Exploring Materials and Methods Used in Construction
VerifiedAdded on 2019/09/30
|33
|7809
|139
Report
AI Summary
The provided content discusses various topics in the field of construction, including daytime urban heat island effect in high-rise residential developments, recent developments in photovoltaics, and methods used to ensure the safety of concrete beams, slabs, and footings. Additionally, it touches on integrating building information modeling with construction process documentation, the evaluation and benefits management practices of SMEs in the construction industry, and an embodied carbon and energy analysis of modern methods of construction in housing. The content also includes studies on construction delay causes, project management, sustainable construction principles, and ultimate bearing capacity of footings on sand layer overlying clay.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

Answer: 1
The national construction code present about minimum technical requirement for new
building as well as existing building in Australia. The Australian building codes board is
established by agreement between commonwealth government, every states and territory.
That present about groups of building by present their function and use. The NCC group are
highlighted and classified about how the building should referred. This kind of information
is difficult for all groups and users of all NCC. The following are representation about
building classification through NCC. It depends on the national perspective and also present
about state and territory variation. The building has been classified according to classes. All
classes have different meaning and different objective.
The NCC comprise the building code of Australia with different volume. The volume one
and two consist plumbing code of Australia. Also national construction code is the uniform
set of technical provisions for the design and construction of building and other structure
throughout Australia.
Answer: 2
The building are classified as per the classes as defined in NCC (national construction code).
The classification have labelled in form of class1 to class 10. That also include classification
with sub classification. The sub classification have mention through alphabetical order from
a, b, c etc. the class 2 to class 9 building are mostly cover the entire volume of two of the
NCC. The volume three of the national construction code contain plumbing code of
Australia. The building have been classified as per user and public associate with that
building and construction requirement. The construction of building have more than one
users and classification done according to users, therefore classification assigned more than
one classification.
1 | P a g e
The national construction code present about minimum technical requirement for new
building as well as existing building in Australia. The Australian building codes board is
established by agreement between commonwealth government, every states and territory.
That present about groups of building by present their function and use. The NCC group are
highlighted and classified about how the building should referred. This kind of information
is difficult for all groups and users of all NCC. The following are representation about
building classification through NCC. It depends on the national perspective and also present
about state and territory variation. The building has been classified according to classes. All
classes have different meaning and different objective.
The NCC comprise the building code of Australia with different volume. The volume one
and two consist plumbing code of Australia. Also national construction code is the uniform
set of technical provisions for the design and construction of building and other structure
throughout Australia.
Answer: 2
The building are classified as per the classes as defined in NCC (national construction code).
The classification have labelled in form of class1 to class 10. That also include classification
with sub classification. The sub classification have mention through alphabetical order from
a, b, c etc. the class 2 to class 9 building are mostly cover the entire volume of two of the
NCC. The volume three of the national construction code contain plumbing code of
Australia. The building have been classified as per user and public associate with that
building and construction requirement. The construction of building have more than one
users and classification done according to users, therefore classification assigned more than
one classification.
1 | P a g e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

There are total ten classes of structure have been classified within the NCC as commercial
low rise building. The classes brief explanation discuss as following:
1. Class 1 are contain building of houses. That are typically single dwell of domestic
nature. They are attachment such as horizontally and building and houses consisting
terrace houses, townhouses and row houses. The class 1a contain single dwelling
with detached house. Class 1b contain boarding house and guest house.
Answer: 3
2. Class 2 are the building construction like apartment. That contain multi story or
mutli-unit residential building.
3. The class 3 contain residential building apart from class 1 and class 2 they have
common land or place e.g. included boarding house and guest house.
4. Class 4 building is dwelling or residence inside the building or non-residential
nature. E.g. caretaker residence in a storage facility.
5. Class 5 types building are the professional type and commercial type. The class 5
also include class 6, 7, 8 and 9 building.
6. Class 6 types building are the shops, cafes and restaurants type building. They are
built for sales and service for public relationship.
7. The class 7 building are carparks building. That typically warehouses, storage
building for present goods.
8. The class 8 building consist construction used for production, assembly, repair,
packaging, food manufacturing or any other manufacturing. That contain sale also.
9. Class 9 classified in class 9a, 9b and 9c. The class 9a refer for hospitals and health
care building. Class 9b consist construction for public and social activity that include
2 | P a g e
low rise building. The classes brief explanation discuss as following:
1. Class 1 are contain building of houses. That are typically single dwell of domestic
nature. They are attachment such as horizontally and building and houses consisting
terrace houses, townhouses and row houses. The class 1a contain single dwelling
with detached house. Class 1b contain boarding house and guest house.
Answer: 3
2. Class 2 are the building construction like apartment. That contain multi story or
mutli-unit residential building.
3. The class 3 contain residential building apart from class 1 and class 2 they have
common land or place e.g. included boarding house and guest house.
4. Class 4 building is dwelling or residence inside the building or non-residential
nature. E.g. caretaker residence in a storage facility.
5. Class 5 types building are the professional type and commercial type. The class 5
also include class 6, 7, 8 and 9 building.
6. Class 6 types building are the shops, cafes and restaurants type building. They are
built for sales and service for public relationship.
7. The class 7 building are carparks building. That typically warehouses, storage
building for present goods.
8. The class 8 building consist construction used for production, assembly, repair,
packaging, food manufacturing or any other manufacturing. That contain sale also.
9. Class 9 classified in class 9a, 9b and 9c. The class 9a refer for hospitals and health
care building. Class 9b consist construction for public and social activity that include
2 | P a g e

schools, universities, children care centre etc. the class 9c construction induce age
care buildings. That include residential accommodation for old peoples.
10. Class 10a buildings are shades, carpets and private premises, class 10b building
construction for swimming pool or lakes. Class 10c buildings are private bushfire
shelter.
Answer: 4
Structural performance of a structure is described in terms of the effect of section
properties on various materials.
Structural performance characteristics of slabs, floors, beams, columns and retaining
walls are explained and applied to the planning of the construction work.
Demolition of existing structures is coordinated in accordance with legislative and
planning requirements, environmental standards, and safe work practices.
Answer: 5
Unit of stress: N
m2 ∨MPa
Pressure unit: Pascal
Answer: 6
Unit of force: Newton or Kilo-Newton
Unit of pressure: Newton or Kilo-Newton
Answer: 7
Structural member: it is support which is part of any structure or building or structure
member is a component used to build or develop entire construction.
The structural member is the principal component of any building or structure. E.g. beam,
plate, riser, support, tread, sill and bracing are the example of structural member.
3 | P a g e
care buildings. That include residential accommodation for old peoples.
10. Class 10a buildings are shades, carpets and private premises, class 10b building
construction for swimming pool or lakes. Class 10c buildings are private bushfire
shelter.
Answer: 4
Structural performance of a structure is described in terms of the effect of section
properties on various materials.
Structural performance characteristics of slabs, floors, beams, columns and retaining
walls are explained and applied to the planning of the construction work.
Demolition of existing structures is coordinated in accordance with legislative and
planning requirements, environmental standards, and safe work practices.
Answer: 5
Unit of stress: N
m2 ∨MPa
Pressure unit: Pascal
Answer: 6
Unit of force: Newton or Kilo-Newton
Unit of pressure: Newton or Kilo-Newton
Answer: 7
Structural member: it is support which is part of any structure or building or structure
member is a component used to build or develop entire construction.
The structural member is the principal component of any building or structure. E.g. beam,
plate, riser, support, tread, sill and bracing are the example of structural member.
3 | P a g e

