Running head: ADVANCED INFO SYSTEMS DESIGN
Advanced Info systems Design
Name of the Student
Name of the University
Author Note
Advanced Info systems Design
Name of the Student
Name of the University
Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
ADVANCED INFO SYSTEMS DESIGN
Table of Contents
1. Project Plan......................................................................................................................2
1.1. Project background...................................................................................................2
1.2. Project Scope............................................................................................................2
1.3. Aims and Objectives.................................................................................................3
1.4. Work Breakdown Structure of the Project................................................................3
1.5. Project Timeline........................................................................................................6
1.6. Project dependencies................................................................................................9
2. System Design Document..............................................................................................10
2.1. Introduction.............................................................................................................10
2.2. Requirements..........................................................................................................10
2.3. Constraints and Assumptions.................................................................................11
2.3.1. Project Constraints...........................................................................................11
2.3.2. Assumptions....................................................................................................11
2.4. Resources................................................................................................................12
2.5. System Overview....................................................................................................12
2.6. Conclusion..............................................................................................................14
References..........................................................................................................................15
ADVANCED INFO SYSTEMS DESIGN
Table of Contents
1. Project Plan......................................................................................................................2
1.1. Project background...................................................................................................2
1.2. Project Scope............................................................................................................2
1.3. Aims and Objectives.................................................................................................3
1.4. Work Breakdown Structure of the Project................................................................3
1.5. Project Timeline........................................................................................................6
1.6. Project dependencies................................................................................................9
2. System Design Document..............................................................................................10
2.1. Introduction.............................................................................................................10
2.2. Requirements..........................................................................................................10
2.3. Constraints and Assumptions.................................................................................11
2.3.1. Project Constraints...........................................................................................11
2.3.2. Assumptions....................................................................................................11
2.4. Resources................................................................................................................12
2.5. System Overview....................................................................................................12
2.6. Conclusion..............................................................................................................14
References..........................................................................................................................15
2
ADVANCED INFO SYSTEMS DESIGN
1. Project Plan
1.1. Project background
The project is based on planning, designing and implementing and Enterprise resource
planning system for ABC Pvt. Ltd. for integrating the entire business process. The new system
will automate the existing processes thus saving a lot of time and money. ABC Pvt. Ltd.
manufactures and supplies stationary goods across the country. There are almost 1000 employees
in each branch and the company is growing as well. Therefore, in order to manage the work
processes of the organization, development of an ERP system is proposed. The existing manual
record keeping process of the organization is prone to human errors and will prevent data
duplication as well. Data duplication is a persisting problem of manual record keeping as the
person who is entering the data might not have a proper knowledge whether the data is already
recorded or not. Furthermore, it becomes extremely difficult to keep a track of the items sold,
ordered or processed in case of manual record keeping. Therefore, the project will be extremely
advantageous to implement in ABC Pvt. Ltd.
The ERP implementation project will however need proper planning and designing of the
system according to the requirements of the organization (Bassil, 2012). This is a bit complex
project as enterprise resource planning software needs high level of accuracy and proper
implementation as the entire process of sales is dependent on a software. Any error in the
software might lead to erroneous data processing or data loss. Therefore, the project needs
adequate implementation time and precision.
1.2. Project Scope
ADVANCED INFO SYSTEMS DESIGN
1. Project Plan
1.1. Project background
The project is based on planning, designing and implementing and Enterprise resource
planning system for ABC Pvt. Ltd. for integrating the entire business process. The new system
will automate the existing processes thus saving a lot of time and money. ABC Pvt. Ltd.
manufactures and supplies stationary goods across the country. There are almost 1000 employees
in each branch and the company is growing as well. Therefore, in order to manage the work
processes of the organization, development of an ERP system is proposed. The existing manual
record keeping process of the organization is prone to human errors and will prevent data
duplication as well. Data duplication is a persisting problem of manual record keeping as the
person who is entering the data might not have a proper knowledge whether the data is already
recorded or not. Furthermore, it becomes extremely difficult to keep a track of the items sold,
ordered or processed in case of manual record keeping. Therefore, the project will be extremely
advantageous to implement in ABC Pvt. Ltd.
The ERP implementation project will however need proper planning and designing of the
system according to the requirements of the organization (Bassil, 2012). This is a bit complex
project as enterprise resource planning software needs high level of accuracy and proper
implementation as the entire process of sales is dependent on a software. Any error in the
software might lead to erroneous data processing or data loss. Therefore, the project needs
adequate implementation time and precision.
1.2. Project Scope
3
ADVANCED INFO SYSTEMS DESIGN
The project is expected to reduce the number of errors in manual data processing system.
The Enterprise resource planning system is expected to resolve the existing issues persisting in
the organization and is expected to contribute to the smooth business processing. Although the
cost of implementation of the Enterprise Resource planning system is high it will provide
eventually provide a cost effective solution to the organization by automating the entire process
and reducing the need of manual labor (Matende & Ogao, 2013). Furthermore, the enterprise
resource planning system to be developed will integrate the business processes of every branch
of ABC Pvt. Ltd. thus increasing the data transparency. Therefore, the project is feasible and
acceptable to consider for ABC Pvt. Ltd (Heagney, 2016).
