A.. Activities entry in weeks.

4 Pages193 Words293 Views
   

Added on  2019-09-21

A.. Activities entry in weeks.

   Added on 2019-09-21

BookmarkShareRelated Documents
A.Activities entry in weeksGantt chartCritical path: A, C, F, H
A.. Activities entry in weeks._1
The project direct cost $35,000.B.11,000 additional is shown below:The total cost reached for the normal schedule is 134,000