Beam is the long thick component or piece of metal, concreate used for construction, a beam
provide strength of the entire construction. Entire construction loaded and load distributed
over the entire span of beam. Plate is a structural member used to consist horizontal beam
which provide bearing and anchorage. Similarly, riser consist vertical part of stair or step.
Support is a device that bears the weight of something else, that have no place to attachment
supports for a shelf.
Answer: 8
Primary loads are classified into main two categories and as per they behaviour on the
structure and structural elements. The classification done as live loads and dead loads. The
loading of the construction structure can be put into different form. At different case the
loading may not manage exactly as per individual category still it can classified as primary
or secondary loading. Primary loading are depends on the structural material, occupants etc.
the primary loading also affected by surrounding medium and weather conditions as well.
Also that affect by the external different loading condition which are apart from primary
loading. The primary loading also affect through extreme weather also. whereas secondary
loading are those loading which affect other properties such as change in temperature,
construction eccentricities, shrinkage of structural member, foundation and other external
loading except primary loading.
Live load: as define name of the loading, that loading are those loads which are transient
and can be varies it magnitude as per external condition. The live load include all
component and part which consist ordinary building structure such as furniture, books, TV,
sofas, machinery, stored materials etc. The live load also affect through external
environment such as loading due to sun, earth and change in weather. The natural disaster
and natural activity which cannot control by human being such as earthquakes load and
4 | P a g e
provide strength of the entire construction. Entire construction loaded and load distributed
over the entire span of beam. Plate is a structural member used to consist horizontal beam
which provide bearing and anchorage. Similarly, riser consist vertical part of stair or step.
Support is a device that bears the weight of something else, that have no place to attachment
supports for a shelf.
Answer: 8
Primary loads are classified into main two categories and as per they behaviour on the
structure and structural elements. The classification done as live loads and dead loads. The
loading of the construction structure can be put into different form. At different case the
loading may not manage exactly as per individual category still it can classified as primary
or secondary loading. Primary loading are depends on the structural material, occupants etc.
the primary loading also affected by surrounding medium and weather conditions as well.
Also that affect by the external different loading condition which are apart from primary
loading. The primary loading also affect through extreme weather also. whereas secondary
loading are those loading which affect other properties such as change in temperature,
construction eccentricities, shrinkage of structural member, foundation and other external
loading except primary loading.
Live load: as define name of the loading, that loading are those loads which are transient
and can be varies it magnitude as per external condition. The live load include all
component and part which consist ordinary building structure such as furniture, books, TV,
sofas, machinery, stored materials etc. The live load also affect through external
environment such as loading due to sun, earth and change in weather. The natural disaster
and natural activity which cannot control by human being such as earthquakes load and
4 | P a g e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Tsunami put into special category called lateral live loads due to its action and reaction.
They are potential to cause of failure and disaster.
Answer: 9
Dead load on a structure is the total weight of the permanent components such as beams,
floor slabs, walls and columns. These kind of components produce similar loading affect
over the lifespan of the building. Dead loads are the loading exerted in the vertical plane. In
mathematical terms dead loads is equal to volume of member multiply by unit weight of
material.
Dead loads are those loads which affect permanently and they are stationary for long life. It
cannot movable, also unable to remove. The self-weight of the structural members are
usually consider as the portion of dead load of building. The permanent non-structural
elements such roof, water pipe, gas –pipe, environmental control system and related
machinery such as solar penal, lift and all other construction system which may be place as
rigid and may not move for long life called dead load.
Dead load:
Table.1 Dead load with different material and unit weight
Material Unit weight kN /m3
Glass 27.5
Hardwood 12
Mild steel 78
Plain concrete 25
Reinforced concreate 23
5 | P a g e
They are potential to cause of failure and disaster.
Answer: 9
Dead load on a structure is the total weight of the permanent components such as beams,
floor slabs, walls and columns. These kind of components produce similar loading affect
over the lifespan of the building. Dead loads are the loading exerted in the vertical plane. In
mathematical terms dead loads is equal to volume of member multiply by unit weight of
material.
Dead loads are those loads which affect permanently and they are stationary for long life. It
cannot movable, also unable to remove. The self-weight of the structural members are
usually consider as the portion of dead load of building. The permanent non-structural
elements such roof, water pipe, gas –pipe, environmental control system and related
machinery such as solar penal, lift and all other construction system which may be place as
rigid and may not move for long life called dead load.
Dead load:
Table.1 Dead load with different material and unit weight
Material Unit weight kN /m3
Glass 27.5
Hardwood 12
Mild steel 78
Plain concrete 25
Reinforced concreate 23
5 | P a g e

Answer: 10
Force: a force is any interaction that will change the motion of object. The basic properties
of all kind of forces are direction and magnitude. The force represent body with direction
and magnitude of the objective.
The force also classified as per fundamental properties of nature.
1. Gravitation
2. Electromagnetic
3. Fundamental and residual force of body.
Answer: 11
Section modulus is the property of beam section. The section modulus is important
properties while designing or selection beams. The section modulus directly affect the
strength of beam cross section. If the beam has large section modulus then it will
stronger than other beam and capable to withstand at greatest loads.
That section modulus react and work in bending is being done by the extreme fibre of
the beam i.e. top and bottom fibre of the beam. The both section (top and bottom fibre)
impact for strength of beam and used in calculation of section modulus. It denoted by Z.
the calculation of section modulus consider distance to the extreme fibres from the
centroid or neutral axis must be observe as that point where maximum stress induce and
cause failure of beam section.
6 | P a g e
Force: a force is any interaction that will change the motion of object. The basic properties
of all kind of forces are direction and magnitude. The force represent body with direction
and magnitude of the objective.
The force also classified as per fundamental properties of nature.
1. Gravitation
2. Electromagnetic
3. Fundamental and residual force of body.
Answer: 11
Section modulus is the property of beam section. The section modulus is important
properties while designing or selection beams. The section modulus directly affect the
strength of beam cross section. If the beam has large section modulus then it will
stronger than other beam and capable to withstand at greatest loads.
That section modulus react and work in bending is being done by the extreme fibre of
the beam i.e. top and bottom fibre of the beam. The both section (top and bottom fibre)
impact for strength of beam and used in calculation of section modulus. It denoted by Z.
the calculation of section modulus consider distance to the extreme fibres from the
centroid or neutral axis must be observe as that point where maximum stress induce and
cause failure of beam section.
6 | P a g e

Section modulus
Section modulus Z= I
Y
I =moment of inertia
Y =distance ¿ centre of gravity ¿ top most extreme position of beam
Answer: 12
Vertical compression member:
A structural elements which are subjected to axial compression force at vertical direction
(positive or negative) called columns, the columns are subjected to axial load at the centroid.
The columns can be represent as other terms of vertical compression member.
The buckling is other properties represent as vertical compression member and its effect
considerably, it cannot neglected. If length of beam is considerably large compare to the
width of the beam and vertical axial force applied then buckling occur. The buckling occur
when straight column subjected to axial compression load and beam undergoes bending as
shown in figure. Buckling is axial compression load members.
Answer: 13
Following professional persons are consult during planning and construction.
1. Architecture: the architecture play important role in construction, the new design
and development of construction assist by architecture. The architecture decide the
layout of building, facility in building, aesthetic appearance with unitization of all
space and all assign area of construction. The architecture provide human life, and
provide suggestion about the different way of construction and possible outcome as
given location and site. That provide guidance about the different suitable material
for construction and suitable structure as per construction. They provide infinity
7 | P a g e
Section modulus Z= I
Y
I =moment of inertia
Y =distance ¿ centre of gravity ¿ top most extreme position of beam
Answer: 12
Vertical compression member:
A structural elements which are subjected to axial compression force at vertical direction
(positive or negative) called columns, the columns are subjected to axial load at the centroid.
The columns can be represent as other terms of vertical compression member.
The buckling is other properties represent as vertical compression member and its effect
considerably, it cannot neglected. If length of beam is considerably large compare to the
width of the beam and vertical axial force applied then buckling occur. The buckling occur
when straight column subjected to axial compression load and beam undergoes bending as
shown in figure. Buckling is axial compression load members.
Answer: 13
Following professional persons are consult during planning and construction.
1. Architecture: the architecture play important role in construction, the new design
and development of construction assist by architecture. The architecture decide the
layout of building, facility in building, aesthetic appearance with unitization of all
space and all assign area of construction. The architecture provide human life, and
provide suggestion about the different way of construction and possible outcome as
given location and site. That provide guidance about the different suitable material
for construction and suitable structure as per construction. They provide infinity
7 | P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

variety of design about the construction which must be sensible toward the nature.
The cost of the construction also depends on the construction design, so design
prepare cost effectively also decide by architecture.
2. Engineers :
The engineer or groups of engineer must needed for construction. Without help of
them consultancies, it was difficult to construct building or structure. All physical
activities of construction have been done with the guidance of that engineering team.
The profession and well experience team of mechanical, civil and electrical
engineering team play important role for construction project. A smart and well
experience engineer reduce human effort, time, and resource and save total cost of
construction project. During planning and construction process, there was unique
place for engineer in construction. The quality control, material selection and
construction maintenance have been monitor and perform by engineering team.
3. Draftsman or design engineer :
The design engineer is also play important role in construction. The building design was
the prime requirement for construction project. The project planning, task allocation and
time line will be decide as per design of construction project. The work break down
structure have been decide through building design. The construction material selection
also decide through design engineer and suitability of specific material decide through
design and design engineer. The geometry location and construction possible decided
through design engineer. Apart from physical work, all construction work have been
prepare draftsman or design engineer. the project planning and quantity of material
require for particular construction project have been decide by design engineer. There
are many task have to perform by draftsman or design engineer. So it is essential to
consult design engineer for construction project.
8 | P a g e
The cost of the construction also depends on the construction design, so design
prepare cost effectively also decide by architecture.
2. Engineers :
The engineer or groups of engineer must needed for construction. Without help of
them consultancies, it was difficult to construct building or structure. All physical
activities of construction have been done with the guidance of that engineering team.
The profession and well experience team of mechanical, civil and electrical
engineering team play important role for construction project. A smart and well
experience engineer reduce human effort, time, and resource and save total cost of
construction project. During planning and construction process, there was unique
place for engineer in construction. The quality control, material selection and
construction maintenance have been monitor and perform by engineering team.
3. Draftsman or design engineer :
The design engineer is also play important role in construction. The building design was
the prime requirement for construction project. The project planning, task allocation and
time line will be decide as per design of construction project. The work break down
structure have been decide through building design. The construction material selection
also decide through design engineer and suitability of specific material decide through
design and design engineer. The geometry location and construction possible decided
through design engineer. Apart from physical work, all construction work have been
prepare draftsman or design engineer. the project planning and quantity of material
require for particular construction project have been decide by design engineer. There
are many task have to perform by draftsman or design engineer. So it is essential to
consult design engineer for construction project.
8 | P a g e

