This TELOS report assesses the feasibility of establishing a new corporate network for Globex Corporation, which has expanded to three offices. The report analyzes technical, economic, legal, and operational aspects, including business, functional, non-functional, and technical requirements. Technical feasibility focuses on secured communication and VPN implementation. Economic feasibility includes a cost-benefit analysis, while legal feasibility ensures compliance. Operational feasibility evaluates compatibility and scalability. Schedule feasibility outlines project milestones. The report concludes that the project is feasible within the existing IT infrastructure, aiming to enhance performance through improved communication and data exchange. References are provided at the end.
Document Page
TELOS report
Project Client Organisation: Globex
Contact:
System Name WOGAC
Document Status
Document Reference 1
Version Number
Prepared by Peter Deng
Team Members Scott Lyons, Nicholas Nancarrow and Yohan
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Lefort.
Change History
Date Description of
Change
Reason for
Change
Author of
Change
Version No.
Document Page
Table of Contents
1. Executive summary...........................................................................................................4
2. Introduction.......................................................................................................................4
3. Technical feasibility..........................................................................................................4
4. Economic feasibility..........................................................................................................4
5. Legal feasibility.................................................................................................................4
6. Operational/Organ
1. Executive summary...........................................................................................................5
2. Introduction.......................................................................................................................5
3. Technical feasibility..........................................................................................................5
Business requirements..........................................................................................................5
Functional requirements......................................................................................................5
Non-functional requirements...............................................................................................5
Technical requirements........................................................................................................5
4. Economic feasibility Business requirements..................................................................5
Business requirements..........................................................................................................5
Functional requirements......................................................................................................5
Non-functional requirements...............................................................................................5
Document Page
Technical requirements........................................................................................................5
5. Legal feasibility.................................................................................................................5
Business requirements..........................................................................................................5
Functional requirements......................................................................................................5
Non-functional requirements...............................................................................................5
Technical requirements........................................................................................................5
6. Operational/Organisational feasibility...........................................................................5
Business requirements..........................................................................................................5
Functional requirements......................................................................................................5
Non-functional requirements...............................................................................................6
Technical requirements........................................................................................................6
7. Schedule feasibility...........................................................................................................6
Business requirements..........................................................................................................6
Functional requirements......................................................................................................6
Non-functional requirements...............................................................................................6
Technical requirements........................................................................................................6
8. Conclusion.........................................................................................................................6
9. References..........................................................................................................................6
4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1. Executive summary
Globex Corporation that has expanded the business through establishing three different
offices in Albury, Grifith, and Wagga Wagga. The purpose of this report is to analysis the
feasibility of the report of establishing the new corporate network for Globex. Secured
and effective network would be helpful in enhancing the performance of the corporation
and providing effective and efficient services to the customers. The identified problem
for the establishment is the effective and secured communication internally and
externally. This report performs feasibility analysis based on the Telos frame in manner
to identify the practical aspects related to the establishment. This will be helpful in
effective communication between the different offices and contribute in the enhancement
of the performance of the organization.
Document Page
2. Introduction
The purpose of this report is to perform feasibility analysis on the needs and requirements
of those needs to be established within this setup. The aim of the report is to present the
aspects related to the enhancement in the network structure of the Global Corporation
that has been not updated with the latest technologies and needs to be transformed using
the latest technologies. This will be helpful in presenting the secured network and secured
VPN that will be resulting in the secured exchange of information between the offices
established at different places. The proposed report analyse the establishment of the
Secured VPN, full mesh topology communication and HTTPS connection via internet.
3. Technical feasibility
Business requirements
The proposed network design will be allowing to make effective communication with
the two other office expansions. Better and enhanced agricultural services can be provided to
the consumers. Better, enhanced and efficient communication and exchange of information
can be accomplished. It will allow the Globex to utilize the cloud services in better and
effective manner.
Functional requirements
Effective communication, smooth exchange of information between the offices, real-
time data collection and execution are some of the basic functional requirements. Secured
connection will be needed for securing the data or information being exchanged. Enough
storage of data or information. User can be connected to the network using mobile devices or
any other computer systems.
Document Page
Non-functional requirements
The proposed system is scalable as many users can be connected to the network and
every staff can access the data or information according to their access level. Compatibility is
another factor, as the network should be connected in any device in manner to access the data
or information stored in the network. Flexibility is another non-functional requirement as the
user should be allowed to enter the network as many times as he or she wants to.
Technical requirements
Implement the effective and secured communication network between the sites and allow
them to communicate in effective and secured manner for the accomplishment of the
operational activities. The proposed system can be implemented within the existing IT
infrastructure of the can be implemented without any extra effort as an upgrade to the existing
system.
4. Economic feasibility
Business requirements
This will be enhancing the overall output and performance of the organization through
establishing the effective and secured communication and data exchange method. It will be
mobilizing the current operational activities and boosting them for the enhancement in the
production.
Functional requirements
Providing an automated system for the real time data collection and real time data
execution through utilizing the cloud services in much better and effective way between the
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
settled offices. Reflecting on the overall output of the organization through the
implementation of the secured and sophisticated network.