1.3. Aims and Objectives
The aim of this project is to develop a suitable Enterprise Resource Planning system for
ABC Pvt. Ltd (Schwalbe, 2015).
The objectives of this project are as follows-
1. To identify the proper requirements for ERP implementation
2. To understand the need of ERP in ABC Pvt. Ltd.
3. To design a proper ERP system for ABC Pvt. Ltd.
4. To implement the ERP system in ABC Pvt. Ltd.
1.4. Work Breakdown Structure of the Project
The work breakdown structure of the project evaluates the different stages a project is
needed to undergo for its successful completion. The following table gives an overview of the
ADVANCED INFO SYSTEMS DESIGN
The project is expected to reduce the number of errors in manual data processing system.
The Enterprise resource planning system is expected to resolve the existing issues persisting in
the organization and is expected to contribute to the smooth business processing. Although the
cost of implementation of the Enterprise Resource planning system is high it will provide
eventually provide a cost effective solution to the organization by automating the entire process
and reducing the need of manual labor (Matende & Ogao, 2013). Furthermore, the enterprise
resource planning system to be developed will integrate the business processes of every branch
of ABC Pvt. Ltd. thus increasing the data transparency. Therefore, the project is feasible and
acceptable to consider for ABC Pvt. Ltd (Heagney, 2016).
1.3. Aims and Objectives
The aim of this project is to develop a suitable Enterprise Resource Planning system for
ABC Pvt. Ltd (Schwalbe, 2015).
The objectives of this project are as follows-
1. To identify the proper requirements for ERP implementation
2. To understand the need of ERP in ABC Pvt. Ltd.
3. To design a proper ERP system for ABC Pvt. Ltd.
4. To implement the ERP system in ABC Pvt. Ltd.
1.4. Work Breakdown Structure of the Project
The work breakdown structure of the project evaluates the different stages a project is
needed to undergo for its successful completion. The following table gives an overview of the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4
ADVANCED INFO SYSTEMS DESIGN
number of stages associated with the ERP implementation project of ABC Pvt. Ltd (Larson and
Gray, 2013).
WBS Task Name Duration Start Finish
0 ERP Implementation 279 days Thu 01-03-18 Tue 26-03-19
1 Project Starts 0 days Thu 01-03-18 Thu 01-03-18
2 Planning 35 days Thu 01-03-18 Wed 18-04-18
2.1 Planning the Project Work 10 days Thu 01-03-18 Wed 14-03-18
2.2 Feasibility Study 20 days Thu 15-03-18 Wed 11-04-18
2.3 Budget estimation 5 days Thu 12-04-18 Wed 18-04-18
2.4 Drafting the Project Plan 0 days Wed 18-04-18 Wed 18-04-18
3 Requirement Analysis 33 days Thu 19-04-18 Mon 04-06-18
3.1 Analysis of Hardware and Software
requirements 10 days Thu 19-04-18 Wed 02-05-18
3.2 Evaluation of Human Resources 8 days Thu 03-05-18 Mon 14-05-18
3.3 Evaluation of the Financial
Resources 10 days Tue 15-05-18 Mon 28-05-18
3.4 Analysis of the project Schedule 5 days Tue 29-05-18 Mon 04-06-18
3.5 Drafting the requirements for
approval 0 days Mon 04-06-18 Mon 04-06-18
4 Designing 95 days Tue 05-06-18 Mon 15-10-18
4.1 Designing the ERP to be
implemented 15 days Tue 05-06-18 Mon 25-06-18
4.2 Development of project design 10 days Tue 26-06-18 Mon 09-07-18
4.3 Use case designing 5 days Tue 10-07-18 Mon 16-07-18
4.4 design of class diagram 5 days Tue 17-07-18 Mon 23-07-18
4.5 Designing the System interface of
the Software 20 days Tue 24-07-18 Mon 20-08-18
4.6 Designing the phase contingency
for the project 10 days Tue 21-08-18 Mon 03-09-18
4.7 Creation of a prototype for approval 30 days Tue 04-09-18 Mon 15-10-18
4.8 Drafting the Report 0 days Mon 15-10-18 Mon 15-10-18
5 Development/Implementation 37 days Tue 16-10-18 Wed 05-12-18
5.1 software coding 20 days Tue 16-10-18 Mon 12-11-18
5.2 inserting data on the database 10 days Tue 13-11-18 Mon 26-11-18
5.3 linking the system with database 5 days Tue 27-11-18 Mon 03-12-18
5.4 Project re-estimation (if required) 2 days Tue 04-12-18 Wed 05-12-18
6 Testing 52 days Thu 06-12-18 Fri 15-02-19
6.1 Developing the checklist 7 days Thu 06-12-18 Fri 14-12-18
6.2 Interface testing 5 days Mon 17-12-18 Fri 21-12-18
6.3 Unit testing 15 days Mon 24-12-18 Fri 11-01-19
6.4 user acceptance testing 10 days Mon 14-01-19 Fri 25-01-19
6.5 system testing 15 days Mon 28-01-19 Fri 15-02-19
ADVANCED INFO SYSTEMS DESIGN
number of stages associated with the ERP implementation project of ABC Pvt. Ltd (Larson and
Gray, 2013).
