Project Report: Ticketing System Development for RALS Project
VerifiedAdded on 2020/05/16
|17
|2241
|31
Report
AI Summary
This project management report details the development of a ticketing system for the Riverina Agriculture and Lifestyle Show (RALS). The report begins with an analysis of MOV values, ranking factors like operations, client needs, finance, social impact, and strategy. It then outlines a comprehensive scope management plan, defining scope, requirements, in-scope and out-of-scope items, and project deliverables. A detailed project schedule, including work breakdown structure (WBS), task durations, and dependencies, is presented. The report also includes a risk analysis, identifying potential risks, their ranking, related project phases, risk owners, probability, severity, and potential responses. A quality management plan, covering verification and validation activities, is also provided. Finally, the report concludes with a project closure checklist and evaluation, assessing the project's functionality, cost-effectiveness, and overall performance. An annotated bibliography supports the report's findings. The report is a comprehensive project management plan for the RALS ticketing system.

Running head: PROJECT MANAGEMENT REPORT
Project Management Report
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Management Report
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT REPORT
Table of Contents
Part 1: MOV Values........................................................................................................................2
Part 2: Scope Management Plan......................................................................................................5
Part 3: Project Schedule...................................................................................................................8
Part 4: Project Risk Analysis.........................................................................................................12
Part 5: Quality Management Plan..................................................................................................13
Part 6: Project Closure and Evaluation..........................................................................................14
Bibliography..................................................................................................................................16
Appendix- Annotated Bibliography..............................................................................................17
Table of Contents
Part 1: MOV Values........................................................................................................................2
Part 2: Scope Management Plan......................................................................................................5
Part 3: Project Schedule...................................................................................................................8
Part 4: Project Risk Analysis.........................................................................................................12
Part 5: Quality Management Plan..................................................................................................13
Part 6: Project Closure and Evaluation..........................................................................................14
Bibliography..................................................................................................................................16
Appendix- Annotated Bibliography..............................................................................................17

2PROJECT MANAGEMENT REPORT
Part 1: MOV Values
Ranking: The project of Ticketing System Development for RALS is formed for ensuring that a
proper and systematic system for the storing and printing of the tickets for the Riverina
Agriculture and Lifestyle Show. The implication of the effective and improved processing
methods would imply the formation of the improved processing and the development of the
integration management. The project had to comprise the formation for enduring the specific
terms of finance, operations, client, strategy, and social issues for the development of the project
operations. The analysis of the these factors have been given in the table below,
Factor Description Ran
k
Operation The business operations are the most prominent factor that can impact
the operations of the improved processes for the project. The changes in
project operations would result in forming the tangibility of the specific
project operations.
1st
Client The client factor plays an important role in forming the impact on the
project activities. The client’s requirement is a major factor that would
form the assertive development factor for the project users.
2nd
Finance The financial impact on the project activities would tend to compel the
most appropriate and assertive impact factor for the project. The
financial factor is largely helpful for forming the modification in the
3rd
Part 1: MOV Values
Ranking: The project of Ticketing System Development for RALS is formed for ensuring that a
proper and systematic system for the storing and printing of the tickets for the Riverina
Agriculture and Lifestyle Show. The implication of the effective and improved processing
methods would imply the formation of the improved processing and the development of the
integration management. The project had to comprise the formation for enduring the specific
terms of finance, operations, client, strategy, and social issues for the development of the project
operations. The analysis of the these factors have been given in the table below,
Factor Description Ran
k
Operation The business operations are the most prominent factor that can impact
the operations of the improved processes for the project. The changes in
project operations would result in forming the tangibility of the specific
project operations.
1st
Client The client factor plays an important role in forming the impact on the
project activities. The client’s requirement is a major factor that would
form the assertive development factor for the project users.
2nd
Finance The financial impact on the project activities would tend to compel the
most appropriate and assertive impact factor for the project. The
financial factor is largely helpful for forming the modification in the
3rd
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT REPORT
change of the project activities.
Social Being an IT based system development would tend to form the
modification of the project due to social influence. The social influence
in the project activities would tend to outlast the development factor for
the project activities.
