Running head: ADVANCED INFO SYSTEMS DESIGN Advanced Info systems Design Name of the Student Name of the University Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 ADVANCED INFO SYSTEMS DESIGN Table of Contents 1. Project Plan......................................................................................................................2 1.1. Project background...................................................................................................2 1.2. Project Scope............................................................................................................2 1.3. Aims and Objectives.................................................................................................3 1.4. Work Breakdown Structure of the Project................................................................3 1.5. Project Timeline........................................................................................................6 1.6. Project dependencies................................................................................................9 2. System Design Document..............................................................................................10 2.1. Introduction.............................................................................................................10 2.2. Requirements..........................................................................................................10 2.3. Constraints and Assumptions.................................................................................11 2.3.1. Project Constraints...........................................................................................11 2.3.2. Assumptions....................................................................................................11 2.4. Resources................................................................................................................12 2.5. System Overview....................................................................................................12 2.6. Conclusion..............................................................................................................14 References..........................................................................................................................15
2 ADVANCED INFO SYSTEMS DESIGN 1. Project Plan 1.1. Project background The project is based on planning, designing and implementing and Enterprise resource planning system for ABC Pvt. Ltd. for integrating the entire business process. The new system will automate the existing processes thus saving a lot of time and money. ABC Pvt. Ltd. manufactures and supplies stationary goods across the country. There are almost 1000 employees in each branch and the company is growing as well. Therefore, in order to manage the work processes of the organization, development of an ERP system is proposed. The existing manual record keeping process of the organization is prone to human errors and will prevent data duplication as well. Data duplication is a persisting problem of manual record keeping as the person who is entering the data might not have a proper knowledge whether the data is already recorded or not. Furthermore, it becomes extremely difficult to keep a track of the items sold, ordered or processed in case of manual record keeping. Therefore, the project will be extremely advantageous to implement in ABC Pvt. Ltd. The ERP implementation project will however need proper planning and designing of the system according to the requirements of the organization (Bassil, 2012). This is a bit complex project as enterprise resource planning software needs high level of accuracy and proper implementation as the entire process of sales is dependent on a software. Any error in the software might lead to erroneous data processing or data loss. Therefore, the project needs adequate implementation time and precision. 1.2. Project Scope
3 ADVANCED INFO SYSTEMS DESIGN The project is expected to reduce the number of errors in manual data processing system. The Enterprise resource planning system is expected to resolve the existing issues persisting in the organization and is expected to contribute to the smooth business processing. Although the cost of implementation of the Enterprise Resource planning system is high it will provide eventually provide a cost effective solution to the organization by automating the entire process and reducing the need of manual labor (Matende & Ogao, 2013). Furthermore, the enterprise resource planning system to be developed will integrate the business processes of every branch of ABC Pvt. Ltd. thus increasing the data transparency. Therefore, the project is feasible and acceptable to consider for ABC Pvt. Ltd (Heagney, 2016). 