WBS Task Name Duration Start Finish
0 ERP Implementation 279 days Thu 01-03-18 Tue 26-03-19
1 Project Starts 0 days Thu 01-03-18 Thu 01-03-18
2 Planning 35 days Thu 01-03-18 Wed 18-04-18
2.1 Planning the Project Work 10 days Thu 01-03-18 Wed 14-03-18
2.2 Feasibility Study 20 days Thu 15-03-18 Wed 11-04-18
2.3 Budget estimation 5 days Thu 12-04-18 Wed 18-04-18
2.4 Drafting the Project Plan 0 days Wed 18-04-18 Wed 18-04-18
3 Requirement Analysis 33 days Thu 19-04-18 Mon 04-06-18
3.1 Analysis of Hardware and Software
requirements 10 days Thu 19-04-18 Wed 02-05-18
3.2 Evaluation of Human Resources 8 days Thu 03-05-18 Mon 14-05-18
3.3 Evaluation of the Financial
Resources 10 days Tue 15-05-18 Mon 28-05-18
3.4 Analysis of the project Schedule 5 days Tue 29-05-18 Mon 04-06-18
3.5 Drafting the requirements for
approval 0 days Mon 04-06-18 Mon 04-06-18
4 Designing 95 days Tue 05-06-18 Mon 15-10-18
4.1 Designing the ERP to be
implemented 15 days Tue 05-06-18 Mon 25-06-18
4.2 Development of project design 10 days Tue 26-06-18 Mon 09-07-18
4.3 Use case designing 5 days Tue 10-07-18 Mon 16-07-18
4.4 design of class diagram 5 days Tue 17-07-18 Mon 23-07-18
4.5 Designing the System interface of
the Software 20 days Tue 24-07-18 Mon 20-08-18
4.6 Designing the phase contingency
for the project 10 days Tue 21-08-18 Mon 03-09-18
4.7 Creation of a prototype for approval 30 days Tue 04-09-18 Mon 15-10-18
4.8 Drafting the Report 0 days Mon 15-10-18 Mon 15-10-18
5 Development/Implementation 37 days Tue 16-10-18 Wed 05-12-18
5.1 software coding 20 days Tue 16-10-18 Mon 12-11-18
5.2 inserting data on the database 10 days Tue 13-11-18 Mon 26-11-18
5.3 linking the system with database 5 days Tue 27-11-18 Mon 03-12-18
5.4 Project re-estimation (if required) 2 days Tue 04-12-18 Wed 05-12-18
6 Testing 52 days Thu 06-12-18 Fri 15-02-19
6.1 Developing the checklist 7 days Thu 06-12-18 Fri 14-12-18
6.2 Interface testing 5 days Mon 17-12-18 Fri 21-12-18
6.3 Unit testing 15 days Mon 24-12-18 Fri 11-01-19
6.4 user acceptance testing 10 days Mon 14-01-19 Fri 25-01-19
6.5 system testing 15 days Mon 28-01-19 Fri 15-02-19
5
ADVANCED INFO SYSTEMS DESIGN
6.6 System ready for release 0 days Fri 15-02-19 Fri 15-02-19
7 Maintenance 27 days Mon 18-02-19 Tue 26-03-19
7.1 System Installation 5 days Mon 18-02-19 Fri 22-02-19
7.2 Training the Users 7 days Mon 25-02-19 Tue 05-03-19
7.3 User testing 5 days Wed 06-03-19 Tue 12-03-19
7.4 System handover 2 days Wed 13-03-19 Thu 14-03-19
7.5 Payment Completion 2 days Fri 15-03-19 Mon 18-03-19
7.6 Resource Release 5 days Tue 19-03-19 Mon 25-03-19
7.7 Client Sign off 1 day Tue 26-03-19 Tue 26-03-19
8 Project Ends 0 days Tue 26-03-19 Tue 26-03-19
Table 1: Representing the Work breakdown Structure of the Project
The above table is representing the different stages of the project ERP implementation
associated with ABC Pvt. Ltd. The scheduled of the project including the start date might change
according to the requirements of the project. The project implementation will start only after the
approval of the project plan. The WBS of the project is represented in pictorial form below-
ERP Implementation
Project Starts Planning
Planning the Project Work
Feasibility
StudyBudget estimation
Drafting the Project Plan
Requirement Analysis
Anlysis of Hardware and
Software requirements
Evaluation of Human
Resources
Evaluation of the
Finaancial Resources
Analysis of the project
Schedule
Drafting the requirements
for approval
Designing
Designing the ERP to be
implemented
Development of projetc
design
Use case designing
design of class diagram
Designing the System
interface of the Software
Designing the phase
contingency for the
project
Creation of a prototype for
approval
Drafting the Report
Development/Implementation
software coding
inserting data on the
database
linking the system with
database
Project re-estimation (if
required)
Testing
Devoloping the
checklistInterface testing
Unit testing
user acceptance testing
system testing
System ready for release
Maintainance
System Installation
Training the Users
User testing
System handover
Payment Completion
Resource Release
Client Sign off
Project Ends
Figure 1: Representing the Work Breakdown Structure of the project
(Source: created by author using WBS Schedule Pro and MS Project)
ADVANCED INFO SYSTEMS DESIGN
6.6 System ready for release 0 days Fri 15-02-19 Fri 15-02-19
7 Maintenance 27 days Mon 18-02-19 Tue 26-03-19
7.1 System Installation 5 days Mon 18-02-19 Fri 22-02-19
7.2 Training the Users 7 days Mon 25-02-19 Tue 05-03-19