4. Land surveyors: the physical construction requirement and planning have been
perform by land surveyors. The land surveyors make exact measurements and obtain
property boundaries. That provide information and data about shape, count,
gravitation, dimension, elevation, location and land feature on or near the earth’s
surface for engineering. They also decide mapmaking, evaluation, construction and
land evaluation. These are the work profile for land surveyors and professional
industrial take consultancies for planning and construction.
5. Quantity surveyors :
The quantity surveyors manages all costs which are related directly or indirectly to
the building construction and related sub project. They provide initial calculation
about the necessary for construction. They are planned or try to manage as low cost
as possible for project. Also make sure about to maintain standard and quality of
construction. They ensure statutory building regulation have met with criteria.
6. Management team or Project Manager: the project Manager play important role for
the construction of building. All keys elements, guidance and monitor require
throughout the project of construction. A smart, efficient, well experience project
manager should hire in order to obtain maximum benefit for client, builder and other
professional persons associate with construction project. The project planning was
the key requirement for any kind of project whether it’s small building or multi-
storey building. The project planning need to prepare with the guidance and monitor
of project manager to ensure project will be complete within time limit mention by
client. The flow of all procedure associate with the construction project have been
guided by project manager. Critical decision have to receive by project manager and
need to take action wisely in order to less consume time and efficient work. The
quality of service or product, budget, costing, maintenance, work satisfaction and
9 | P a g e
perform by land surveyors. The land surveyors make exact measurements and obtain
property boundaries. That provide information and data about shape, count,
gravitation, dimension, elevation, location and land feature on or near the earth’s
surface for engineering. They also decide mapmaking, evaluation, construction and
land evaluation. These are the work profile for land surveyors and professional
industrial take consultancies for planning and construction.
5. Quantity surveyors :
The quantity surveyors manages all costs which are related directly or indirectly to
the building construction and related sub project. They provide initial calculation
about the necessary for construction. They are planned or try to manage as low cost
as possible for project. Also make sure about to maintain standard and quality of
construction. They ensure statutory building regulation have met with criteria.
6. Management team or Project Manager: the project Manager play important role for
the construction of building. All keys elements, guidance and monitor require
throughout the project of construction. A smart, efficient, well experience project
manager should hire in order to obtain maximum benefit for client, builder and other
professional persons associate with construction project. The project planning was
the key requirement for any kind of project whether it’s small building or multi-
storey building. The project planning need to prepare with the guidance and monitor
of project manager to ensure project will be complete within time limit mention by
client. The flow of all procedure associate with the construction project have been
guided by project manager. Critical decision have to receive by project manager and
need to take action wisely in order to less consume time and efficient work. The
quality of service or product, budget, costing, maintenance, work satisfaction and
9 | P a g e

relevant all parameter depends on project manager skills and technique. To obey
principal of ethics and apply over work as per given authority have follow a great
project manager. So client must looking forward to good and well experience project
manager which lead any project and provide quality work.
Answer: 14
In order to construct commercial low rise building following material and different method
obtain for construction.
Timber: timber is the prime material used for construction of low rise building. The timbers
are vastly used where it easy available. The different types of timber have used to construct
commercial low rise building. With the help of timber it is easy to construct frame type
structure. The standard size and shapes are available for construction of commercial low rise
building.
Masonry walls:
The structural masonry walls are used in commercial low rise building construction.
Primarily in multi-story buildings, where there require to sustain high load bearing capacity
and fire resistance. The bricks materials and concrete block are the major parts and
component of this construction. Mostly bricks are used because it durable appearance good
compare to others. The solid bricks are also used for construction but it used rarely because
of higher labour and material costs. The composite walls of brick and block are usual used
for construction. The cavity walls are used commonly for cold weather. Two vertical layers
of masonry are developed for rigid insulation. The wythes are connect through steel joint
which provide insulation and that would be laid in the layer joint at the regular interval. The
Cavity walls contain heat flow rate higher then solid wall, approximate 50 percentage more
10 | P a g e
principal of ethics and apply over work as per given authority have follow a great
project manager. So client must looking forward to good and well experience project
manager which lead any project and provide quality work.
Answer: 14
In order to construct commercial low rise building following material and different method
obtain for construction.
Timber: timber is the prime material used for construction of low rise building. The timbers
are vastly used where it easy available. The different types of timber have used to construct
commercial low rise building. With the help of timber it is easy to construct frame type
structure. The standard size and shapes are available for construction of commercial low rise
building.
Masonry walls:
The structural masonry walls are used in commercial low rise building construction.
Primarily in multi-story buildings, where there require to sustain high load bearing capacity
and fire resistance. The bricks materials and concrete block are the major parts and
component of this construction. Mostly bricks are used because it durable appearance good
compare to others. The solid bricks are also used for construction but it used rarely because
of higher labour and material costs. The composite walls of brick and block are usual used
for construction. The cavity walls are used commonly for cold weather. Two vertical layers
of masonry are developed for rigid insulation. The wythes are connect through steel joint
which provide insulation and that would be laid in the layer joint at the regular interval. The
Cavity walls contain heat flow rate higher then solid wall, approximate 50 percentage more
10 | P a g e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

than solid wall. The timber wall, floor and roof constriction was same as balloon framing
which also used for masonry construction.
Steel: in case construction require more strength and more story then steel material is most
suitable for construction. The steel is strong and stiff material, also considerable less
expensive compare to other material. it is non-combustible and can be withstand at around
400 degree temperature without change shape. The steel also fireproof which is mostly used
in multi-story building. For small and medium hazardous building, the fireproof is not
essential. All types of structural steel have used in construction whether it pure or inform of
alloy. The standard parts of structural steel have available such as square bars, angles, tubes,
channels, I-beam, different shape of flanges are used as per requirement of building
construction. The steel can formed in to different shape through hot-rolling process.
Apart from fundamental material bricks, stones, rocks sand, woods, cements, ceramics,
metal, plastics, glass fibre, composite material, glass material are used for construction of
commercial low rise building and that are the essential material for construction.
There are different method used for construct commercial low rise building, following are
discuss about different method used for construct method.
Precast flat panel system:
The floor and wall are construct off- site in the building campus and erected done at on-site
to for robust structure, this method is ideal for all types of repetitive projects. That also
include services, doors, windows and construction finishes. The penal with building fitted
with insulation and external cladding can be used as load-bearing elements. This types of
construction called cross wall construction and this can be improve with advance design.
11 | P a g e
which also used for masonry construction.
Steel: in case construction require more strength and more story then steel material is most
suitable for construction. The steel is strong and stiff material, also considerable less
expensive compare to other material. it is non-combustible and can be withstand at around
400 degree temperature without change shape. The steel also fireproof which is mostly used
in multi-story building. For small and medium hazardous building, the fireproof is not
essential. All types of structural steel have used in construction whether it pure or inform of
alloy. The standard parts of structural steel have available such as square bars, angles, tubes,
channels, I-beam, different shape of flanges are used as per requirement of building
construction. The steel can formed in to different shape through hot-rolling process.
Apart from fundamental material bricks, stones, rocks sand, woods, cements, ceramics,
metal, plastics, glass fibre, composite material, glass material are used for construction of
commercial low rise building and that are the essential material for construction.
There are different method used for construct commercial low rise building, following are
discuss about different method used for construct method.
Precast flat panel system:
The floor and wall are construct off- site in the building campus and erected done at on-site
to for robust structure, this method is ideal for all types of repetitive projects. That also
include services, doors, windows and construction finishes. The penal with building fitted
with insulation and external cladding can be used as load-bearing elements. This types of
construction called cross wall construction and this can be improve with advance design.
11 | P a g e