1.3. Aims and Objectives The aim of this project is to develop a suitable Enterprise Resource Planning system for ABC Pvt. Ltd (Schwalbe, 2015). The objectives of this project are as follows- 1. To identify the proper requirements for ERP implementation 2. To understand the need of ERP in ABC Pvt. Ltd. 3. To design a proper ERP system for ABC Pvt. Ltd. 4. To implement the ERP system in ABC Pvt. Ltd. 1.4. Work Breakdown Structure of the Project The work breakdown structure of the project evaluates the different stages a project is needed to undergo for its successful completion. The following table gives an overview of the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 ADVANCED INFO SYSTEMS DESIGN number of stages associated with the ERP implementation project of ABC Pvt. Ltd (Larson and Gray, 2013). WBSTask NameDurationStartFinish 0ERP Implementation279 daysThu 01-03-18Tue 26-03-19 1Project Starts0 daysThu 01-03-18Thu 01-03-18 2Planning35 daysThu 01-03-18Wed 18-04-18 2.1Planning the Project Work10 daysThu 01-03-18Wed 14-03-18 2.2Feasibility Study20 daysThu 15-03-18Wed 11-04-18 2.3Budget estimation5 daysThu 12-04-18Wed 18-04-18 2.4Drafting the Project Plan0 daysWed 18-04-18Wed 18-04-18 3Requirement Analysis33 daysThu 19-04-18Mon 04-06-18 3.1Analysis of Hardware and Software requirements10 daysThu 19-04-18Wed 02-05-18 3.2Evaluation of Human Resources8 daysThu 03-05-18Mon 14-05-18 3.3Evaluation of the Financial Resources10 daysTue 15-05-18Mon 28-05-18 3.4Analysis of the project Schedule5 daysTue 29-05-18Mon 04-06-18 3.5Drafting the requirements for approval0 daysMon 04-06-18Mon 04-06-18 4Designing95 daysTue 05-06-18Mon 15-10-18 4.1Designing the ERP to be implemented15 daysTue 05-06-18Mon 25-06-18 4.2Development of project design10 daysTue 26-06-18Mon 09-07-18 4.3Use case designing5 daysTue 10-07-18Mon 16-07-18 4.4design of class diagram5 daysTue 17-07-18Mon 23-07-18 4.5Designing the System interface of the Software20 daysTue 24-07-18Mon 20-08-18 4.6Designing the phase contingency for the project10 daysTue 21-08-18Mon 03-09-18 4.7Creation of a prototype for approval30 daysTue 04-09-18Mon 15-10-18 4.8Drafting the Report0 daysMon 15-10-18Mon 15-10-18 5Development/Implementation37 daysTue 16-10-18Wed 05-12-18 5.1software coding20 daysTue 16-10-18Mon 12-11-18 5.2inserting data on the database10 daysTue 13-11-18Mon 26-11-18 5.3linking the system with database5 daysTue 27-11-18Mon 03-12-18 5.4Project re-estimation (if required)2 daysTue 04-12-18Wed 05-12-18 6Testing52 daysThu 06-12-18Fri 15-02-19 6.1Developing the checklist7 daysThu 06-12-18Fri 14-12-18 6.2Interface testing5 daysMon 17-12-18Fri 21-12-18 6.3Unit testing15 daysMon 24-12-18Fri 11-01-19 6.4user acceptance testing10 daysMon 14-01-19Fri 25-01-19 6.5system testing15 daysMon 28-01-19Fri 15-02-19
5 ADVANCED INFO SYSTEMS DESIGN 6.6System ready for release0 daysFri 15-02-19Fri 15-02-19 7Maintenance27 daysMon 18-02-19Tue 26-03-19 7.1System Installation5 daysMon 18-02-19Fri 22-02-19 7.2Training the Users7 daysMon 25-02-19Tue 05-03-19 7.3User testing5 daysWed 06-03-19Tue 12-03-19 7.4System handover2 daysWed 13-03-19Thu 14-03-19 7.5Payment Completion2 daysFri 15-03-19Mon 18-03-19 7.6Resource Release5 daysTue 19-03-19Mon 25-03-19 7.7Client Sign off1 dayTue 26-03-19Tue 26-03-19 8Project Ends0 daysTue 26-03-19Tue 26-03-19 Table 1: Representing the Work breakdown Structure of the Project The above table is representing the different stages of the project ERP implementation associated with ABC Pvt. Ltd. The scheduled of the project including the start date might change according to the requirements of the project. The project implementation will start only after the approval of the project plan. The WBS of the project is represented in pictorial form below- ERP Implementation Project StartsPlanning Planning the Project Work Feasibility StudyBudget estimation Drafting the Project Plan Requirement Analysis Anlysis of Hardware and Software requirements Evaluation of Human Resources Evaluation of the Finaancial Resources Analysis of the project Schedule Drafting the requirements for approval Designing Designing the ERP to be implemented Development of projetc design Use case designing design of class diagram Designing the System interface of the Software Designing the phase contingency for the project Creation of a prototype for approval Drafting the Report Development/Implementation software coding inserting data on the database linking the system with database Project re-estimation (if required) Testing Devoloping the checklistInterface testing Unit testing user acceptance testing system testing System ready for release Maintainance System Installation Training the Users User testing System handover Payment Completion Resource Release Client Sign off Project Ends Figure 1: Representing the Work Breakdown Structure of the project (Source: created by author using WBS Schedule Pro and MS Project)
6 ADVANCED INFO SYSTEMS DESIGN The ERP implementation is a complex project and therefore, it requires adequate precision in implementation. Testing phase plays a major role in successful completion of the project and is very necessary to perform the system testing phase as if any bug is detected in this phase, it can be easily rectified before the project launch (Kerzner & Kerzner, 2017). The work breakdown structure represented above defines the works that are needed to be performed in order to achieve the project deliverables. 