Cost benefit analysis:
Cost benefit analysis
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Net economic
benefit $114,000 $114,000 $114,000 $114,000 $114,000
One time cost ($450,000) $0 $0 $0 $0 $0
Recurring cost $10,000 ($6,000) ($6,000) ($6,000) ($6,000) ($6,000)
Net cash flow ($440,000) $108,000 $108,000 $108,000 $108,000 $108,000
Discount
factors
Discount rate
Year Index 0 1 2 3 4 5
Discount
factor 1 1.00 1.00 1.00 1.00 1.00
Discounted
flows
Cost ($450,000) ($6,000) ($6,000) ($6,000) ($6,000) ($6,000)
Benefit $0 $114,000 $114,000 $114,000 $114,000 $114,000
Net ($450,000) $108,000 $108,000 $108,000 $108,000 $108,000
Cummulative ($450,000)
($342,00
0)
($234,00
0)
($126,00
0) ($18,000) $90,000
Net present
value $90,000
NPV in
fraction 1.188
IRR 7%
Payback
Analysis
Fraction Row - - - - - 2.57
Partial years
for negative
cash flow 2.57
Payback
Period in
Years 2.57
Non-functional requirements
The network should be reliable and services being utilized should bring out the
Document Page
necessary outcome from the project. It should be easily utilized by the user in manner to
deliver the operational activities.
Technical requirements
Better applications hosted by the cloud services. Secured connection that could be
delivered by VPN implementation and hosting the web pages at HTTPS. VLAN can be
helpful in controlling the traffic and eliminating the congestions in the network.
5. Legal feasibility
Business requirements
Proper and effective agreement will needed to be managed in manner to legally
implement the network that will be complying according to the policies of the Globex. All the
legal agreements should be complying with the business strategy in manner to meet the
objectives and goals of this network establishment.
Functional requirements
Router and network distribution should be made according to the agreement made
with the telecommunication company. The bandwidth and network strength should be high in
manner to provide unstoppable connection for all the centres. The database and file storage
actions should be complying with the existing policies of the Globex.
Non-functional requirements
The established network will be providing the secured network of high bandwidth with
crossing any policy agreements with the government and the company itself. There should not
be any congestions in the network or any downtime; at least the established network will be
Document Page
providing 99% of the traffic without any congestions allowing every staff to access the
network.
Technical requirements
High quality standard routers those will be helpful in distributing the network without
any issues. The fibre cables will be used for the distribution of the network within the work
place enhancing the speed of the internet and establishing better and effective communication.
6. Operational/Organisational feasibility
Business requirements
The proposed solution will be helpful in meeting the objectives and goals of the
organization through providing an efficient and secured network. This will be resulting in the
smooth flow and exchange of the information and thus, resulting in the enhancement of the
performance of the Globex.
Functional requirements
The IT infrastructure will be easily compatible with all the devices those can be
connected to the network and there will not be extra effort on upgrading the previous
infrastructure. Third party services will be helpful in ensuring the proper and effective
establishment of the new infrastructure.
Non-functional requirements
It could be easily upgradable and compatible with all the devices. It can be effectively
incorporated within the every expanded office providing network connectivity within the
offices and resulting in the proper and efficient flow of the operational activities. It should be
easily compatible as per the policies set by the Globex.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Technical requirements
Cost effective implementation and transformation can be helpful in keeping the
objectives and goals of the organization. Orange and Cloud will be helpful in availing the
third party services and thus, it will be saving a large amount of money.
7. Schedule feasibility
Business requirements
It is being expected that the project will be completed within the expected schedule
without affecting the timeline and schedule as proposed in the project charter. Following are
some of the milestones with the expected schedule:
Project Milestone Deliverable Expected Date
Project Start-up Charter and Management Plan 16/03/2018
Requirements
Specification -
Feasibility Study
Specification of Requirements (use cases
or similar)
Test Strategy
Updated Project Plan
Feasibility Study
02/04/2018
Draft Design -
Detailed PMP
Fully worked out architecture and detail of
design
Test Plan in detail
30/04/2018
Final Documentation
& presentation
15 minute presentation showing proposed
solution exhibiting understanding of client
problem, vision of project, requirements,
scope and risks. Overview showing how
client’s needs will be met
21/05/2018
Document Page
Iteration Additional functionality
Test Cases
Iteration Test results
Iteration Test results
Final Release Solution plus all documentation, provided
electronically
Project Completion Individual evaluation reports November 2018
8. Conclusion
Based on the above report it can be concluded that the project is very feasible within the
existing IT infrastructure of the organization. The feasibility analysis have been
accomplished in successful manner the proposed solution is very much feasible within
the organization considering the enhancement in the performance of the organization.
9. References
Aartman, J. Q., Diemer, F. S., Karamat, F. A., Bohte, E., Baldew, S. M., Jarbandhan, A. V., ...
& Brewster, L. M. (2017). Assessing the feasibility of the Healthy Life in Suriname
Study: using advanced hemodynamics to evaluate cardiovascular risk. Revista
Panamericana de Salud Pública, 41, e46.
Avan, B. I., Berhanu, D., Umar, N., Wickremasinghe, D., & Schellenberg, J. (2016). District
decision-making for health in low-income settings: a feasibility study of a data-
informed platform for health in India, Nigeria and Ethiopia. Health policy and
planning, 31(suppl_2), ii3-ii11.
chevron_up_icon
1 out of 14
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]