3D Volumetric Construction
The 3D volumetric construction consist the preparation of three –dimensional unit with
control construction. The modules can be arrange to the site in a variety of forms, the
construction range would be basic structure to concern one with all external and internal
finishes and usual service installed. The casting of modules uses the advantages of building
situation and require for quick assembly at the location which make it mostly desirable.
Hybrid concreate construction:
The hybrid concreate construction conduct all advantages of the pre-casting with the benefit
of cast in suit construction. Merge two as hybrid frame. That results in still good for
construction speed, quality and economy. The hybrid concrete construction can be satisfied
client requirement for economic cost and great quality of construction work. This kind of
construction can be manageable, achievable and competitive structures which offer
performance and quality output.
Answer: 15
Following documentation need to obtained and analysed to assist planning and construction
process:
Building approval plan
contract plans
12 | P a g e
The 3D volumetric construction consist the preparation of three –dimensional unit with
control construction. The modules can be arrange to the site in a variety of forms, the
construction range would be basic structure to concern one with all external and internal
finishes and usual service installed. The casting of modules uses the advantages of building
situation and require for quick assembly at the location which make it mostly desirable.
Hybrid concreate construction:
The hybrid concreate construction conduct all advantages of the pre-casting with the benefit
of cast in suit construction. Merge two as hybrid frame. That results in still good for
construction speed, quality and economy. The hybrid concrete construction can be satisfied
client requirement for economic cost and great quality of construction work. This kind of
construction can be manageable, achievable and competitive structures which offer
performance and quality output.
Answer: 15
Following documentation need to obtained and analysed to assist planning and construction
process:
Building approval plan
contract plans
12 | P a g e

designs and specifications
engineer footing designs and specifications
original contour survey plan
registered plans
retaining walls
site plans
soil investigation reports
structural floor systems, wall systems and roof systems
tanking designs and specifications
Underpinning, rock anchors and shoring designs and specifications.
Answer: 16
Footing are the important part of the construction of foundation. The footing is usually
made form concreate with rebar reinforcement which need to pour in side an excavated
trench. The footings are construct in order to support the foundation and prevent settling.
The footings are important at the place of troublesome soils. The construction of footing
are the best leave to the pros which can check the soil situation and obtain on the specific
depth and width for the footing and also proper placement. The dimensions of footings
are also depends on the different size and types of construction structure which will be
built. The placement of the footings are critical that require the proper support for the
foundation and structure also.
The concrete footing may also require for project such as pergola, deck, retaining wall and
different types of construction.
Answer: 17
The following are explain different types of footing:
1. Isolated footing:
13 | P a g e
engineer footing designs and specifications
original contour survey plan
registered plans
retaining walls
site plans
soil investigation reports
structural floor systems, wall systems and roof systems
tanking designs and specifications
Underpinning, rock anchors and shoring designs and specifications.
Answer: 16
Footing are the important part of the construction of foundation. The footing is usually
made form concreate with rebar reinforcement which need to pour in side an excavated
trench. The footings are construct in order to support the foundation and prevent settling.
The footings are important at the place of troublesome soils. The construction of footing
are the best leave to the pros which can check the soil situation and obtain on the specific
depth and width for the footing and also proper placement. The dimensions of footings
are also depends on the different size and types of construction structure which will be
built. The placement of the footings are critical that require the proper support for the
foundation and structure also.
The concrete footing may also require for project such as pergola, deck, retaining wall and
different types of construction.
Answer: 17
The following are explain different types of footing:
1. Isolated footing:
13 | P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

The footing in which are provided under each column individually are known as
isolated footings. The shape of isolated footings are usually square, rectangular or
circular cross section. The isolated footing is laid down on the PCC. These footing
are considerable less price compare to other types of footing. These types of footing
are used where soil bearing capacity is usually high.
Isolated footing have following advantages:
1. This types of footing are economical when columns are placed at the long distances.
2. No special knowledge or guidance require to place or used isolated footing
3. Excavation, form work and reinforcement placement is easy through isolated footing.
2. Flat or pad or plain footing:
These kind of footing are usually square, rectangular and circular cross section which
are usually under individual column. Flat or plain footing is one of the shallow
foundation. That is circular, square or rectangular slab with uniform thickness.
3. Stepped footing:
As suggest name, it resembling that footings are stacked upon one another as steps.
These types of footing are made from concrete cross section and stacked upon each
other. These types of footing are usually used residential building construction.
4. Sloped footing:
Sloped footing are trapezoidal footings. This types of footing prepare with great care and
can be observed that top slop of 45 degree is maintain around all sides. If compare
trapezoidal footing with flat footing then it require less concreate compare to flat footing.
Therefore it reduces the cost of footing in concreate.
5. Shoe or eccentric footing
14 | P a g e
isolated footings. The shape of isolated footings are usually square, rectangular or
circular cross section. The isolated footing is laid down on the PCC. These footing
are considerable less price compare to other types of footing. These types of footing
are used where soil bearing capacity is usually high.
Isolated footing have following advantages:
1. This types of footing are economical when columns are placed at the long distances.
2. No special knowledge or guidance require to place or used isolated footing
3. Excavation, form work and reinforcement placement is easy through isolated footing.
2. Flat or pad or plain footing:
These kind of footing are usually square, rectangular and circular cross section which
are usually under individual column. Flat or plain footing is one of the shallow
foundation. That is circular, square or rectangular slab with uniform thickness.
3. Stepped footing:
As suggest name, it resembling that footings are stacked upon one another as steps.
These types of footing are made from concrete cross section and stacked upon each
other. These types of footing are usually used residential building construction.
4. Sloped footing:
Sloped footing are trapezoidal footings. This types of footing prepare with great care and
can be observed that top slop of 45 degree is maintain around all sides. If compare
trapezoidal footing with flat footing then it require less concreate compare to flat footing.
Therefore it reduces the cost of footing in concreate.
5. Shoe or eccentric footing
14 | P a g e

Shoe or eccentric footing is the half footing slid from the original shape of footing and it
shape was shoe type. That provided at the corner of the plot that will be no provision of
setback area. That require proper boundary for construction. The column is provided and
loaded at the boundary of the footing. The shoe bearing are constructed when soil bearing
capacity is normal to 24 kN/m2.
Answer: 18
Types of footing system:
Stump pad footings :
The stump is the basic and simplest footing which is most familiar that used to kept vertical
support and keep withstand from transferring of building loads to the foundations. The
function of stump is to keep support of timber framed and this types of footing is most
cost effective. Mainly three types of material have used for stumps such as timber,
concrete and steel.
Stump pad footing
The stumps must have timber or concrete put inside the base of stump. That will to spread
the load transferred to the stump from the construction building. The support underneath the
15 | P a g e
shape was shoe type. That provided at the corner of the plot that will be no provision of
setback area. That require proper boundary for construction. The column is provided and
loaded at the boundary of the footing. The shoe bearing are constructed when soil bearing
capacity is normal to 24 kN/m2.
Answer: 18
Types of footing system:
Stump pad footings :
The stump is the basic and simplest footing which is most familiar that used to kept vertical
support and keep withstand from transferring of building loads to the foundations. The
function of stump is to keep support of timber framed and this types of footing is most
cost effective. Mainly three types of material have used for stumps such as timber,
concrete and steel.
Stump pad footing
The stumps must have timber or concrete put inside the base of stump. That will to spread
the load transferred to the stump from the construction building. The support underneath the
15 | P a g e