1.5. Project Timeline The project timeline is important to communicate the essential milestone associated with a project. The following project timeline provides an outline of the major deliverables of the project ERP implementation in chronological sequence. Task NameDurationStartFinish ERP Implementation279 daysThu 01-03-18Tue 26-03-19 Project Starts0 daysThu 01-03-18Thu 01-03-18 Planning35 daysThu 01-03-18Wed 18-04-18 Planning the Project Work10 daysThu 01-03-18Wed 14-03-18 Feasibility Study20 daysThu 15-03-18Wed 11-04-18 Budget estimation5 daysThu 12-04-18Wed 18-04-18 Drafting the Project Plan0 daysWed 18-04-18Wed 18-04-18 Requirement Analysis33 daysThu 19-04-18Mon 04-06-18 Analysis of Hardware and Software requirements10 daysThu 19-04-18Wed 02-05-18 Evaluation of Human Resources8 daysThu 03-05-18Mon 14-05-18 Evaluation of the Financial Resources10 daysTue 15-05-18Mon 28-05-18 Analysis of the project Schedule5 daysTue 29-05-18Mon 04-06-18 Drafting the requirements for approval0 daysMon 04-06-18Mon 04-06-18 Designing95 daysTue 05-06-18Mon 15-10-18 Designing the ERP to be implemented15 daysTue 05-06-18Mon 25-06-18 Development of project design10 daysTue 26-06-18Mon 09-07-18 Use case designing5 daysTue 10-07-18Mon 16-07-18 design of class diagram5 daysTue 17-07-18Mon 23-07-18 Designing the System interface of the Software20 daysTue 24-07-18Mon 20-08-18 Designing the phase contingency for the10 daysTue 21-08-18Mon 03-09-18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 ADVANCED INFO SYSTEMS DESIGN project Creation of a prototype for approval30 daysTue 04-09-18Mon 15-10-18 Drafting the Report0 daysMon 15-10-18Mon 15-10-18 Development/Implementation37 daysTue 16-10-18Wed 05-12-18 software coding20 daysTue 16-10-18Mon 12-11-18 inserting data on the database10 daysTue 13-11-18Mon 26-11-18 linking the system with database5 daysTue 27-11-18Mon 03-12-18 Project re-estimation (if required)2 daysTue 04-12-18Wed 05-12-18 Testing52 daysThu 06-12-18Fri 15-02-19 Developing the checklist7 daysThu 06-12-18Fri 14-12-18 Interface testing5 daysMon 17-12-18Fri 21-12-18 Unit testing15 daysMon 24-12-18Fri 11-01-19 user acceptance testing10 daysMon 14-01-19Fri 25-01-19 system testing15 daysMon 28-01-19Fri 15-02-19 System ready for release0 daysFri 15-02-19Fri 15-02-19 Maintenance27 daysMon 18-02-19Tue 26-03-19 System Installation5 daysMon 18-02-19Fri 22-02-19 Training the Users7 daysMon 25-02-19Tue 05-03-19 User testing5 daysWed 06-03-19Tue 12-03-19 System handover2 daysWed 13-03-19Thu 14-03-19 Payment Completion2 daysFri 15-03-19Mon 18-03-19 Resource Release5 daysTue 19-03-19Mon 25-03-19 Client Sign off1 dayTue 26-03-19Tue 26-03-19 Project Ends0 daysTue 26-03-19Tue 26-03-19 Table 2: Representing the Project Timeline (The project milestone are marked in green) The Gantt chart showing a pictorial representation of the Project Timeline is shown below-
8 ADVANCED INFO SYSTEMS DESIGN Figure 2: Representing the Gantt chart of the shifting project (Source: Generated by Author using MS project)
9 ADVANCED INFO SYSTEMS DESIGN Since the Project is following a waterfall approach, end of each task marks the beginning of the next (Saxena & Upadhyay 2016). The project will be following a planned approach; however, if required, the project might include certain changes while its implementation. 1.6. Project dependencies The successful implementation of the project depends on the proper evaluation of the project plan and approval of the project design. For development of a proper design it is essential to evaluate the requirements of the project, and therefore, the project success is largely dependent on the requirement analysis phase of the project. Furthermore, since the project will be following a waterfall approach, every stages of the project will depend on the previous phase (McCormick, 2012).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 ADVANCED INFO SYSTEMS DESIGN 2. System Design Document 2.1. Introduction The system design document for the project is essential to develop as it gives an overview of the system to be developed in an architectural level. It gives a clear idea of the services, hardware and software requirements and the design of a product. The system design document for the ERP implementation project outlines the project requirements, constraints associated with the project, the resource requirements and a detailed overview of the system to be developed. The system design document will provide a clear idea of the project requirements and the system is to be delivered after the successful implementation of the project. 2.2. Requirements The project aims at development of an integrated ERP system for ABC Pvt. Ltd. that will operate in real time. Integration of all the processes running within the organization will be possible only if a common database is maintained that will support all the application. The system shall include an administrative portal, data update and data delete option. The portal will allow only authorized users in accessing the system as a necessary security measure. The system interference shall be simple so that it can be easily operated by the employees of the ABC Pvt. Ltd.Development of a transactional database is another major project requirement. The system shall include a search option for easy query and report generation. Furthermore, the system shall incorporate automated mail generation and instant messaging to keep the management informed about the number of orders processed. This is a part of workflow management that includes logical data flow and data updates to the senior management of the organization. The interface of