4th
Strategy Strategically the project faces very less change or modification as it can
be implemented by using any of the project management principles and
approach for IT system development and implementation.
5th
a. Better- The project of Ticketing System Development for RALS would be helpful for forming
an integrated information system that is capable for storing all the information in a single
database along with the specific and improved operations for the show.
b. Faster- The ticket generation system for the Riverina Agriculture and Lifestyle Show would be
helpful for listing the visitors of the show and easily form the ticket generation system. The
system would result in compiling and accessing the information by consuming very less amount
of time.
c. Cheaper- The cost of manual ticket generation, salaries of the people managing the operations,
and the information management at various places (files or drives) is very high compare to the
cost of using the ticketing system. Hence, it would decrease the overall cost of the processes and
make the process cheaper in comparison.
change of the project activities.
Social Being an IT based system development would tend to form the
modification of the project due to social influence. The social influence
in the project activities would tend to outlast the development factor for
the project activities.
4th
Strategy Strategically the project faces very less change or modification as it can
be implemented by using any of the project management principles and
approach for IT system development and implementation.
5th
a. Better- The project of Ticketing System Development for RALS would be helpful for forming
an integrated information system that is capable for storing all the information in a single
database along with the specific and improved operations for the show.
b. Faster- The ticket generation system for the Riverina Agriculture and Lifestyle Show would be
helpful for listing the visitors of the show and easily form the ticket generation system. The
system would result in compiling and accessing the information by consuming very less amount
of time.
c. Cheaper- The cost of manual ticket generation, salaries of the people managing the operations,
and the information management at various places (files or drives) is very high compare to the
cost of using the ticketing system. Hence, it would decrease the overall cost of the processes and
make the process cheaper in comparison.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT REPORT
d. Do more- The system would also serve as a medium for communication and future operations
as the data would be stored permanently. The system would result in easing the process of the
effective program development and operations.
Appropriate Metric with timeframe:
Factor Metrics Timeframe (in months)
Operation Operational Management Plan 4
Client Customer Review and Feedback Forums 6
Finance Profit Analysis, Net Present Value, and
Revenue Calculation
3
Social Social Implementation Model 2
Strategy Strategy Development and Analysis Matrix 3
MOV statement: The MOV statement signifies that, “Ticketing System Development for RALS
Project” can be implied for the modification of the existing information system so that a new
ticketing system for the Riverina Agriculture and Lifestyle Show would be formed for
developing the effective and improved processing methods. The system would also help in
easing the process of the information transfer and accessing.
d. Do more- The system would also serve as a medium for communication and future operations
as the data would be stored permanently. The system would result in easing the process of the
effective program development and operations.
Appropriate Metric with timeframe:
Factor Metrics Timeframe (in months)
Operation Operational Management Plan 4
Client Customer Review and Feedback Forums 6
Finance Profit Analysis, Net Present Value, and
Revenue Calculation
3
Social Social Implementation Model 2
Strategy Strategy Development and Analysis Matrix 3
MOV statement: The MOV statement signifies that, “Ticketing System Development for RALS
Project” can be implied for the modification of the existing information system so that a new
ticketing system for the Riverina Agriculture and Lifestyle Show would be formed for
developing the effective and improved processing methods. The system would also help in
easing the process of the information transfer and accessing.

5PROJECT MANAGEMENT REPORT
Part 2: Scope Management Plan
Define Scope: The project of Ticketing System Development for RALS would be helpful for
forming a ticketing system that would be capable of forming the improved functional analysis
and modification of the existing functional development models. The project would involve the
development of a project charter document, project scheduling process, cost budget estimation,
and risk management plan.
Requirements: The project of Ticketing System Development for RALS would comprise of
forming an effective and improved system for ticketing process of Riverina Agriculture and
Lifestyle Show. The project would require the use of the IT system development technology,
project management principles, and effective leadership style. The project plan would also
comprise of using Waterfall Approach for developing the complete project plan. The human
resources required for the project are Analyst, Documenter, Project Manager, Planner, Designer,
IT Engineer, Database Developer, Programmer, Tester, and Trainer.