stump is called a soleplate or pad. Generally concrete stumps are providing with the concrete
pad and timber stumps are provided with the timber soleplates.
Strip footing:
Substantial footing supports of reinforced concreate require for construction of building that
contain external and internal masonry walls which are solid brick, brick veneer, cavity wall
or concrete block and stonewall. The reinforced concrete footings are usually known as strip
footings and continuous surrounded to the entire perimeter of the building. The strip footing
requires a minimum particular depth of the concrete that make sure about footings have
adequate strength. The depth called the overall depth of the strip footing and its symbol as
Df.
Another foot system such as stepped footing, concrete footing, pier and beam footing used in
commercial low rise constructions.
Answer: 19:
Brick bases.
Engineered timber products
Panel system of concrete and AAC
Suspended and slab on ground concrete slab floors.
Timber and steel floor construction.
16 | P a g e
pad and timber stumps are provided with the timber soleplates.
Strip footing:
Substantial footing supports of reinforced concreate require for construction of building that
contain external and internal masonry walls which are solid brick, brick veneer, cavity wall
or concrete block and stonewall. The reinforced concrete footings are usually known as strip
footings and continuous surrounded to the entire perimeter of the building. The strip footing
requires a minimum particular depth of the concrete that make sure about footings have
adequate strength. The depth called the overall depth of the strip footing and its symbol as
Df.
Another foot system such as stepped footing, concrete footing, pier and beam footing used in
commercial low rise constructions.
Answer: 19:
Brick bases.
Engineered timber products
Panel system of concrete and AAC
Suspended and slab on ground concrete slab floors.
Timber and steel floor construction.
16 | P a g e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Answer: 20
The basic requirement of the wall system is to cover surrounding medium and limited are
with different material such concrete, cement and other construction material, however as
technology developed then requirement of wall system may also change with the wall
system. sometimes that use for protection, sometimes developed from keep separate
distance from social people, sometime it used for protect against heat, air, temperature,
humidity, cold and other natural climate change which difficult to sustain by human being
at all time. Different terms and definitions are selected for wall system such as exterior
cladding, wet zone, and dry zone. Drainage plane, air retarder, vapour retarder, insulation
element, structural elements, interface condition, flashing, wetting, drying, storage
capacity etc. affected to wall system.
Answer: 21
Composite wall featuring tilt-slab, post and beam, pole and truss and portal frame.
Earth walls, including rammed earth and mud brick.
Framed walls incorporating timber, engineered timber products and lightweight
section steel.
Masonry walls incorporating cavity brick, single-leaf masonry and lightweight
concrete (AAC).
Answer: 22
boarding
coatings over base materials
sheeting
tilt-slab
Unfired, fired and autoclaved masonry.
Answer: 23
Relevant service include for wall cladding system:
ducting for heating and cooling
electrical, electronic and communication systems
extractive vacuum and exhaust systems
passive and active fire detection and prevention systems
17 | P a g e
The basic requirement of the wall system is to cover surrounding medium and limited are
with different material such concrete, cement and other construction material, however as
technology developed then requirement of wall system may also change with the wall
system. sometimes that use for protection, sometimes developed from keep separate
distance from social people, sometime it used for protect against heat, air, temperature,
humidity, cold and other natural climate change which difficult to sustain by human being
at all time. Different terms and definitions are selected for wall system such as exterior
cladding, wet zone, and dry zone. Drainage plane, air retarder, vapour retarder, insulation
element, structural elements, interface condition, flashing, wetting, drying, storage
capacity etc. affected to wall system.
Answer: 21
Composite wall featuring tilt-slab, post and beam, pole and truss and portal frame.
Earth walls, including rammed earth and mud brick.
Framed walls incorporating timber, engineered timber products and lightweight
section steel.
Masonry walls incorporating cavity brick, single-leaf masonry and lightweight
concrete (AAC).
Answer: 22
boarding
coatings over base materials
sheeting
tilt-slab
Unfired, fired and autoclaved masonry.
Answer: 23
Relevant service include for wall cladding system:
ducting for heating and cooling
electrical, electronic and communication systems
extractive vacuum and exhaust systems
passive and active fire detection and prevention systems
17 | P a g e

plumbing and drainage powered systems for operating doors and windows
Smoke control and containment systems.
Answer: 24
gable including dual pitch
hip
north light
rafter and purlin
skillion
prefabricated and site fabricated trussed roof
Framing.
Answer: 25
Width of the opening and combine load.
Answer: 26
As shown in figure below, the timber windows frames are needed for flashing under the sill
which require to stop water traveling to the inside wall lining. The side flashing also
essential in order to prevent water travelling to the back of the stiles. Usually developer
provides a groove in the stile in which to tuck the flashing.
Installation of flashing
In case head of the windows may be express to weather, the head of the windows require to
be flashed to terminate any water pouring inside.
18 | P a g e
Smoke control and containment systems.
Answer: 24
gable including dual pitch
hip
north light
rafter and purlin
skillion
prefabricated and site fabricated trussed roof
Framing.
Answer: 25
Width of the opening and combine load.
Answer: 26
As shown in figure below, the timber windows frames are needed for flashing under the sill
which require to stop water traveling to the inside wall lining. The side flashing also
essential in order to prevent water travelling to the back of the stiles. Usually developer
provides a groove in the stile in which to tuck the flashing.
Installation of flashing
In case head of the windows may be express to weather, the head of the windows require to
be flashed to terminate any water pouring inside.
18 | P a g e

Answer: 27
concrete, clay and metal tiles
shakes and shingles
Short and long run metal sheeting.
Answer: 28
The following are the examples for effective communication skills used when consulting
with other such as client and sub-contractor.
The communication skill are two types, it could be verbal and non-verbal. Verbal
communication skills are deliver to other person such as client with speaking and listening
with them. Whereas non-verbal skills are the include expression and gesture from body
language deliver to client without speak.
important things in communication skills is listening properly when deliver by someone
especially client. Good listeners are always good communicator. No one likes
communication with someone who did not care about listen to other person. So good
communication skill have essential quality such as listening.
19 | P a g e
concrete, clay and metal tiles
shakes and shingles
Short and long run metal sheeting.
Answer: 28
The following are the examples for effective communication skills used when consulting
with other such as client and sub-contractor.
The communication skill are two types, it could be verbal and non-verbal. Verbal
communication skills are deliver to other person such as client with speaking and listening
with them. Whereas non-verbal skills are the include expression and gesture from body
language deliver to client without speak.
important things in communication skills is listening properly when deliver by someone
especially client. Good listeners are always good communicator. No one likes
communication with someone who did not care about listen to other person. So good
communication skill have essential quality such as listening.
19 | P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

The communication also consider through non-verbal communication through body
language, eye contact, tone, gesture with help of massage try to convey to listener or client.
A relaxed and open arms will encourage to allow speak openly with communicator.
Concision and clarity:
Good communication means did not means talk too much and too little. The good
communicator try to convey message in few words as possible as receiver person can
understand. Always focus on what you want to deliver clearly and directly without added
additional words and sentences. Think about what you are trying to say before deliver. That
helps you to express your though and boost confident.
Confidence:
It is essential to be confidence while interaction with client. The confidence shows your
truth and sincerity about the project or any work which you trying to deliver. The confidence
can be simple as making eye contact with client and express your though friendly and freely.
It is also important voice and sound quality that means it did not present with loud voice
which sounds arrogant.
Respect:
People will more comfortable if your provide respect with special communication word and
behave more friendly with you. In case communication through cell phone then avoid
disturbance and focus on conversion. The respect is quality element of communication
skills and it is require while communicated with client. If you want to earn respect someone
then It is require to give respect someone.
Friendliness:
The friendliness tones means personal question, simple smile, casual gesture, without
arrogance that will encourage your confidence and helps to deliver easy way to convey your
talk to listener.
Body language:
the body language is the non-verbal part of communication skills. That was also important
while dealing with client or project manager. The body language itself said to receiver in
manner of positive and negative term. The body should straight and relax while dealing with
client. Make eye contact with the person who listen you or person who are deliver to words.
20 | P a g e
language, eye contact, tone, gesture with help of massage try to convey to listener or client.
A relaxed and open arms will encourage to allow speak openly with communicator.
Concision and clarity:
Good communication means did not means talk too much and too little. The good
communicator try to convey message in few words as possible as receiver person can
understand. Always focus on what you want to deliver clearly and directly without added
additional words and sentences. Think about what you are trying to say before deliver. That
helps you to express your though and boost confident.
Confidence:
It is essential to be confidence while interaction with client. The confidence shows your
truth and sincerity about the project or any work which you trying to deliver. The confidence
can be simple as making eye contact with client and express your though friendly and freely.
It is also important voice and sound quality that means it did not present with loud voice
which sounds arrogant.
Respect:
People will more comfortable if your provide respect with special communication word and
behave more friendly with you. In case communication through cell phone then avoid
disturbance and focus on conversion. The respect is quality element of communication
skills and it is require while communicated with client. If you want to earn respect someone
then It is require to give respect someone.
Friendliness:
The friendliness tones means personal question, simple smile, casual gesture, without
arrogance that will encourage your confidence and helps to deliver easy way to convey your
talk to listener.
Body language:
the body language is the non-verbal part of communication skills. That was also important
while dealing with client or project manager. The body language itself said to receiver in
manner of positive and negative term. The body should straight and relax while dealing with
client. Make eye contact with the person who listen you or person who are deliver to words.
20 | P a g e

The eye contact should be in eye towards the receiver and do not look here and there while
taking with client. That indicate lake of confident. Use hand movement and gesture when it
require else do not use hand movement. More body and hand movement sign of lack of
confident and that result indicate that communicator may be lay about that talk.
Fluency in speech:
Usually English language is common language to deal with unknown person. In
professional, there are English language used to deliver talk. In many case client would like
to receive comment and communication in mother tongue language. So speaker should have
enough knowledge about both language. Also able to deliver speech in both language.
English language would be first priority to deliver speech to client. Make sure you are not
getting fumble while talking with them that would also sign of lack of confidence and not
sure about your speech.
21 | P a g e
taking with client. That indicate lake of confident. Use hand movement and gesture when it
require else do not use hand movement. More body and hand movement sign of lack of
confident and that result indicate that communicator may be lay about that talk.
Fluency in speech:
Usually English language is common language to deal with unknown person. In
professional, there are English language used to deliver talk. In many case client would like
to receive comment and communication in mother tongue language. So speaker should have
enough knowledge about both language. Also able to deliver speech in both language.
English language would be first priority to deliver speech to client. Make sure you are not
getting fumble while talking with them that would also sign of lack of confidence and not
sure about your speech.
21 | P a g e

