plan.
Mohamoud, F.A., 2019. Somalia-AFRICA-P154875-Somalia Recurrent Cost and Reform
Financing Project-Phase 2-Procurement Plan.
Ahmed, A. and Ali, S., 2022. Lessons learned from adapting a quantitative to an emergent mixed
methods research design in Pakistan during COVID-19. International Journal of
Research & Method in Education, pp.1-17.
Liang, Q., Leung, M.Y. and Ahmed, K., 2021. How adoption of coping behaviors determines
construction workers’ safety: A quantitative and qualitative investigation. Safety
Science, 133, p.105035.
22
Facchin, F., Buggio, L. and Saita, E., 2020. Partners' perspective in endometriosis research and
treatment: A systematic review of qualitative and quantitative evidence. Journal of
Psychosomatic Research, 137, p.110213.
Patel, D., Shah, D. and Shah, M., 2020. The intertwine of brain and body: a quantitative analysis
on how big data influences the system of sports. Annals of Data Science, 7(1), pp.1-16.
Conway, E., 2019. Quantitative impacts of mandatory integrated reporting. Journal of Financial
Reporting and Accounting.
Zhang, M., 2019. Towards a quantitative model of understanding the dynamics of collaboration
in collaborative writing. Journal of second language writing, 45, pp.16-30.
Humble, S., 2020. Quantitative analysis of questionnaires: Techniques to explore structures and
relationships. Routledge.
Hechter, M., 2019. The future of rational choice theory and its relationships to quantitative
macro-sociological research. In Rational Choice Theory and Large-Scale Data
Analysis (pp. 281-290). Routledge.
Hou, K. and Wen, J., 2020. Quantitative analysis of the relationship between land use and
urbanization development in typical arid areas. Environmental Science and Pollution
Research, 27(31), pp.38758-38768.
Joshi, A. and Goyal, S.B., 2019, November. Comparison of Various Round Robin Scheduling
Algorithms. In 2019 8th International Conference System Modeling and Advancement
in Research Trends (SMART) (pp. 18-21). IEEE.
23
treatment: A systematic review of qualitative and quantitative evidence. Journal of
Psychosomatic Research, 137, p.110213.
Patel, D., Shah, D. and Shah, M., 2020. The intertwine of brain and body: a quantitative analysis
on how big data influences the system of sports. Annals of Data Science, 7(1), pp.1-16.
Conway, E., 2019. Quantitative impacts of mandatory integrated reporting. Journal of Financial
Reporting and Accounting.
Zhang, M., 2019. Towards a quantitative model of understanding the dynamics of collaboration
in collaborative writing. Journal of second language writing, 45, pp.16-30.
Humble, S., 2020. Quantitative analysis of questionnaires: Techniques to explore structures and
relationships. Routledge.
Hechter, M., 2019. The future of rational choice theory and its relationships to quantitative
macro-sociological research. In Rational Choice Theory and Large-Scale Data
Analysis (pp. 281-290). Routledge.
Hou, K. and Wen, J., 2020. Quantitative analysis of the relationship between land use and
urbanization development in typical arid areas. Environmental Science and Pollution
Research, 27(31), pp.38758-38768.
Joshi, A. and Goyal, S.B., 2019, November. Comparison of Various Round Robin Scheduling
Algorithms. In 2019 8th International Conference System Modeling and Advancement
in Research Trends (SMART) (pp. 18-21). IEEE.
23
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
APPENDIX
Questionnaire
Q1) Do you think workplace transformation is necessary in this digital world?
a) Yes
b) No
Q2) As per your opinion, what is the requirement of workplace transformation within retail
industry?
a) To make workforce work independently
b) To reskill and build the apt talent pool
c) To build new business model expertise
d) To increase social interaction and collaboration
e) To integrate several business dimensions systematically
Q3) According to your knowledge, which advanced technology is the best adopted by Next Plc
for employees to carry out their roles and collaborate?
a) Chatbots
b) Virtual assistants
c) IoT
d) Sentiment analysis
e) Data analytics
Q4) As per your knowledge, what is the impact of workplace transformation on workforce
satisfaction within Next PLc?
a) Positive impact
b) Negative impact
c) Neutral impact
Q5) What is the major benefit experienced by Next Plc through workplace transformation on
organisational performance?
a) Empowered and encouraged employees
b) Better communication and collaboration
c) Recruitment of top candidates
d) Increased flexibility
24
Questionnaire
Q1) Do you think workplace transformation is necessary in this digital world?
a) Yes
b) No
Q2) As per your opinion, what is the requirement of workplace transformation within retail
industry?
a) To make workforce work independently
b) To reskill and build the apt talent pool
c) To build new business model expertise
d) To increase social interaction and collaboration
e) To integrate several business dimensions systematically
Q3) According to your knowledge, which advanced technology is the best adopted by Next Plc
for employees to carry out their roles and collaborate?
a) Chatbots
b) Virtual assistants
c) IoT
d) Sentiment analysis
e) Data analytics
Q4) As per your knowledge, what is the impact of workplace transformation on workforce
satisfaction within Next PLc?
a) Positive impact
b) Negative impact
c) Neutral impact
Q5) What is the major benefit experienced by Next Plc through workplace transformation on
organisational performance?
a) Empowered and encouraged employees
b) Better communication and collaboration
c) Recruitment of top candidates
d) Increased flexibility
24
e) Decreased operational costs
25
25
1 out of 27
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.