In Scope and Out of Scope: The in scope items are the factors or elements of the project that
would be included in the deliverables or activities of the project. The project of Ticketing System
Development for RALS would involve the formation of the project initiation documentation,
charter documentation, project scheduling plan, cost estimation planning, risk management
planning, communication planning, scope management planning, complete design development,
user interface development, database development, system is developed, user interface testing,
black box testing, white box testing, training manual development, staff training, and final
documentation. The out of scope items of the project are the elements or components of the
system development and implementation that are not a part of the project management plan. The
Part 2: Scope Management Plan
Define Scope: The project of Ticketing System Development for RALS would be helpful for
forming a ticketing system that would be capable of forming the improved functional analysis
and modification of the existing functional development models. The project would involve the
development of a project charter document, project scheduling process, cost budget estimation,
and risk management plan.
Requirements: The project of Ticketing System Development for RALS would comprise of
forming an effective and improved system for ticketing process of Riverina Agriculture and
Lifestyle Show. The project would require the use of the IT system development technology,
project management principles, and effective leadership style. The project plan would also
comprise of using Waterfall Approach for developing the complete project plan. The human
resources required for the project are Analyst, Documenter, Project Manager, Planner, Designer,
IT Engineer, Database Developer, Programmer, Tester, and Trainer.
In Scope and Out of Scope: The in scope items are the factors or elements of the project that
would be included in the deliverables or activities of the project. The project of Ticketing System
Development for RALS would involve the formation of the project initiation documentation,
charter documentation, project scheduling plan, cost estimation planning, risk management
planning, communication planning, scope management planning, complete design development,
user interface development, database development, system is developed, user interface testing,
black box testing, white box testing, training manual development, staff training, and final
documentation. The out of scope items of the project are the elements or components of the
system development and implementation that are not a part of the project management plan. The
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT REPORT
change management plan, transportation requirements, and contractor agreements are not a part
of this project and can be said as out of scope items of the project.
Deliverables: The deliverables for the project of Ticketing System Development for RALS are
listed in the table below,
WBS Task Name Duration Start Finish
1.4 Project Initiation Documentation 2 days Fri 3/16/18 Mon 3/19/18
1.5 Charter Documentation 2 days Tue 3/20/18 Wed 3/21/18
2.1 Project Scheduling Plan 4 days Mon 3/26/18 Thu 3/29/18
2.2 Cost Estimation Planning 2 days Fri 3/30/18 Mon 4/2/18
2.3 Risk Management Planning 5 days Tue 4/3/18 Mon 4/9/18
2.4 Communication Planning 3 days Tue 4/10/18 Thu 4/12/18
2.5 Scope Management Planning 3 days Fri 4/13/18 Tue 4/17/18
3.1.4 Complete Design Development 5 days Mon 4/30/18 Fri 5/4/18
3.2.1 User Interface Development 6 days Tue 5/8/18 Tue 5/15/18
3.2.2 Database Development 5 days Wed 5/16/18 Tue 5/22/18
3.2.4 System Functional Programming 7 days Mon 5/28/18 Tue 6/5/18
3.2.6 System is Developed 1 day Tue 6/12/18 Tue 6/12/18
4.4 Testing Results Documentation 2 days Tue 6/26/18 Wed 6/27/18
5.1 Training Manual Development 3 days Thu 6/28/18 Mon 7/2/18
5.4 Final Documents are made 3 days Mon 7/16/18 Wed 7/18/18
change management plan, transportation requirements, and contractor agreements are not a part
of this project and can be said as out of scope items of the project.