11 ADVANCED INFO SYSTEMS DESIGN ERP system shall include the read only data processing option for preventing data duplication (Tsai et al., 2012). 2.3. Constraints and Assumptions 2.3.1. Project Constraints The systemconstraintsof theEnterpriseResourcePlanning systemthat istobe developed for ABC Pvt. Ltd are as follows- 1.Everyprocessesrunningwithintheorganizationwillbeautomatedbythe implementation of this ERP system. However, the system might subject to malfunctioning, leading to erroneous data processing. The malfunctioning of the ERP system might occur due a fault in software implementation (Leon, 2014). 2. The ERP system to be developed will be subjected to proper maintenance for maintaining its proper functionality (Shaul & Tauber, 2013). 3. The success of the project will largely depend on the proper formulation of the project plan and evaluation of the project requirements. 2.3.2. Assumptions The assumptions of the project are as follows- 1. It is assumed that the project requirements are properly analyzed prior to development of project plan. 2.Itisassumedthataproperprojectenvironmentissetpriortotheproject implementation
12 ADVANCED INFO SYSTEMS DESIGN 3. It is assumed that the project can be successfully completed within the set budget. 4. It is assumed that the resource allocation of the project is properly done. 5.It is assumed that the time allocated for the project is adequate for its successful completion. 6. It is assumed that the business will be benefited by the implementation of the enterprise resource planning system (Matende & Ogao, 2013). These are the basic constraints and assumptions associated with this project. The chosen waterfall methodology of the project is considered to be the correct approach of project implementation. 2.4. Resources The resources required for the ERP implementation project are as follows- 1. The major resource requirement of the project is development of the project team for successful project implementation 2. Different hardware and software requirements for ERP implementation 3. Allocation of work force according to the different project stages. 2.5. System Overview The ERP system to be developed for ABC Pvt. Ltd. is expected to integrate all the business processes running within the organization (Almutairi, 2015). The ERP system to be developed will organize and integrate the different functional areas of the organization such as
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13 ADVANCED INFO SYSTEMS DESIGN logistics, production, finance and accounting. Furthermore, the ERP to be developed is expected to make optimum use of organizational resources. The entire system will be integrated and will incorporate one database, one application and one user interface for easy access of the system. The diagrammatic representation of the ERP system is shown below- Figure 3: Representing the ERP system to be implemented (Source: Yang, Liang & Avgeriou, 2016) The above figure gives a clear idea of the different processes that the enterprise resource planning system will manage in ABC Pvt. Ltd. The design of the ERP shall be very simple and efficient.
14 ADVANCED INFO SYSTEMS DESIGN The project design phase will further evaluate the use case and class diagram developed for the enterprise resource planning system to understand the functionality of ERP system (Mir & Pinnington, 2014). 2.6. Conclusion Therefore, from the above discussion it can be concluded that system design document plays a major role in successful implementation of a project. The system design document evaluates the different assumptions, constraints and resource requirements associated with the project. This document is essential for developing the initial designing of the project.
15 ADVANCED INFO SYSTEMS DESIGN References Almutairi, M. K. M. (2015). Enterprise resource Planning ERP. Bassil, Y. (2012). A simulation model for the waterfall software development life cycle.arXiv preprint arXiv:1205.6904. Heagney, J. (2016).Fundamentals of project management. AMACOM Div American Mgmt Assn. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Larson, E.W. and Gray, C., (2013).Project management: The managerial process with MS project. McGraw-Hill. Leon, A. (2014).Enterprise resource planning. McGraw-Hill Education. Matende, S., & Ogao, P. (2013). Enterprise resource planning (ERP) system implementation: a case for user participation.Procedia Technology,9, 518-526. McCormick, M. (2012). Waterfall vs. Agile methodology.MPCS, N/A. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217. Saxena, A., & Upadhyay, P. (2016). Waterfall vs. prototype: Comparative study of sdlc.Imperial Journal of Interdisciplinary Research,2(6).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16 ADVANCED INFO SYSTEMS DESIGN Schwalbe, K., (2015).Information technology project management. Cengage Learning. Shaul, L., & Tauber, D. (2013). Critical success factors in enterprise resource planning systems: Review of the last decade.ACM Computing Surveys (CSUR),45(4), 55. Tsai, W. H., Lee, P. L., Shen, Y. S., & Lin, H. L. (2012). A comprehensive study of the relationshipbetweenenterpriseresourceplanningselectioncriteriaandenterprise resource planning system success.Information & Management,49(1), 36-46. Yang, C., Liang, P., & Avgeriou, P. (2016). A survey on software architectural assumptions. Journal of Systems and Software, 113, 362-380.