This project report outlines a comprehensive plan for the renovation and upgrade of Royale Pizza, aiming to enhance its dining facilities and increase its customer base. The report begins with an abstract that highlights the project's objectives, followed by a detailed table of contents. The project involves various phases, including design, procurement and delivery, construction, and installation, each with specific tasks, durations, and assigned resources. A Work Breakdown Structure (WBS) is provided to organize the project into manageable activities, along with a schedule that defines milestones and due dates. The project's scope encompasses improvements ranging from shop flooring to equipment installation, ensuring deliverables are completed within the allocated timeframe. The project management methodology includes stakeholder identification, task assignment, and monitoring to ensure the project's success, with project supervisors overseeing product testing before the shop's reopening. The report concludes with a discussion of the project's goals, scope, and delivery methodology, providing a structured approach to project management within the context of a restaurant renovation.
Document Page
Schedule Plan
Milestons Due Dates
1. Getting approval for the design
2. Completion of procurement and delivery phase
3. Completion of construction phase
4. Completion of installation and painting phase
28-03-19
23-05-19
20-06-19
15-08-19
WBS
ID
Activity
description
Precedence Duration
estimate
Resource Cost
estimate
0 Pizza shop
renovation
6 mons AU$ 40,000.00
1 Design phase 1 mon AU$ 5,000.00
1 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1.1 Undertaking
meeting with the
workers of the store
1 day Project management
consultant
AU$ 500.00
1.2 Researching the
problem
2 4 days Project manager AU$ 500.00
1.3 Identifying
solution
3 5 days Project management
consultant, Project manager
AU$ 500.00
1.4 Creating
schematic design
4 10 days Designer AU$ 3,500.00
1.5 Milestone 1:
Getting approval for
the design
5 0 days AU$ 0.00
2 Procurement
and delivery phase
2 mons AU$ 18,000.00
2.1 Determining
products and
5 5 days Procurement manager AU$ 400.00
2 | P a g e
Document Page
services
2.2 Hiring suppliers 8 9 days Procurement manager,
Project management
consultant
AU$ 300.00
2.3 Buying different
types of materials
and equipment
9 10 days Supplier AU$ 12,000.00
2.4 Performing
quality assurance
10 8 days Quality analyst AU$ 4,300.00
2.5 Analyzing the
results and margins
11 8 days Procurement manager,
Project management
consultant
AU$ 1,000.00
2.6 Milestone 2:
Completion of
procurement and
delivery phase
12 0 days AU$ 0.00
3 | P a g e
Document Page
3 Construction
phase
1 mon AU$ 7,000.00
3.1 Completing the
work of flooring
12 5 days Civil engineer, Construction
manager
AU$ 2,000.00
3.2 Professional
cleaning of kitchen
15 4 days Construction manager AU$ 2,000.00
3.3 Removing the
shop from rear area
for providing
cooking space
16 6 days Civil engineer, Construction
manager
AU$ 1,500.00
3.4 Adding
additional dining
space
17 4 days Construction manager AU$ 1,000.00
3.5 Undertaking
inspection
18 1 day Inspection officer AU$ 500.00
3.6 Milestone 3: 19 0 days AU$ 0.00
4 | P a g e
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Completion of
construction phase
4 Installation
phase
2 mons AU$ 10,000.00
4.1 Installation of
air conditioning
system
20 4 days Installer AU$ 2,000.00
4.2 Dust free
painting
22 27 days Painter AU$ 5,500.00
4.3 Equipment
installation
23 5 days Installer AU$ 1,500.00
4.4 Hardware and
software installation
24 4 days Installer, Quality analyst AU$ 1,000.00
4.5 Milestone 4:
Completion of
installation and
25 0 days AU$ 0.00
5 | P a g e
Document Page
painting phase
6 | P a g e