7.3 User testing 5 days Wed 06-03-19 Tue 12-03-19
7.4 System handover 2 days Wed 13-03-19 Thu 14-03-19
7.5 Payment Completion 2 days Fri 15-03-19 Mon 18-03-19
7.6 Resource Release 5 days Tue 19-03-19 Mon 25-03-19
7.7 Client Sign off 1 day Tue 26-03-19 Tue 26-03-19
8 Project Ends 0 days Tue 26-03-19 Tue 26-03-19
Table 1: Representing the Work breakdown Structure of the Project
The above table is representing the different stages of the project ERP implementation
associated with ABC Pvt. Ltd. The scheduled of the project including the start date might change
according to the requirements of the project. The project implementation will start only after the
approval of the project plan. The WBS of the project is represented in pictorial form below-
ERP Implementation
Project Starts Planning
Planning the Project Work
Feasibility
StudyBudget estimation
Drafting the Project Plan
Requirement Analysis
Anlysis of Hardware and
Software requirements
Evaluation of Human
Resources
Evaluation of the
Finaancial Resources
Analysis of the project
Schedule
Drafting the requirements
for approval
Designing
Designing the ERP to be
implemented
Development of projetc
design
Use case designing
design of class diagram
Designing the System
interface of the Software
Designing the phase
contingency for the
project
Creation of a prototype for
approval
Drafting the Report
Development/Implementation
software coding
inserting data on the
database
linking the system with
database
Project re-estimation (if
required)
Testing
Devoloping the
checklistInterface testing
Unit testing
user acceptance testing
system testing
System ready for release
Maintainance
System Installation
Training the Users
User testing
System handover
Payment Completion
Resource Release
Client Sign off
Project Ends
Figure 1: Representing the Work Breakdown Structure of the project
(Source: created by author using WBS Schedule Pro and MS Project)
6
ADVANCED INFO SYSTEMS DESIGN
The ERP implementation is a complex project and therefore, it requires adequate
precision in implementation. Testing phase plays a major role in successful completion of the
project and is very necessary to perform the system testing phase as if any bug is detected in this
phase, it can be easily rectified before the project launch (Kerzner & Kerzner, 2017). The work
breakdown structure represented above defines the works that are needed to be performed in
order to achieve the project deliverables.
1.5. Project Timeline
The project timeline is important to communicate the essential milestone associated with
a project. The following project timeline provides an outline of the major deliverables of the
project ERP implementation in chronological sequence.
Task Name Duration Start Finish
ERP Implementation 279 days Thu 01-03-18 Tue 26-03-19
Project Starts 0 days Thu 01-03-18 Thu 01-03-18
Planning 35 days Thu 01-03-18 Wed 18-04-18
Planning the Project Work 10 days Thu 01-03-18 Wed 14-03-18
Feasibility Study 20 days Thu 15-03-18 Wed 11-04-18
Budget estimation 5 days Thu 12-04-18 Wed 18-04-18
Drafting the Project Plan 0 days Wed 18-04-18 Wed 18-04-18
Requirement Analysis 33 days Thu 19-04-18 Mon 04-06-18
Analysis of Hardware and Software
requirements 10 days Thu 19-04-18 Wed 02-05-18
Evaluation of Human Resources 8 days Thu 03-05-18 Mon 14-05-18
Evaluation of the Financial Resources 10 days Tue 15-05-18 Mon 28-05-18
Analysis of the project Schedule 5 days Tue 29-05-18 Mon 04-06-18
Drafting the requirements for approval 0 days Mon 04-06-18 Mon 04-06-18
Designing 95 days Tue 05-06-18 Mon 15-10-18
Designing the ERP to be implemented 15 days Tue 05-06-18 Mon 25-06-18
Development of project design 10 days Tue 26-06-18 Mon 09-07-18
Use case designing 5 days Tue 10-07-18 Mon 16-07-18
design of class diagram 5 days Tue 17-07-18 Mon 23-07-18
Designing the System interface of the
Software 20 days Tue 24-07-18 Mon 20-08-18
Designing the phase contingency for the 10 days Tue 21-08-18 Mon 03-09-18
ADVANCED INFO SYSTEMS DESIGN
The ERP implementation is a complex project and therefore, it requires adequate
precision in implementation. Testing phase plays a major role in successful completion of the
project and is very necessary to perform the system testing phase as if any bug is detected in this
phase, it can be easily rectified before the project launch (Kerzner & Kerzner, 2017). The work
breakdown structure represented above defines the works that are needed to be performed in
order to achieve the project deliverables.
