This project management assignment focuses on the Riverina Agriculture and Lifetime Shows (RALS) project, a scenario involving Virtucon and Globex. The assignment details the development of an online ticketing system to address issues with long queues. The report is divided into several parts, including the Measurable Organizational Value (MOV), project scope management, Work Breakdown Structure (WBS) development, project activities, resource identification, cost and time estimations, risk analysis, quality management plan, and a closure plan. It outlines desired areas of impact, identifies different types of values, and develops appropriate metrics. The assignment also includes a Gantt chart illustrating the project timeline, a list of project resources, and a detailed WBS. Furthermore, it presents a risk management plan and a quality management plan. The project aims to improve customer satisfaction, streamline operations, and ensure financial viability through efficient online ticketing.
Document Page
Running head: PROJECT MANAGEMENT
Project Management: Riverina Agriculture and Lifetime Shows (RALS) Virtucon and Globex
Scenario
Name of the student:
Name of the university:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT MANAGEMENT
Table of Contents
Part 1: Measurable Organizational Value (MOV)...........................................................................3
1.1 Identified desired area of impact...........................................................................................4
1.2 Identification of different types of values..............................................................................6
1.3 Appropriate metrics development..........................................................................................6
1.4 Development of the timeframe for RALS project.................................................................7
1.5 Summary of MOV project...................................................................................................11
2. Part 2: Scope management of RALS project.............................................................................11
2.1 Developing project scope....................................................................................................11
2.2 List of project resources.......................................................................................................11
2.3 The details of resources.......................................................................................................13
3. Part 3..........................................................................................................................................14
3.1 Development of Work Breakdown Structure (WBS)..........................................................14
3.2 Identification of project activities........................................................................................15
3.3 Identification of project resources.......................................................................................17
3.4 Cost estimation for the tasks................................................................................................17
3.5 Estimation of time for RALS project...................................................................................21
4. Part 4: Risk analysis and project plan........................................................................................23
4.1 Project risk management plan..............................................................................................23
5. Part 5: Quality Management Plan..............................................................................................26
5.1 Philosophy of the project team............................................................................................26
5.2 Quality assurance for RALS project....................................................................................26
6. Part 6: Closure plan and evaluation...........................................................................................27
6.1 Development of closure checklist........................................................................................27
6.2 Development of project checklist outline............................................................................27
Bibliography..................................................................................................................................28
Document Page
2PROJECT MANAGEMENT
Part 1: Measurable Organizational Value (MOV)
Analyzing the Virtucon and Globex scenario it has been defined that the company is
willing to arrange a 3 days event named as Riverina Agriculture and Lifetime Shows (RALS) for
their consumers. The show mainly deals with the local businesses, suppliers of the agricultural
equipment suppliers and other lifetime products. The most important components those are
strictly required to be followed by the project developers include co –ordination for show stand,
live program display, catering and volunteers. The volunteers have thought about this planning in
the year of 2000 and the show is organizing by the organizers from 2000. With the number of
passing days the numbers of participants are also increasing accordingly thus the queue for ticket
booking is also increasing and the participants are losing their patients for this long queue. In
order to reduce these issues the organizers have decided to develop an online ticket booking
website for their consumers.
This report depicts the scope of the project including the project resources, allotted time
and estimated cost as well. In addition to this, for reducing the work pressure from the consumers
a work Breakdown structure is also developed by the program organizers. In order to implement
the RALS project successfully it is necessary for the project manager to allot proper time and
cost for the project. Apart from the time and cost management a quality management and risk
management plan is also developed in this report. Even team philosophy must be set properly for
the successful execution of the RALS project.
1.1 Identified desired area of impact
Desired areas Ranking Impact
Strategies 2 Proper business and project
Document Page
3PROJECT MANAGEMENT
development strategies will
help the project manager to
gain measurable business
success and even huge number
of consumers throughout
(Pemsel & Wiewiora,
2013).
Customers 3 Customers are referred to as
the most important asset for
any business thus they are
needed to be satisfied properly
by the services and products
of any business. With user
friendly online ticket booking
website the number of
participants will be increased
accordingly.
Operational 4 With the help of functional
and operational excellence the
consumers will be able to get
handle the online ticket
booking system properly
(Schwalbe, 2015).
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT MANAGEMENT
Financial 1 Financial support is the most
important thing for the
development of RALS project.
With the help of this capital
invested the additional
resources could be added to
the system including the
security and user friendly
mechanism as well (Sanchez,
2015)
Social 5 The communication approach
of between the project
manager and the other project
team members and even with
the sponsors as well could be
improved for adopting social
components.
1.2 Identification of different types of values
Better: The online ticket booking system will help the project manager to serve better
quality and user friendly service to their participants.
Document Page
5PROJECT MANAGEMENT
Faster: In the online ticket booking system the participants need not to wait in the queue
for getting the tickets rather the entire system will become faster that the manual ticket booking
system.
Cheaper: The number of manpower will get reduced after the implementation of online
ticket booking system because computerized system does not required human power.
1.3 Appropriate metrics development
In order to implement the RALS project successfully, it is necessary for the project
manager to contract with proper project stakeholders. For this project the identified project
stakeholders are as follows:
Name of the stakeholders Expectation
Project manager To complete the project on time within
estimated budget
Finance manager Expect to complete the project within the
estimated budget even if additional resources
are required.