Deliverables: The deliverables for the project of Ticketing System Development for RALS are
listed in the table below,
WBS Task Name Duration Start Finish
1.4 Project Initiation Documentation 2 days Fri 3/16/18 Mon 3/19/18
1.5 Charter Documentation 2 days Tue 3/20/18 Wed 3/21/18
2.1 Project Scheduling Plan 4 days Mon 3/26/18 Thu 3/29/18
2.2 Cost Estimation Planning 2 days Fri 3/30/18 Mon 4/2/18
2.3 Risk Management Planning 5 days Tue 4/3/18 Mon 4/9/18
2.4 Communication Planning 3 days Tue 4/10/18 Thu 4/12/18
2.5 Scope Management Planning 3 days Fri 4/13/18 Tue 4/17/18
3.1.4 Complete Design Development 5 days Mon 4/30/18 Fri 5/4/18
3.2.1 User Interface Development 6 days Tue 5/8/18 Tue 5/15/18
3.2.2 Database Development 5 days Wed 5/16/18 Tue 5/22/18
3.2.4 System Functional Programming 7 days Mon 5/28/18 Tue 6/5/18
3.2.6 System is Developed 1 day Tue 6/12/18 Tue 6/12/18
4.4 Testing Results Documentation 2 days Tue 6/26/18 Wed 6/27/18
5.1 Training Manual Development 3 days Thu 6/28/18 Mon 7/2/18
5.4 Final Documents are made 3 days Mon 7/16/18 Wed 7/18/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT REPORT
6 Project is Closed 1 day Mon 7/23/18 Mon 7/23/18
Acceptance Criteria: The project acceptance criteria for the project of Ticketing System
Development for RALS are,
a. Project Team would use the effective project management principles for implementing
the advances technology of ticketing system for RALS
b. Overall expense of the project would be limited to an estimated budget of $ 65,000.00
and a provisional budget for $ 5,000.00
c. Project life span would be limited to four months of time duration and the project life
cycle would be limited to the 101 working days
Provide a list of resources:
Resource Name Type of Resource Duration/Units
Analyst Human 72 hrs
Documenter Human 96 hrs
Project Manager Human 40 hrs
Planner Human 136 hrs
Designer Human 80 hrs
IT Engineer Human 88 hrs
Database Developer Human 64 hrs
Programmer Human 56 hrs
6 Project is Closed 1 day Mon 7/23/18 Mon 7/23/18
Acceptance Criteria: The project acceptance criteria for the project of Ticketing System
Development for RALS are,
a. Project Team would use the effective project management principles for implementing
the advances technology of ticketing system for RALS
b. Overall expense of the project would be limited to an estimated budget of $ 65,000.00
and a provisional budget for $ 5,000.00
c. Project life span would be limited to four months of time duration and the project life
cycle would be limited to the 101 working days
Provide a list of resources:
Resource Name Type of Resource Duration/Units
Analyst Human 72 hrs
Documenter Human 96 hrs
Project Manager Human 40 hrs
Planner Human 136 hrs
Designer Human 80 hrs
IT Engineer Human 88 hrs
Database Developer Human 64 hrs
Programmer Human 56 hrs

8PROJECT MANAGEMENT REPORT
Tester Human 104 hrs
Trainer Human 96 hrs
Computer devices Material 1
Database Storage Material 1
Network Components Material 1
Project Scheduling Method Principle 1
Cost Estimation Theory Principle 1
Risk Management Method Principle 1