1.5. Project Timeline
The project timeline is important to communicate the essential milestone associated with
a project. The following project timeline provides an outline of the major deliverables of the
project ERP implementation in chronological sequence.
Task Name Duration Start Finish
ERP Implementation 279 days Thu 01-03-18 Tue 26-03-19
Project Starts 0 days Thu 01-03-18 Thu 01-03-18
Planning 35 days Thu 01-03-18 Wed 18-04-18
Planning the Project Work 10 days Thu 01-03-18 Wed 14-03-18
Feasibility Study 20 days Thu 15-03-18 Wed 11-04-18
Budget estimation 5 days Thu 12-04-18 Wed 18-04-18
Drafting the Project Plan 0 days Wed 18-04-18 Wed 18-04-18
Requirement Analysis 33 days Thu 19-04-18 Mon 04-06-18
Analysis of Hardware and Software
requirements 10 days Thu 19-04-18 Wed 02-05-18
Evaluation of Human Resources 8 days Thu 03-05-18 Mon 14-05-18
Evaluation of the Financial Resources 10 days Tue 15-05-18 Mon 28-05-18
Analysis of the project Schedule 5 days Tue 29-05-18 Mon 04-06-18
Drafting the requirements for approval 0 days Mon 04-06-18 Mon 04-06-18
Designing 95 days Tue 05-06-18 Mon 15-10-18
Designing the ERP to be implemented 15 days Tue 05-06-18 Mon 25-06-18
Development of project design 10 days Tue 26-06-18 Mon 09-07-18
Use case designing 5 days Tue 10-07-18 Mon 16-07-18
design of class diagram 5 days Tue 17-07-18 Mon 23-07-18
Designing the System interface of the
Software 20 days Tue 24-07-18 Mon 20-08-18
Designing the phase contingency for the 10 days Tue 21-08-18 Mon 03-09-18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7
ADVANCED INFO SYSTEMS DESIGN
project
Creation of a prototype for approval 30 days Tue 04-09-18 Mon 15-10-18
Drafting the Report 0 days Mon 15-10-18 Mon 15-10-18
Development/Implementation 37 days Tue 16-10-18 Wed 05-12-18
software coding 20 days Tue 16-10-18 Mon 12-11-18
inserting data on the database 10 days Tue 13-11-18 Mon 26-11-18
linking the system with database 5 days Tue 27-11-18 Mon 03-12-18
Project re-estimation (if required) 2 days Tue 04-12-18 Wed 05-12-18
Testing 52 days Thu 06-12-18 Fri 15-02-19
Developing the checklist 7 days Thu 06-12-18 Fri 14-12-18
Interface testing 5 days Mon 17-12-18 Fri 21-12-18
Unit testing 15 days Mon 24-12-18 Fri 11-01-19
user acceptance testing 10 days Mon 14-01-19 Fri 25-01-19
system testing 15 days Mon 28-01-19 Fri 15-02-19
System ready for release 0 days Fri 15-02-19 Fri 15-02-19
Maintenance 27 days Mon 18-02-19 Tue 26-03-19
System Installation 5 days Mon 18-02-19 Fri 22-02-19
Training the Users 7 days Mon 25-02-19 Tue 05-03-19
User testing 5 days Wed 06-03-19 Tue 12-03-19
System handover 2 days Wed 13-03-19 Thu 14-03-19
Payment Completion 2 days Fri 15-03-19 Mon 18-03-19
Resource Release 5 days Tue 19-03-19 Mon 25-03-19
Client Sign off 1 day Tue 26-03-19 Tue 26-03-19
Project Ends 0 days Tue 26-03-19 Tue 26-03-19
Table 2: Representing the Project Timeline
(The project milestone are marked in green)
The Gantt chart showing a pictorial representation of the Project Timeline is shown
below-
ADVANCED INFO SYSTEMS DESIGN
project
Creation of a prototype for approval 30 days Tue 04-09-18 Mon 15-10-18
Drafting the Report 0 days Mon 15-10-18 Mon 15-10-18
Development/Implementation 37 days Tue 16-10-18 Wed 05-12-18
software coding 20 days Tue 16-10-18 Mon 12-11-18
inserting data on the database 10 days Tue 13-11-18 Mon 26-11-18
linking the system with database 5 days Tue 27-11-18 Mon 03-12-18
Project re-estimation (if required) 2 days Tue 04-12-18 Wed 05-12-18
Testing 52 days Thu 06-12-18 Fri 15-02-19
Developing the checklist 7 days Thu 06-12-18 Fri 14-12-18
Interface testing 5 days Mon 17-12-18 Fri 21-12-18
Unit testing 15 days Mon 24-12-18 Fri 11-01-19
user acceptance testing 10 days Mon 14-01-19 Fri 25-01-19
system testing 15 days Mon 28-01-19 Fri 15-02-19
System ready for release 0 days Fri 15-02-19 Fri 15-02-19
Maintenance 27 days Mon 18-02-19 Tue 26-03-19
System Installation 5 days Mon 18-02-19 Fri 22-02-19
Training the Users 7 days Mon 25-02-19 Tue 05-03-19
User testing 5 days Wed 06-03-19 Tue 12-03-19
System handover 2 days Wed 13-03-19 Thu 14-03-19
Payment Completion 2 days Fri 15-03-19 Mon 18-03-19
Resource Release 5 days Tue 19-03-19 Mon 25-03-19
Client Sign off 1 day Tue 26-03-19 Tue 26-03-19
Project Ends 0 days Tue 26-03-19 Tue 26-03-19
Table 2: Representing the Project Timeline
(The project milestone are marked in green)
The Gantt chart showing a pictorial representation of the Project Timeline is shown