Operation manager To provide proper operational and functional
excellence to the consumers
Application programming manager Provide appreciable application of the website
HR manager To manage the issues of the manpower and all
project team members
Project team members To complete the project on time
Document Page
6PROJECT MANAGEMENT
1.4 Development of the timeframe for RALS project
WBS Task Name Duration Start Finish Predecessors Resource Names
Cost
Variance
0
RALS
timeframe
development
163
days
Fri
10/6/17
Tue
5/22/18
$28,624.00
1
Project
initiation phase
51 days
Fri
10/6/17
Fri
12/15/17
$9,664.00
1.1
Conceptualiz
ing the details of
RALS project
5 days
Fri
10/6/17
Thu
10/12/17
Project manager $800.00
1.2
Developing
project charter
18 days
Fri
10/13/17
Tue
11/7/17
$3,744.00
1.2.1
Identificati
on of business
requirements
6 days
Fri
10/13/17
Fri
10/20/17
2
business
analyst,project
sponsor
$1,584.00
1.2.2
Understand
ing project
specification
5 days
Mon
10/23/17
Fri
10/27/17
4
business
analyst,project
sponsor
$1,320.00
1.2.3 Arrangeme 7 days Mon Tue 5 business analyst $840.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
nt of meeting
between the
project manager
and project team
members
10/30/17 11/7/17
1.3
Vendor
appointment
10 days
Wed
11/8/17
Tue
11/21/17
$1,440.00
1.3.1
Identificati
on vendors
4 days
Wed
11/8/17
Mon
11/13/17
6 operation manager $576.00
1.3.2
Ability
analysis of the
vendors
according to the
budget
6 days
Tue
11/14/17
Tue
11/21/17
8 operation manager $864.00
1.4
Feasibility
study
10 days
Wed
11/22/17
Tue
12/5/17
9 operation manager $1,440.00
1.5
Time
management for
RALS Project
8 days
Wed
12/6/17
Fri
12/15/17
10
finance
manager,Project
manager
$2,240.00
1.6 Milestone 1:
Completion of
0 days Fri
12/15/17
Fri
12/15/17
11 Project manager $0.00
Document Page
8PROJECT MANAGEMENT
project initiation
phase
2
Project
planning phase
52 days
Mon
12/18/17
Tue
2/27/18
$7,088.00
2.1
Understandin
g the website
details for online
ticketing system
10 days
Mon
12/18/17
Fri
12/29/17
12
application
programming
manager,operation
manager
$2,720.00
2.2 Prototyping 11 days
Mon
1/1/18
Mon
1/15/18
14
application
programming
manager
$1,408.00
2.3
website
testing
10 days
Tue
1/16/18
Mon
1/29/18
2,15
application
programming
manager
$1,280.00
2.4
Customer
requirement
analysis
9 days
Tue
1/30/18
Fri
2/9/18
16 HR manager $720.00
2.5
Based on the
feedback website
development
12 days
Mon
2/12/18
Tue
2/27/18
17 HR manager $960.00
Document Page
9PROJECT MANAGEMENT
2.6
Milestone 2:
Completion of
project
planning phase
0 days
Tue
2/27/18
Tue
2/27/18
18 Project manager $0.00
3
Project
execution phase
54 days
Wed
2/28/18
Mon
5/14/18
$10,704.00
3.1
Final website
development
7 days
Wed
2/28/18
Thu
3/8/18
19
application
programming
manager
$896.00
3.2
website
modeling
6 days
Fri
3/9/18
Fri
3/16/18
21
application
programming
manager,operation
manager
$1,632.00
3.3 Coding 6 days
Mon
3/19/18
Mon
3/26/18
22
application
programming
manager,operation
manager
$1,632.00
3.4 Unit testing 7 days
Tue
3/27/18
Wed
4/4/18
23 project tester $1,008.00
3.5 Integration 5 days Thu Wed 24 project tester $720.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT MANAGEMENT
testing 4/5/18 4/11/18
3.6
Final
implementation
6 days
Thu
4/12/18
Thu
4/19/18
25 Project manager $960.00
3.7
Incorporatin
g online
payment options
8 days
Fri
4/20/18
Tue
5/1/18
26
finance
manager,operation
manager,application
programming
manager
$3,136.00
3.8
Review final
requirements
9 days
Wed
5/2/18
Mon
5/14/18
27 HR manager $720.00
3.9
Milestone 3:
Completion of
project
execution phase
0 days
Mon
5/14/18
Mon
5/14/18
28 Project manager $0.00
4
Project
closure phase
6 days
Tue
5/15/18
Tue
5/22/18
$1,168.00
4.1
Final
documentation
2 days
Tue
5/15/18
Wed
5/16/18
29 Project manager $320.00
4.2 Post project 2 days Thu Fri 31 Project manager, $560.00
Document Page
11PROJECT MANAGEMENT
evaluation 5/17/18 5/18/18 business analyst
4.3
Stakeholder
signoff
2 days
Mon
5/21/18
Tue
5/22/18
32 project sponsor $288.00
4.4
Milestone 4:
Completion of
project closure
phase
0 days
Tue
5/22/18
Tue
5/22/18
33 Project manager $0.00