Networking Protocols Technology 1
Network connection Technology 1
Part 3: Project Schedule
The schedule for the project of Ticketing System Development for RALS is given in the
table below,
WBS Task Name Duration Start Finish
0 Ticketing System Development for RALS 101 days Mon 3/5/18 Mon 7/23/18
1 Requirement and Documentation Phase 15 days Mon 3/5/18 Fri 3/23/18
1.1 Requirement Analysis 3 days Mon 3/5/18 Wed 3/7/18
1.2 Feasibility Analysis 3 days Thu 3/8/18 Mon 3/12/18
1.3 Sustainability Analysis 3 days Tue 3/13/18 Thu 3/15/18
1.4 Project Initiation Documentation 2 days Fri 3/16/18 Mon 3/19/18
1.5 Charter Documentation 2 days Tue 3/20/18 Wed 3/21/18
1.6 Document Submission 1 day Thu 3/22/18 Thu 3/22/18
Tester Human 104 hrs
Trainer Human 96 hrs
Computer devices Material 1
Database Storage Material 1
Network Components Material 1
Project Scheduling Method Principle 1
Cost Estimation Theory Principle 1
Risk Management Method Principle 1
Networking Protocols Technology 1
Network connection Technology 1
Part 3: Project Schedule
The schedule for the project of Ticketing System Development for RALS is given in the
table below,
WBS Task Name Duration Start Finish
0 Ticketing System Development for RALS 101 days Mon 3/5/18 Mon 7/23/18
1 Requirement and Documentation Phase 15 days Mon 3/5/18 Fri 3/23/18
1.1 Requirement Analysis 3 days Mon 3/5/18 Wed 3/7/18
1.2 Feasibility Analysis 3 days Thu 3/8/18 Mon 3/12/18
1.3 Sustainability Analysis 3 days Tue 3/13/18 Thu 3/15/18
1.4 Project Initiation Documentation 2 days Fri 3/16/18 Mon 3/19/18
1.5 Charter Documentation 2 days Tue 3/20/18 Wed 3/21/18
1.6 Document Submission 1 day Thu 3/22/18 Thu 3/22/18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT REPORT
1.7 Review and Sign up 1 day Fri 3/23/18 Fri 3/23/18
2 Planning Phase 18 days Mon 3/26/18 Wed 4/18/18
2.1 Project Scheduling Plan 4 days Mon 3/26/18 Thu 3/29/18
2.2 Cost Estimation Planning 2 days Fri 3/30/18 Mon 4/2/18
2.3 Risk Management Planning 5 days Tue 4/3/18 Mon 4/9/18
2.4 Communication Planning 3 days Tue 4/10/18 Thu 4/12/18
2.5 Scope Management Planning 3 days Fri 4/13/18 Tue 4/17/18
2.6 Plan Approval 1 day Wed 4/18/18 Wed 4/18/18
3 System Development 39 days Thu 4/19/18 Tue 6/12/18
3.1 Designing Phase 13 days Thu 4/19/18 Mon 5/7/18
3.1.1 Selection of design methodology 2 days Thu 4/19/18 Fri 4/20/18
3.1.2 Development of Design Outline 3 days Mon 4/23/18 Wed 4/25/18
3.1.3 Simulation of the design 2 days Thu 4/26/18 Fri 4/27/18
3.1.4 Complete Design Development 5 days Mon 4/30/18 Fri 5/4/18
3.1.5 Review and Approval of Design 1 day Mon 5/7/18 Mon 5/7/18
3.2 Developing Phase 26 days Tue 5/8/18 Tue 6/12/18
3.2.1 User Interface Development 6 days Tue 5/8/18 Tue 5/15/18
3.2.2 Database Development 5 days Wed 5/16/18 Tue 5/22/18
3.2.3 Integration of the database 3 days Wed 5/23/18 Fri 5/25/18
3.2.4 System Functional Programming 7 days Mon 5/28/18 Tue 6/5/18
3.2.5 System Components Integration 4 days Wed 6/6/18 Mon 6/11/18
3.2.6 System is Developed 1 day Tue 6/12/18 Tue 6/12/18
4 Testing 11 days Wed 6/13/18 Wed 6/27/18
4.1 User Interface Testing 3 days Wed 6/13/18 Fri 6/15/18