below-
8
ADVANCED INFO SYSTEMS DESIGN
Figure 2: Representing the Gantt chart of the shifting project
(Source: Generated by Author using MS project)
ADVANCED INFO SYSTEMS DESIGN
Figure 2: Representing the Gantt chart of the shifting project
(Source: Generated by Author using MS project)
9
ADVANCED INFO SYSTEMS DESIGN
Since the Project is following a waterfall approach, end of each task marks the beginning
of the next (Saxena & Upadhyay 2016). The project will be following a planned approach;
however, if required, the project might include certain changes while its implementation.
1.6. Project dependencies
The successful implementation of the project depends on the proper evaluation of the
project plan and approval of the project design. For development of a proper design it is essential
to evaluate the requirements of the project, and therefore, the project success is largely dependent
on the requirement analysis phase of the project. Furthermore, since the project will be following
a waterfall approach, every stages of the project will depend on the previous phase (McCormick,
2012).
ADVANCED INFO SYSTEMS DESIGN
Since the Project is following a waterfall approach, end of each task marks the beginning
of the next (Saxena & Upadhyay 2016). The project will be following a planned approach;
however, if required, the project might include certain changes while its implementation.
1.6. Project dependencies
The successful implementation of the project depends on the proper evaluation of the
project plan and approval of the project design. For development of a proper design it is essential
to evaluate the requirements of the project, and therefore, the project success is largely dependent
on the requirement analysis phase of the project. Furthermore, since the project will be following
a waterfall approach, every stages of the project will depend on the previous phase (McCormick,
2012).
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10
ADVANCED INFO SYSTEMS DESIGN
2. System Design Document
2.1. Introduction
The system design document for the project is essential to develop as it gives an
overview of the system to be developed in an architectural level. It gives a clear idea of the
services, hardware and software requirements and the design of a product. The system design
document for the ERP implementation project outlines the project requirements, constraints
associated with the project, the resource requirements and a detailed overview of the system to
be developed. The system design document will provide a clear idea of the project requirements
and the system is to be delivered after the successful implementation of the project.
2.2. Requirements
The project aims at development of an integrated ERP system for ABC Pvt. Ltd. that will
operate in real time. Integration of all the processes running within the organization will be
possible only if a common database is maintained that will support all the application. The
system shall include an administrative portal, data update and data delete option. The portal will
allow only authorized users in accessing the system as a necessary security measure. The system
interference shall be simple so that it can be easily operated by the employees of the ABC Pvt.
Ltd. Development of a transactional database is another major project requirement. The system
shall include a search option for easy query and report generation. Furthermore, the system shall
incorporate automated mail generation and instant messaging to keep the management informed
about the number of orders processed. This is a part of workflow management that includes
logical data flow and data updates to the senior management of the organization. The interface of
ADVANCED INFO SYSTEMS DESIGN
2. System Design Document
2.1. Introduction
The system design document for the project is essential to develop as it gives an
overview of the system to be developed in an architectural level. It gives a clear idea of the
services, hardware and software requirements and the design of a product. The system design
document for the ERP implementation project outlines the project requirements, constraints
associated with the project, the resource requirements and a detailed overview of the system to
be developed. The system design document will provide a clear idea of the project requirements
and the system is to be delivered after the successful implementation of the project.