Task:1
Introduction:
The constructed building was not heritage item. However this report has been prepared to
respond of requirement of woollahra council which provide a demolition report for establish
new development. The historical information have bene obtain from councils local history
library. That contains development and construction building files, also contain council rates
lists held through Woollahra Local history Centre.
The report should be read in conjunction with the accompanying Statement of
Environmental Effects prepared by GSA Planning, which includes a detailed discussion of
the character and context of the area.
Access: this building is not occupied yet.
The documentation divided in to six divisions. That include introduction, site and surrounds,
heritage planning context, subdivision history, significant consideration and conclusion.
Site and Surrounds:
Site location and Map:
The site located around 4 km east of the Sydney CBD and 2 km from the Bondi Junction and
situated within the local Government Area of Woollahra Council.
22 | P a g e
Introduction:
The constructed building was not heritage item. However this report has been prepared to
respond of requirement of woollahra council which provide a demolition report for establish
new development. The historical information have bene obtain from councils local history
library. That contains development and construction building files, also contain council rates
lists held through Woollahra Local history Centre.
The report should be read in conjunction with the accompanying Statement of
Environmental Effects prepared by GSA Planning, which includes a detailed discussion of
the character and context of the area.
Access: this building is not occupied yet.
The documentation divided in to six divisions. That include introduction, site and surrounds,
heritage planning context, subdivision history, significant consideration and conclusion.
Site and Surrounds:
Site location and Map:
The site located around 4 km east of the Sydney CBD and 2 km from the Bondi Junction and
situated within the local Government Area of Woollahra Council.
22 | P a g e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Site location (Red Mark subject location)
Site introduction:
The location is situation on the northern side of cross street between Bay street and well
known as No.33 cross street. The site shape is irregular parcel of land and also contain 63.19
m, added estern boundary of 70.23m , south boundary 52.23 m with cross street and western
boundary 59.55 m. the site occupied 3675 m2 area.
Heritage planning context:
The site subjected to 3(a) under council of LEP, gazetted 10th March. The site is not as
condition of as heritage structure. The demolition of building require consent from council.
Any demolition of building within the woollahra council require to prepare demolition
report as per policy of demolition.
23 | P a g e
Site introduction:
The location is situation on the northern side of cross street between Bay street and well
known as No.33 cross street. The site shape is irregular parcel of land and also contain 63.19
m, added estern boundary of 70.23m , south boundary 52.23 m with cross street and western
boundary 59.55 m. the site occupied 3675 m2 area.
Heritage planning context:
The site subjected to 3(a) under council of LEP, gazetted 10th March. The site is not as
condition of as heritage structure. The demolition of building require consent from council.
Any demolition of building within the woollahra council require to prepare demolition
report as per policy of demolition.
23 | P a g e

Requirement for Demolition reports:
As per council’s guidance for “Demolition reports”. Following information require in order
to mention that building is not identified in as planning instrument.
Date of original construction.
Details of original designer or builder.
Copy of original plan.
Subdivision history.
List of current owners as well as past owner, in case site occupied to other provide
statement.
Photographs of the existing building and other structures.
Description of the current construction and building site.
Structural report.
Conclusion regards to heritage important of property, retention of any
construction/building elements.
BUILDING AND SUBDIVISION HISTORY
Subdivision history:
The site was a part of john Piper Estate since 1816. In 1827 the heritage was converted to
the Cooper and Levey Estate. The Cooper and Levey Estate was became Cooper Estate. At
1846 subdivision of part of Cooper Estate through surveyor General Thomas Mitchell
24 | P a g e
As per council’s guidance for “Demolition reports”. Following information require in order
to mention that building is not identified in as planning instrument.
Date of original construction.
Details of original designer or builder.
Copy of original plan.
Subdivision history.
List of current owners as well as past owner, in case site occupied to other provide
statement.
Photographs of the existing building and other structures.
Description of the current construction and building site.
Structural report.
Conclusion regards to heritage important of property, retention of any
construction/building elements.
BUILDING AND SUBDIVISION HISTORY
Subdivision history:
The site was a part of john Piper Estate since 1816. In 1827 the heritage was converted to
the Cooper and Levey Estate. The Cooper and Levey Estate was became Cooper Estate. At
1846 subdivision of part of Cooper Estate through surveyor General Thomas Mitchell
24 | P a g e

manage the eastern portion of cross street between Bay Street and New south Road No. 33
cross street situated at the section R of this location.
At the time of 1850s, the R section was developed and manage to create seven irregular
shaped arrange from the original design.
No.33 cross street was situated on Lot 60a
1. The acre allocation called ad Heath and leased to john Grey in 1860. In year of 1889,
the Lot separate out into two separate sized, that was western allotment. The western
allotment managed to build heath Villa and remaining eastern part manage to empty
space.
2. In year of 1927 the Heath Estate was separate out into six division. The sub-
allotment cover four cross street and two battle axe allotment.
3. In 1934 ,valuer Generals list suggested total five building were manage to
constructed.
Physical Analysis
The construction at No.33 cross street have a six storey complex and was developed at the
time between 1989 and 1991. The construction was developed at five start Ritz Carlton
hotel. As per construction of interior and exterior the building elements and aesthetic
appearance were considered while designing and construction and provide luxurious output.
If consider opened interiors considering in a years of 18th and 19th century and the art works
provided from southerbys London and other remaining construction. As per the woolllahra
Council’s construction application records, there were considerable improvement and
construction of building applications for the site while construction of heritage like royal
hotel. Mostly variation occur for the retailer or retail fit outsource.
Following information provided and associate application have changed so far for building
construction till this years.
1. In year 1988, hotel and retailing development owner of sahben groups of companies.
2. In years 1988-89 work application for demolition and owner at that time was Trust
Company Ltd.
3. In Years of 1989-90 work allocation for new development by Trust Company Ltd.
25 | P a g e
cross street situated at the section R of this location.
At the time of 1850s, the R section was developed and manage to create seven irregular
shaped arrange from the original design.
No.33 cross street was situated on Lot 60a
1. The acre allocation called ad Heath and leased to john Grey in 1860. In year of 1889,
the Lot separate out into two separate sized, that was western allotment. The western
allotment managed to build heath Villa and remaining eastern part manage to empty
space.
2. In year of 1927 the Heath Estate was separate out into six division. The sub-
allotment cover four cross street and two battle axe allotment.
3. In 1934 ,valuer Generals list suggested total five building were manage to
constructed.
Physical Analysis
The construction at No.33 cross street have a six storey complex and was developed at the
time between 1989 and 1991. The construction was developed at five start Ritz Carlton
hotel. As per construction of interior and exterior the building elements and aesthetic
appearance were considered while designing and construction and provide luxurious output.
If consider opened interiors considering in a years of 18th and 19th century and the art works
provided from southerbys London and other remaining construction. As per the woolllahra
Council’s construction application records, there were considerable improvement and
construction of building applications for the site while construction of heritage like royal
hotel. Mostly variation occur for the retailer or retail fit outsource.
Following information provided and associate application have changed so far for building
construction till this years.
1. In year 1988, hotel and retailing development owner of sahben groups of companies.
2. In years 1988-89 work application for demolition and owner at that time was Trust
Company Ltd.
3. In Years of 1989-90 work allocation for new development by Trust Company Ltd.
25 | P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4. In years of 2000-01 work for alternation and addition for hotel development and
expansion by Stamford property service.
Significant consideration:
5.2 Significance
The considerable significance of this site has been collect with observe to the NSW as
discuss following:
Evaluation significant:
The hotel only establish for enough years and have potential customer and client while
opening. There were royal customer also associate with the hotel. The architecture and
owner also focus on the cultural interest and development but there were no regular visited
by potential source and there were no instrument to attract potential client or customer. The
scenario of royal customer was not regular, therefor it cannot consider potential historic
significance.
Aesthetic significance:
The hotel is not constructed to aesthetical good characteristics and quality landmarks also.
There were no special feature which make potentially consideration and demonstrate
aesthetic distractive. Technical achievement also low.
Social significant:
The construction was not consider as heritage and nor any special allocation which provide
social significant appearance. The building development was not too sound which attract
heritage people for visit regularly.
Scientific research and significance:
The construction of building was built through traditionally and simple characteristics. There
was no evidence find to provide such scientific research and consideration.
Conclusion:
26 | P a g e
expansion by Stamford property service.
Significant consideration:
5.2 Significance
The considerable significance of this site has been collect with observe to the NSW as
discuss following:
Evaluation significant:
The hotel only establish for enough years and have potential customer and client while
opening. There were royal customer also associate with the hotel. The architecture and
owner also focus on the cultural interest and development but there were no regular visited
by potential source and there were no instrument to attract potential client or customer. The
scenario of royal customer was not regular, therefor it cannot consider potential historic
significance.
Aesthetic significance:
The hotel is not constructed to aesthetical good characteristics and quality landmarks also.
There were no special feature which make potentially consideration and demonstrate
aesthetic distractive. Technical achievement also low.
Social significant:
The construction was not consider as heritage and nor any special allocation which provide
social significant appearance. The building development was not too sound which attract
heritage people for visit regularly.
Scientific research and significance:
The construction of building was built through traditionally and simple characteristics. There
was no evidence find to provide such scientific research and consideration.
Conclusion:
26 | P a g e