4.2 Black Box Testing 3 days Mon 6/18/18 Wed 6/20/18
1.7 Review and Sign up 1 day Fri 3/23/18 Fri 3/23/18
2 Planning Phase 18 days Mon 3/26/18 Wed 4/18/18
2.1 Project Scheduling Plan 4 days Mon 3/26/18 Thu 3/29/18
2.2 Cost Estimation Planning 2 days Fri 3/30/18 Mon 4/2/18
2.3 Risk Management Planning 5 days Tue 4/3/18 Mon 4/9/18
2.4 Communication Planning 3 days Tue 4/10/18 Thu 4/12/18
2.5 Scope Management Planning 3 days Fri 4/13/18 Tue 4/17/18
2.6 Plan Approval 1 day Wed 4/18/18 Wed 4/18/18
3 System Development 39 days Thu 4/19/18 Tue 6/12/18
3.1 Designing Phase 13 days Thu 4/19/18 Mon 5/7/18
3.1.1 Selection of design methodology 2 days Thu 4/19/18 Fri 4/20/18
3.1.2 Development of Design Outline 3 days Mon 4/23/18 Wed 4/25/18
3.1.3 Simulation of the design 2 days Thu 4/26/18 Fri 4/27/18
3.1.4 Complete Design Development 5 days Mon 4/30/18 Fri 5/4/18
3.1.5 Review and Approval of Design 1 day Mon 5/7/18 Mon 5/7/18
3.2 Developing Phase 26 days Tue 5/8/18 Tue 6/12/18
3.2.1 User Interface Development 6 days Tue 5/8/18 Tue 5/15/18
3.2.2 Database Development 5 days Wed 5/16/18 Tue 5/22/18
3.2.3 Integration of the database 3 days Wed 5/23/18 Fri 5/25/18
3.2.4 System Functional Programming 7 days Mon 5/28/18 Tue 6/5/18
3.2.5 System Components Integration 4 days Wed 6/6/18 Mon 6/11/18
3.2.6 System is Developed 1 day Tue 6/12/18 Tue 6/12/18
4 Testing 11 days Wed 6/13/18 Wed 6/27/18
4.1 User Interface Testing 3 days Wed 6/13/18 Fri 6/15/18
4.2 Black Box Testing 3 days Mon 6/18/18 Wed 6/20/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT REPORT
4.3 White Box Testing 3 days Thu 6/21/18 Mon 6/25/18
4.4 Testing Results Documentation 2 days Tue 6/26/18 Wed 6/27/18
5 Training and Documentation 17 days Thu 6/28/18 Fri 7/20/18
5.1 Training Manual Development 3 days Thu 6/28/18 Mon 7/2/18
5.2 Training Program development 2 days Tue 7/3/18 Wed 7/4/18
5.3 Training is Provided 7 days Thu 7/5/18 Fri 7/13/18
5.4 Final Documents are made 3 days Mon 7/16/18 Wed 7/18/18
5.5 Documents are Submitted 1 day Thu 7/19/18 Thu 7/19/18
5.6 Review and Sign off 1 day Fri 7/20/18 Fri 7/20/18
6 Project is Closed 1 day Mon 7/23/18 Mon 7/23/18
4.3 White Box Testing 3 days Thu 6/21/18 Mon 6/25/18
4.4 Testing Results Documentation 2 days Tue 6/26/18 Wed 6/27/18
5 Training and Documentation 17 days Thu 6/28/18 Fri 7/20/18
5.1 Training Manual Development 3 days Thu 6/28/18 Mon 7/2/18
5.2 Training Program development 2 days Tue 7/3/18 Wed 7/4/18
5.3 Training is Provided 7 days Thu 7/5/18 Fri 7/13/18
5.4 Final Documents are made 3 days Mon 7/16/18 Wed 7/18/18
5.5 Documents are Submitted 1 day Thu 7/19/18 Thu 7/19/18
5.6 Review and Sign off 1 day Fri 7/20/18 Fri 7/20/18
6 Project is Closed 1 day Mon 7/23/18 Mon 7/23/18

11PROJECT MANAGEMENT REPORT
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Ticketing System Development for RALS101 days Mon 3/5/18 Mon 7/23/18
1 1 Requirement and Documentation Phase15 days Mon 3/5/18 Fri 3/23/18
2 1.1 Requirement Analysis 3 days Mon 3/5/18 Wed 3/7/18
3 1.2 Feasibility Analysis 3 days Thu 3/8/18 Mon 3/12/18