2.2. Requirements
The project aims at development of an integrated ERP system for ABC Pvt. Ltd. that will
operate in real time. Integration of all the processes running within the organization will be
possible only if a common database is maintained that will support all the application. The
system shall include an administrative portal, data update and data delete option. The portal will
allow only authorized users in accessing the system as a necessary security measure. The system
interference shall be simple so that it can be easily operated by the employees of the ABC Pvt.
Ltd. Development of a transactional database is another major project requirement. The system
shall include a search option for easy query and report generation. Furthermore, the system shall
incorporate automated mail generation and instant messaging to keep the management informed
about the number of orders processed. This is a part of workflow management that includes
logical data flow and data updates to the senior management of the organization. The interface of
11
ADVANCED INFO SYSTEMS DESIGN
ERP system shall include the read only data processing option for preventing data duplication
(Tsai et al., 2012).
2.3. Constraints and Assumptions
2.3.1. Project Constraints
The system constraints of the Enterprise Resource Planning system that is to be
developed for ABC Pvt. Ltd are as follows-
1. Every processes running within the organization will be automated by the
implementation of this ERP system. However, the system might subject to malfunctioning,
leading to erroneous data processing. The malfunctioning of the ERP system might occur due a
fault in software implementation (Leon, 2014).
2. The ERP system to be developed will be subjected to proper maintenance for
maintaining its proper functionality (Shaul & Tauber, 2013).
3. The success of the project will largely depend on the proper formulation of the project
plan and evaluation of the project requirements.
2.3.2. Assumptions
The assumptions of the project are as follows-
1. It is assumed that the project requirements are properly analyzed prior to development
of project plan.
2. It is assumed that a proper project environment is set prior to the project
implementation
ADVANCED INFO SYSTEMS DESIGN
ERP system shall include the read only data processing option for preventing data duplication
(Tsai et al., 2012).
2.3. Constraints and Assumptions
2.3.1. Project Constraints
The system constraints of the Enterprise Resource Planning system that is to be
developed for ABC Pvt. Ltd are as follows-
1. Every processes running within the organization will be automated by the
implementation of this ERP system. However, the system might subject to malfunctioning,
leading to erroneous data processing. The malfunctioning of the ERP system might occur due a
fault in software implementation (Leon, 2014).
2. The ERP system to be developed will be subjected to proper maintenance for
maintaining its proper functionality (Shaul & Tauber, 2013).
3. The success of the project will largely depend on the proper formulation of the project
plan and evaluation of the project requirements.
2.3.2. Assumptions
The assumptions of the project are as follows-
1. It is assumed that the project requirements are properly analyzed prior to development
of project plan.
2. It is assumed that a proper project environment is set prior to the project
implementation
12
ADVANCED INFO SYSTEMS DESIGN
3. It is assumed that the project can be successfully completed within the set budget.
4. It is assumed that the resource allocation of the project is properly done.
5. It is assumed that the time allocated for the project is adequate for its successful
completion.
6. It is assumed that the business will be benefited by the implementation of the
enterprise resource planning system (Matende & Ogao, 2013).
These are the basic constraints and assumptions associated with this project. The chosen
waterfall methodology of the project is considered to be the correct approach of project
implementation.
2.4. Resources
The resources required for the ERP implementation project are as follows-
1. The major resource requirement of the project is development of the project team for
successful project implementation
2. Different hardware and software requirements for ERP implementation
3. Allocation of work force according to the different project stages.
2.5. System Overview
The ERP system to be developed for ABC Pvt. Ltd. is expected to integrate all the
business processes running within the organization (Almutairi, 2015). The ERP system to be
developed will organize and integrate the different functional areas of the organization such as
ADVANCED INFO SYSTEMS DESIGN
3. It is assumed that the project can be successfully completed within the set budget.
4. It is assumed that the resource allocation of the project is properly done.
5. It is assumed that the time allocated for the project is adequate for its successful
completion.
6. It is assumed that the business will be benefited by the implementation of the
enterprise resource planning system (Matende & Ogao, 2013).
These are the basic constraints and assumptions associated with this project. The chosen
waterfall methodology of the project is considered to be the correct approach of project
implementation.
2.4. Resources
The resources required for the ERP implementation project are as follows-
1. The major resource requirement of the project is development of the project team for
successful project implementation
2. Different hardware and software requirements for ERP implementation
3. Allocation of work force according to the different project stages.
2.5. System Overview
The ERP system to be developed for ABC Pvt. Ltd. is expected to integrate all the
business processes running within the organization (Almutairi, 2015). The ERP system to be
developed will organize and integrate the different functional areas of the organization such as
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13
ADVANCED INFO SYSTEMS DESIGN
logistics, production, finance and accounting. Furthermore, the ERP to be developed is expected
to make optimum use of organizational resources. The entire system will be integrated and will
incorporate one database, one application and one user interface for easy access of the system.
