A.. Activities entry in weeks.
4 Pages
193 Words
293 Views
Added on 2019-09-21
Get Access
Get Access
Bookmark
Share
Related Documents
A.
Activities entry in weeks
Gantt chart
Critical path: A, C, F, H
The project direct cost $35,000.
B.
11,000 additional is shown below:
The total cost reached for the normal schedule is 134,000
Found this document preview useful?
Subscribe Now
Related Documents
Ms-Project Practical - PDF
lg
...
|
12
|
928
|
310
View document
Construction Sequence Analysis for Optimum Cost and Duration
lg
...
|
4
|
625
|
446
View document
Project Management - Desklib
lg
...
|
6
|
629
|
143
View document
Project Management: Critical Path, Iron Triangle, and Project Types
lg
...
|
10
|
2248
|
51
View document
PRMG-010 Project Planning and Control Teqniques
lg
...
|
14
|
1545
|
76
View document
Pert Analysis and Network Diagram - PDF
lg
...
|
13
|
1191
|
90
View document