4 1.3 Sustainability Analysis 3 days Tue 3/13/18 Thu 3/15/18
5 1.4 Project Initiation Documentation 2 days Fri 3/16/18 Mon 3/19/18
6 1.5 Charter Documentation 2 days Tue 3/20/18 Wed 3/21/18
7 1.6 Document Submission 1 day Thu 3/22/18 Thu 3/22/18
8 1.7 Review and Sign up 1 day Fri 3/23/18 Fri 3/23/18
9 2 Planning Phase 18 days Mon 3/26/18 Wed 4/18/18
10 2.1 Project Scheduling Plan 4 days Mon 3/26/18 Thu 3/29/18
11 2.2 Cost Estimation Planning 2 days Fri 3/30/18 Mon 4/2/18
12 2.3 Risk Management Planning 5 days Tue 4/3/18 Mon 4/9/18
13 2.4 Communication Planning 3 days Tue 4/10/18 Thu 4/12/18
14 2.5 Scope Management Planning 3 days Fri 4/13/18 Tue 4/17/18
15 2.6 Plan Approval 1 day Wed 4/18/18 Wed 4/18/18
16 3 System Development 39 days Thu 4/19/18 Tue 6/12/18
17 3.1 Designing Phase 13 days Thu 4/19/18 Mon 5/7/18
18 3.1.1 Selection of design methodology2 days Thu 4/19/18 Fri 4/20/18
19 3.1.2 Development of Design Outline3 days Mon 4/23/18 Wed 4/25/18
20 3.1.3 Simulation of the design 2 days Thu 4/26/18 Fri 4/27/18
21 3.1.4 Complete Design Development5 days Mon 4/30/18 Fri 5/4/18
22 3.1.5 Review and Approval of Design1 day Mon 5/7/18 Mon 5/7/18
23 3.2 Developing Phase 26 days Tue 5/8/18 Tue 6/12/18
24 3.2.1 User Interface Development 6 days Tue 5/8/18 Tue 5/15/18
25 3.2.2 Database Development 5 days Wed 5/16/18 Tue 5/22/18
26 3.2.3 Integration of the database 3 days Wed 5/23/18 Fri 5/25/18
27 3.2.4 System Functional Programming7 days Mon 5/28/18 Tue 6/5/18
28 3.2.5 System Components Integration4 days Wed 6/6/18 Mon 6/11/18
29 3.2.6 System is Developed 1 day Tue 6/12/18 Tue 6/12/18
30 4 Testing 11 days Wed 6/13/18 Wed 6/27/18
31 4.1 User Interface Testing 3 days Wed 6/13/18 Fri 6/15/18
32 4.2 Black Box Testing 3 days Mon 6/18/18 Wed 6/20/18
33 4.3 White Box Testing 3 days Thu 6/21/18 Mon 6/25/18
34 4.4 Testing Results Documentation 2 days Tue 6/26/18 Wed 6/27/18
35 5 Training and Documentation 17 days Thu 6/28/18 Fri 7/20/18
36 5.1 Training Manual Development 3 days Thu 6/28/18 Mon 7/2/18
37 5.2 Training Program development 2 days Tue 7/3/18 Wed 7/4/18
38 5.3 Training is Provided 7 days Thu 7/5/18 Fri 7/13/18
39 5.4 Final Documents are made 3 days Mon 7/16/18 Wed 7/18/18
40 5.5 Documents are Submitted 1 day Thu 7/19/18 Thu 7/19/18
41 5.6 Review and Sign off 1 day Fri 7/20/18 Fri 7/20/18
42 6 Project is Closed 1 day Mon 7/23/18 Mon 7/23/18
Analyst
Analyst
Analyst
Documenter
Documenter
Documenter
Project Manager
Planner
Planner
Planner
Planner
Planner
Project Manager
Designer
Designer
Tester
Designer
Project Manager
IT Engineer
Database Developer
Database Developer
Programmer
IT Engineer
IT Engineer
Tester
Tester
Tester
Tester
Documenter,Trainer
Trainer
Trainer
Documenter
Documenter
Project Manager
Project Manager
2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12
January 11 March 1 April 21 June 11 August 1
Figure 1: Project Gantt chart
(Source: created by the author)
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Ticketing System Development for RALS101 days Mon 3/5/18 Mon 7/23/18
1 1 Requirement and Documentation Phase15 days Mon 3/5/18 Fri 3/23/18