The diagrammatic representation of the ERP system is shown below-
Figure 3: Representing the ERP system to be implemented
(Source: Yang, Liang & Avgeriou, 2016)
The above figure gives a clear idea of the different processes that the enterprise resource
planning system will manage in ABC Pvt. Ltd. The design of the ERP shall be very simple and
efficient.
ADVANCED INFO SYSTEMS DESIGN
logistics, production, finance and accounting. Furthermore, the ERP to be developed is expected
to make optimum use of organizational resources. The entire system will be integrated and will
incorporate one database, one application and one user interface for easy access of the system.
The diagrammatic representation of the ERP system is shown below-
Figure 3: Representing the ERP system to be implemented
(Source: Yang, Liang & Avgeriou, 2016)
The above figure gives a clear idea of the different processes that the enterprise resource
planning system will manage in ABC Pvt. Ltd. The design of the ERP shall be very simple and
efficient.
14
ADVANCED INFO SYSTEMS DESIGN
The project design phase will further evaluate the use case and class diagram developed
for the enterprise resource planning system to understand the functionality of ERP system (Mir
& Pinnington, 2014).
2.6. Conclusion
Therefore, from the above discussion it can be concluded that system design document
plays a major role in successful implementation of a project. The system design document
evaluates the different assumptions, constraints and resource requirements associated with the
project. This document is essential for developing the initial designing of the project.
ADVANCED INFO SYSTEMS DESIGN
The project design phase will further evaluate the use case and class diagram developed
for the enterprise resource planning system to understand the functionality of ERP system (Mir
& Pinnington, 2014).
2.6. Conclusion
Therefore, from the above discussion it can be concluded that system design document
plays a major role in successful implementation of a project. The system design document
evaluates the different assumptions, constraints and resource requirements associated with the
project. This document is essential for developing the initial designing of the project.
15
ADVANCED INFO SYSTEMS DESIGN
References
Almutairi, M. K. M. (2015). Enterprise resource Planning ERP.
Bassil, Y. (2012). A simulation model for the waterfall software development life cycle. arXiv
preprint arXiv:1205.6904.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt
Assn.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E.W. and Gray, C., (2013). Project management: The managerial process with MS
project. McGraw-Hill.
Leon, A. (2014). Enterprise resource planning. McGraw-Hill Education.
Matende, S., & Ogao, P. (2013). Enterprise resource planning (ERP) system implementation: a
case for user participation. Procedia Technology, 9, 518-526.
McCormick, M. (2012). Waterfall vs. Agile methodology. MPCS, N/A.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Saxena, A., & Upadhyay, P. (2016). Waterfall vs. prototype: Comparative study of sdlc. Imperial
Journal of Interdisciplinary Research, 2(6).
ADVANCED INFO SYSTEMS DESIGN
References
Almutairi, M. K. M. (2015). Enterprise resource Planning ERP.
Bassil, Y. (2012). A simulation model for the waterfall software development life cycle. arXiv
preprint arXiv:1205.6904.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt
Assn.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E.W. and Gray, C., (2013). Project management: The managerial process with MS
project. McGraw-Hill.
Leon, A. (2014). Enterprise resource planning. McGraw-Hill Education.
Matende, S., & Ogao, P. (2013). Enterprise resource planning (ERP) system implementation: a
case for user participation. Procedia Technology, 9, 518-526.
McCormick, M. (2012). Waterfall vs. Agile methodology. MPCS, N/A.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Saxena, A., & Upadhyay, P. (2016). Waterfall vs. prototype: Comparative study of sdlc. Imperial
Journal of Interdisciplinary Research, 2(6).
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16
ADVANCED INFO SYSTEMS DESIGN
Schwalbe, K., (2015). Information technology project management. Cengage Learning.
Shaul, L., & Tauber, D. (2013). Critical success factors in enterprise resource planning systems:
Review of the last decade. ACM Computing Surveys (CSUR), 45(4), 55.
Tsai, W. H., Lee, P. L., Shen, Y. S., & Lin, H. L. (2012). A comprehensive study of the
relationship between enterprise resource planning selection criteria and enterprise
resource planning system success. Information & Management, 49(1), 36-46.
Yang, C., Liang, P., & Avgeriou, P. (2016). A survey on software architectural assumptions.
Journal of Systems and Software, 113, 362-380.
ADVANCED INFO SYSTEMS DESIGN
Schwalbe, K., (2015). Information technology project management. Cengage Learning.
Shaul, L., & Tauber, D. (2013). Critical success factors in enterprise resource planning systems:
Review of the last decade. ACM Computing Surveys (CSUR), 45(4), 55.
Tsai, W. H., Lee, P. L., Shen, Y. S., & Lin, H. L. (2012). A comprehensive study of the
relationship between enterprise resource planning selection criteria and enterprise
resource planning system success. Information & Management, 49(1), 36-46.
Yang, C., Liang, P., & Avgeriou, P. (2016). A survey on software architectural assumptions.
Journal of Systems and Software, 113, 362-380.
1 out of 17
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.