Considered with regard to the NSW Heritage Assessment Criteria, the existing site and
building are considered to have some historical interest as it hosted many high profile
guests. However the building is 21 years old and has been vacant for nearly 18 months.
Based on our assessment, we are of the opinion that the building is not of such potential
heritage value that it should be retained.
While it will be remembered by former guests and surrounding residents, the hotel since its
closure is unlikely to have potential social significance, particularly extending into the
future. In addition the hotel does not provide any other historical values that would make the
building potentially significant. Therefore, we are suggest that retention is not required, and
a suitable replacement building could be constructed, subjected to obtaining the necessary
approval.
Task: 2
Adequacy report:
Introduction:
The report have prepare as per client require to develop new construction for low rise
commercial building. It is assume that client want to construct new building at NSW state
and discuss his requirement. This report present about the assessment about the selection
particular information regards to construction whether it observation of types of soil, footing
system, damp courses and barriers. The framing, cladding and windows structure suitable as
per site requirement and location of the low rise commercial building construction.
Body:
As per client requirement and given site specification i.e. for individual site there are two
class which are class A and class M soils are use respectively. For site A Strip footing
suggest to use for construction. The depth of concrete 300, width of concrete 300 and Top
and Bottom Reo. 3-8 TM. Whereas for Soil M depth in case strip footing used then footing
size would be depth of concrete 500, width of concrete 300 and Top and Bottom Reo. 3-
12TM. 100 X 75 bearers are used to span between the walls and isolated piers, 230 x 230.
Flooring:
Strips of flooring 75 and 100 wide by 19 thick can be place over the joist after frame
erected. That will require double joists under some walls to provide a bases in order to
27 | P a g e
building are considered to have some historical interest as it hosted many high profile
guests. However the building is 21 years old and has been vacant for nearly 18 months.
Based on our assessment, we are of the opinion that the building is not of such potential
heritage value that it should be retained.
While it will be remembered by former guests and surrounding residents, the hotel since its
closure is unlikely to have potential social significance, particularly extending into the
future. In addition the hotel does not provide any other historical values that would make the
building potentially significant. Therefore, we are suggest that retention is not required, and
a suitable replacement building could be constructed, subjected to obtaining the necessary
approval.
Task: 2
Adequacy report:
Introduction:
The report have prepare as per client require to develop new construction for low rise
commercial building. It is assume that client want to construct new building at NSW state
and discuss his requirement. This report present about the assessment about the selection
particular information regards to construction whether it observation of types of soil, footing
system, damp courses and barriers. The framing, cladding and windows structure suitable as
per site requirement and location of the low rise commercial building construction.
Body:
As per client requirement and given site specification i.e. for individual site there are two
class which are class A and class M soils are use respectively. For site A Strip footing
suggest to use for construction. The depth of concrete 300, width of concrete 300 and Top
and Bottom Reo. 3-8 TM. Whereas for Soil M depth in case strip footing used then footing
size would be depth of concrete 500, width of concrete 300 and Top and Bottom Reo. 3-
12TM. 100 X 75 bearers are used to span between the walls and isolated piers, 230 x 230.
Flooring:
Strips of flooring 75 and 100 wide by 19 thick can be place over the joist after frame
erected. That will require double joists under some walls to provide a bases in order to
27 | P a g e

provide flooring and wall plate. The flooring can be swell in case cramped and nailed in case
bare to the weather condition. Therefore it may not be laid until the assembly of brickwork
is not completed and roof is not constructed.
In order to construct as per client requirement of flooring system, it is require to use concrete
slab on ground or suspended timber floor. In NSW a reinforced concrete slab on ground
considering integrated edge beam is usually design and obtain certificate from engineer also.
local council and leading institute have specific requirement. Following present steel
flooring using timber also.
Steel Flooring system
Walling system:
For this construction sub floor walling system have been used for construction. For the floor
walls for Masonry Veneer Construction are usually used in order to provide support as
suspended floor for the ground and suggested construction as following explain.
1. Single lead masonry that connected to piers like 110mm brick wall couple with 120 x
230 connected to piers.
2. 230mm brick wall in order to stabilise the high walls.
3. 270mm cavity walls in order to provide two story brick veneer construction.
28 | P a g e
bare to the weather condition. Therefore it may not be laid until the assembly of brickwork
is not completed and roof is not constructed.
In order to construct as per client requirement of flooring system, it is require to use concrete
slab on ground or suspended timber floor. In NSW a reinforced concrete slab on ground
considering integrated edge beam is usually design and obtain certificate from engineer also.
local council and leading institute have specific requirement. Following present steel
flooring using timber also.
Steel Flooring system
Walling system:
For this construction sub floor walling system have been used for construction. For the floor
walls for Masonry Veneer Construction are usually used in order to provide support as
suspended floor for the ground and suggested construction as following explain.
1. Single lead masonry that connected to piers like 110mm brick wall couple with 120 x
230 connected to piers.
2. 230mm brick wall in order to stabilise the high walls.
3. 270mm cavity walls in order to provide two story brick veneer construction.
28 | P a g e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

Walling system
Roofing system:
The construction used brick Veneer type construction. In this case truss roof is used for
construction low rise commercial building. In case truss roof is used for total mass of the
roof is carried through external wall only. The attached pier can provided to closer as per the
convince of roof construction. The construction of internal wall are no loaded bearing and
further that advantage should be use such as piers can be spaced in order to place at
maximum centre which need not under the internal wall. In case, ordinary roof can place the
load to the internal walls and piers can be built through all load bearing walls.
100 x 75 bearers are used to span between the walls and isolated piers, which was 230 x 230.
Joints are manage to skew to the bearer. Must be place 2-3 courses above the finish ground
level in areas subject to increase salt damp which prevent salt in solution which increase
through the wall.
Cladding system:
The masonry with the 25 to 40 mm cavity between new and existing wall can be developed.
The cavity should be washed out. Any specific masonry wall should be manage to attached
to the new masonry veneer with ties at the standard spacing such as Ramset, Dynabolt and
Abey or different type of masonry wall ties with 600 x 600 centres.
29 | P a g e
Roofing system:
The construction used brick Veneer type construction. In this case truss roof is used for
construction low rise commercial building. In case truss roof is used for total mass of the
roof is carried through external wall only. The attached pier can provided to closer as per the
convince of roof construction. The construction of internal wall are no loaded bearing and
further that advantage should be use such as piers can be spaced in order to place at
maximum centre which need not under the internal wall. In case, ordinary roof can place the
load to the internal walls and piers can be built through all load bearing walls.
100 x 75 bearers are used to span between the walls and isolated piers, which was 230 x 230.
Joints are manage to skew to the bearer. Must be place 2-3 courses above the finish ground
level in areas subject to increase salt damp which prevent salt in solution which increase
through the wall.
Cladding system:
The masonry with the 25 to 40 mm cavity between new and existing wall can be developed.
The cavity should be washed out. Any specific masonry wall should be manage to attached
to the new masonry veneer with ties at the standard spacing such as Ramset, Dynabolt and
Abey or different type of masonry wall ties with 600 x 600 centres.
29 | P a g e

Footing with different cladding.
As discuss earlier all points that cover all requirement of client and suggest necessary points
about the construction of commercial building.
Task: 3
Supervision checklist:
Supervisor checklist for construction of commercial
construction
Component Action or comment
Foundation commencement data
Construction safety plan received from
builder
Available of electric source
Sub-contractor agreement. (in case present)
Plan site approval
30 | P a g e
As discuss earlier all points that cover all requirement of client and suggest necessary points
about the construction of commercial building.
Task: 3
Supervision checklist:
Supervisor checklist for construction of commercial
construction
Component Action or comment
Foundation commencement data
Construction safety plan received from
builder
Available of electric source
Sub-contractor agreement. (in case present)
Plan site approval
30 | P a g e

