Structural Steel Snagging

   

Added on  2022-09-07

13 Pages989 Words17 Views
Running head: PROJECT MANAGEMENT
Project management
Name of the Student
Name of the University
Author’s Note
Structural Steel    Snagging_1
PROJECT MANAGEMENT
1
Table of Contents
1. Gantt chart and WBS as per weighted expected time duration..................................................2
1.1 Calculation of time................................................................................................................2
1.2 Gantt chart.............................................................................................................................3
1.3 WBS.......................................................................................................................................4
2. Reflecting dependencies..............................................................................................................5
3. Assigning resources, materials and facilities...............................................................................6
4. Critical path.................................................................................................................................7
5. Resolving resource overload........................................................................................................8
6. Budget..........................................................................................................................................8
6.1 Total budget...........................................................................................................................8
6.2 Cashflow..............................................................................................................................11
Bibliography..................................................................................................................................12
Structural Steel    Snagging_2
PROJECT MANAGEMENT
2
1. Gantt chart and WBS as per weighted expected time duration
1.1 Calculation of time
Activity
Optimist
ic
Pessimisti
c
Most
likely
Weighted expected time
duration
Steel framework design 13 19 16 17.5
Detail design 20 30 25 27.5
Material procurement 9 12 9.75 11.1
Steel fabrication 18 28 22 25.3
Sub-assembly batching for
shipment 14 17 13 15.8
Road transport to railhead 2 8 5 6.5
Rail transport to site 2.5 5 3.75 4.4
Steel structure erection 3 7 6 6.2
Structural steel snagging 1 6 2 4.5
Framework inspection 2 2 2 2
Steel roof design 10 18 14 16.0
Detail design 22 27 24.5 25.8
Test section procurement 5.4 11.4 8.4 9.9
Test section build 4 6 5 5.5
Roof testing 1 3 2 2.5
Roof design updates 6 8 7 7.5
Material procurement 7.5 12.75 8.55 11.2
Roof section fabrication 18 20 19 19.5
Sub-assembly batching for
shipment 7 16 9 13.3
Road transport to railhead 3 6 4.5 5.3
Rail transport to site 4 8 6 7
Roof build 5 10 7 8.7
Roof structure snagging 1 4 2 3.2
Framework inspection 1 4 2.5 3.3
Structural Steel    Snagging_3
PROJECT MANAGEMENT
3
1.2 Gantt chart
Figure 1: Gantt chart
(Source: Created by Author)
Structural Steel    Snagging_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
International Journal of Commerce and Management
|7
|652
|11

Project Management
|7
|765
|32

Project Management: Time Inc.
|16
|2347
|145

BNV6047 Project Management Assignment
|6
|1309
|304

Project Management: Benefits Administration Software
|4
|811
|299

Project Progress Report 13 Project Scheduling: Network Diagram Activity Data
|15
|1200
|349