2 1.1 Requirement Analysis 3 days Mon 3/5/18 Wed 3/7/18
3 1.2 Feasibility Analysis 3 days Thu 3/8/18 Mon 3/12/18
4 1.3 Sustainability Analysis 3 days Tue 3/13/18 Thu 3/15/18
5 1.4 Project Initiation Documentation 2 days Fri 3/16/18 Mon 3/19/18
6 1.5 Charter Documentation 2 days Tue 3/20/18 Wed 3/21/18
7 1.6 Document Submission 1 day Thu 3/22/18 Thu 3/22/18
8 1.7 Review and Sign up 1 day Fri 3/23/18 Fri 3/23/18
9 2 Planning Phase 18 days Mon 3/26/18 Wed 4/18/18
10 2.1 Project Scheduling Plan 4 days Mon 3/26/18 Thu 3/29/18
11 2.2 Cost Estimation Planning 2 days Fri 3/30/18 Mon 4/2/18
12 2.3 Risk Management Planning 5 days Tue 4/3/18 Mon 4/9/18
13 2.4 Communication Planning 3 days Tue 4/10/18 Thu 4/12/18
14 2.5 Scope Management Planning 3 days Fri 4/13/18 Tue 4/17/18
15 2.6 Plan Approval 1 day Wed 4/18/18 Wed 4/18/18
16 3 System Development 39 days Thu 4/19/18 Tue 6/12/18
17 3.1 Designing Phase 13 days Thu 4/19/18 Mon 5/7/18
18 3.1.1 Selection of design methodology2 days Thu 4/19/18 Fri 4/20/18
19 3.1.2 Development of Design Outline3 days Mon 4/23/18 Wed 4/25/18
20 3.1.3 Simulation of the design 2 days Thu 4/26/18 Fri 4/27/18
21 3.1.4 Complete Design Development5 days Mon 4/30/18 Fri 5/4/18
22 3.1.5 Review and Approval of Design1 day Mon 5/7/18 Mon 5/7/18
23 3.2 Developing Phase 26 days Tue 5/8/18 Tue 6/12/18
24 3.2.1 User Interface Development 6 days Tue 5/8/18 Tue 5/15/18
25 3.2.2 Database Development 5 days Wed 5/16/18 Tue 5/22/18
26 3.2.3 Integration of the database 3 days Wed 5/23/18 Fri 5/25/18
27 3.2.4 System Functional Programming7 days Mon 5/28/18 Tue 6/5/18
28 3.2.5 System Components Integration4 days Wed 6/6/18 Mon 6/11/18
29 3.2.6 System is Developed 1 day Tue 6/12/18 Tue 6/12/18
30 4 Testing 11 days Wed 6/13/18 Wed 6/27/18
31 4.1 User Interface Testing 3 days Wed 6/13/18 Fri 6/15/18
32 4.2 Black Box Testing 3 days Mon 6/18/18 Wed 6/20/18
33 4.3 White Box Testing 3 days Thu 6/21/18 Mon 6/25/18
34 4.4 Testing Results Documentation 2 days Tue 6/26/18 Wed 6/27/18
35 5 Training and Documentation 17 days Thu 6/28/18 Fri 7/20/18
36 5.1 Training Manual Development 3 days Thu 6/28/18 Mon 7/2/18
37 5.2 Training Program development 2 days Tue 7/3/18 Wed 7/4/18
38 5.3 Training is Provided 7 days Thu 7/5/18 Fri 7/13/18
39 5.4 Final Documents are made 3 days Mon 7/16/18 Wed 7/18/18
40 5.5 Documents are Submitted 1 day Thu 7/19/18 Thu 7/19/18
41 5.6 Review and Sign off 1 day Fri 7/20/18 Fri 7/20/18
42 6 Project is Closed 1 day Mon 7/23/18 Mon 7/23/18
Analyst
Analyst
Analyst
Documenter
Documenter
Documenter
Project Manager
Planner
Planner
Planner
Planner
Planner
Project Manager
Designer
Designer
Tester
Designer
Project Manager
IT Engineer
Database Developer
Database Developer
Programmer
IT Engineer
IT Engineer
Tester
Tester
Tester
Tester
Documenter,Trainer
Trainer
Trainer
Documenter
Documenter
Project Manager
Project Manager
2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12
January 11 March 1 April 21 June 11 August 1
Figure 1: Project Gantt chart
(Source: created by the author)
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.