Facility of water source
Quality of floor and roof construction
system
The construction standard follow or not
Surrounding position, location and usual
weather condition.
Height from ground level of building
Parking facility
Emergency exit facility.
Facility of rubbish removal
Methodology for hazardous
Site, location cleanliness
Internal walls considerable set with at least
+ 10 below the bottom chord of the truss.
Wall insulation and installation
Quality of construction and appearance
Licence availability for construction
In case superior qualification constructor
education engineer require, provide licence
and certificate.
References
(2018). Retrieved 7 February 2018, from
http://www.tandfonline.com/doi/abs/10.1080/0144619042000287787
(2018). Retrieved 7 February 2018, from
http://journals.sagepub.com/doi/abs/10.1177/107110078100200110?
journalCode=faia'
Akintoye, A., McIntosh, G., & Fitzgerald, E. (2018). A survey of supply
chain collaboration and management in the UK construction industry.
Retrieved 7 February 2018, from
Black, J. (2018). Higher Density Housing and Transport in Australian
Cities. Retrieved 7 February 2018, from
31 | P a g e
Quality of floor and roof construction
system
The construction standard follow or not
Surrounding position, location and usual
weather condition.
Height from ground level of building
Parking facility
Emergency exit facility.
Facility of rubbish removal
Methodology for hazardous
Site, location cleanliness
Internal walls considerable set with at least
+ 10 below the bottom chord of the truss.
Wall insulation and installation
Quality of construction and appearance
Licence availability for construction
In case superior qualification constructor
education engineer require, provide licence
and certificate.
References
(2018). Retrieved 7 February 2018, from
http://www.tandfonline.com/doi/abs/10.1080/0144619042000287787
(2018). Retrieved 7 February 2018, from
http://journals.sagepub.com/doi/abs/10.1177/107110078100200110?
journalCode=faia'
Akintoye, A., McIntosh, G., & Fitzgerald, E. (2018). A survey of supply
chain collaboration and management in the UK construction industry.
Retrieved 7 February 2018, from
Black, J. (2018). Higher Density Housing and Transport in Australian
Cities. Retrieved 7 February 2018, from
31 | P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Fundamentals of Building Construction. (2018). Google Books. Retrieved
7 February 2018, from https://books.google.co.in/books?
hl=en&lr=&id=j9kov8X-
0n8C&oi=fnd&pg=PT10&dq=material+and+methods+used+in+cons
truction+&ots=SyY4wuCG0Z&sig=1LSKb7Beoa2Cgliki6NNuMk1BB8#
v=onepage&q=material%20and%20methods%20used%20in
%20construction&f=false
Giridharan, R., Ganesan, S., & Lau, S. (2018). Daytime urban heat island
effect in high-rise and high-density residential developments in Hong
Kong. Retrieved 7 February 2018, from
Green, M. (2018). Recent developments in photovoltaics. Retrieved 7
February 2018, from
How Safe Are Our Large, Lightly Reinforced Concrete Beams, Slabs, and
Footings?. (2018). Retrieved 7 February 2018, from
Integrating Construction Process Documentation into Building Information
Modeling | Journal of Construction Engineering and Management | Vol
134, No 7. (2018). Ascelibrary.org. Retrieved 7 February 2018, from
https://ascelibrary.org/doi/abs/10.1061/(ASCE)0733-
9364(2008)134:7(509)
Love, P., & Irani, Z. (2018). An exploratory study of information
technology evaluation and benefits management practices of SMEs in
the construction industry. Retrieved 7 February 2018, from
Monahan, J., & Powell, J. (2018). An embodied carbon and energy analysis
of modern methods of construction in housing: A case study using a
lifecycle assessment framework. Retrieved 7 February 2018, from
Odeh, A., & Battaineh, H. (2018). Causes of construction delay:
traditional contracts. Retrieved 7 February 2018, from
Project Management in Construction. (2018). Google Books. Retrieved 7
February 2018, from https://books.google.co.in/books?
hl=en&lr=&id=KA51BgAAQBAJ&oi=fnd&pg=PA8&dq=industry+peopl
e+consult+during+plannig+and+construction+&ots=kTzOWPthzV&si
g=cEajCdjwCQ73ksiRph9PwzrNokU#v=onepage&q&f=false
Staunton, D., Marlin, S., Stratowa, C., Dustin, M., & Springer, T. (2018).
Primary structure of ICAM-1 demonstrates interaction between
members of the immunoglobulin and integrin supergene families.
Retrieved 7 February 2018, from
Sustainable Construction. (2018). Google Books. Retrieved 7 February
2018, from https://books.google.co.in/books?
hl=en&lr=&id=2xgWCgAAQBAJ&oi=fnd&pg=PR15&dq=principles+to
+commerical+low+rise+construction+&ots=G8Ut6Kc_xB&sig=zBnQ
k6Lip9KEFwzRBDemLHEBaMs#v=onepage&q=principles%20to
%20commerical%20low%20rise%20construction&f=false
32 | P a g e
7 February 2018, from https://books.google.co.in/books?
hl=en&lr=&id=j9kov8X-
0n8C&oi=fnd&pg=PT10&dq=material+and+methods+used+in+cons
truction+&ots=SyY4wuCG0Z&sig=1LSKb7Beoa2Cgliki6NNuMk1BB8#
v=onepage&q=material%20and%20methods%20used%20in
%20construction&f=false
Giridharan, R., Ganesan, S., & Lau, S. (2018). Daytime urban heat island
effect in high-rise and high-density residential developments in Hong
Kong. Retrieved 7 February 2018, from
Green, M. (2018). Recent developments in photovoltaics. Retrieved 7
February 2018, from
How Safe Are Our Large, Lightly Reinforced Concrete Beams, Slabs, and
Footings?. (2018). Retrieved 7 February 2018, from
Integrating Construction Process Documentation into Building Information
Modeling | Journal of Construction Engineering and Management | Vol
134, No 7. (2018). Ascelibrary.org. Retrieved 7 February 2018, from
https://ascelibrary.org/doi/abs/10.1061/(ASCE)0733-
9364(2008)134:7(509)
Love, P., & Irani, Z. (2018). An exploratory study of information
technology evaluation and benefits management practices of SMEs in
the construction industry. Retrieved 7 February 2018, from
Monahan, J., & Powell, J. (2018). An embodied carbon and energy analysis
of modern methods of construction in housing: A case study using a
lifecycle assessment framework. Retrieved 7 February 2018, from
Odeh, A., & Battaineh, H. (2018). Causes of construction delay:
traditional contracts. Retrieved 7 February 2018, from
Project Management in Construction. (2018). Google Books. Retrieved 7
February 2018, from https://books.google.co.in/books?
hl=en&lr=&id=KA51BgAAQBAJ&oi=fnd&pg=PA8&dq=industry+peopl
e+consult+during+plannig+and+construction+&ots=kTzOWPthzV&si
g=cEajCdjwCQ73ksiRph9PwzrNokU#v=onepage&q&f=false
Staunton, D., Marlin, S., Stratowa, C., Dustin, M., & Springer, T. (2018).
Primary structure of ICAM-1 demonstrates interaction between
members of the immunoglobulin and integrin supergene families.
Retrieved 7 February 2018, from
Sustainable Construction. (2018). Google Books. Retrieved 7 February
2018, from https://books.google.co.in/books?
hl=en&lr=&id=2xgWCgAAQBAJ&oi=fnd&pg=PR15&dq=principles+to
+commerical+low+rise+construction+&ots=G8Ut6Kc_xB&sig=zBnQ
k6Lip9KEFwzRBDemLHEBaMs#v=onepage&q=principles%20to
%20commerical%20low%20rise%20construction&f=false
32 | P a g e

The Construction Industry. (2018). Google Books. Retrieved 7 February
2018, from https://books.google.co.in/books?
hl=en&lr=&id=glkZox6TStwC&oi=fnd&pg=PR8&dq=principles+to+c
ommerical+low+rise+construction+in+australia&ots=vZfQeT3Oh8&s
ig=sQDi5XfPj5gXZDJDlWIr9Fx5h3Q#v=onepage&q&f=false
Ultimate Bearing Capacity of Footings on Sand Layer Overlying Clay -
Canadian Geotechnical Journal. (2018). Nrcresearchpress.com.
Retrieved 7 February 2018, from
http://www.nrcresearchpress.com/doi/abs/10.1139/t74-018
US6578333B1 - Integrated precast footings - Google Patents. (2018).
Patents.google.com. Retrieved 7 February 2018, from
https://patents.google.com/patent/US6578333B1/en
33 | P a g e
2018, from https://books.google.co.in/books?
hl=en&lr=&id=glkZox6TStwC&oi=fnd&pg=PR8&dq=principles+to+c
ommerical+low+rise+construction+in+australia&ots=vZfQeT3Oh8&s
ig=sQDi5XfPj5gXZDJDlWIr9Fx5h3Q#v=onepage&q&f=false
Ultimate Bearing Capacity of Footings on Sand Layer Overlying Clay -
Canadian Geotechnical Journal. (2018). Nrcresearchpress.com.
Retrieved 7 February 2018, from
http://www.nrcresearchpress.com/doi/abs/10.1139/t74-018
US6578333B1 - Integrated precast footings - Google Patents. (2018).
Patents.google.com. Retrieved 7 February 2018, from
https://patents.google.com/patent/US6578333B1/en
33 | P a g e
1 out of 33
Related Documents
![[object Object]](/_next/image/?url=%2F_next%2Fstatic%2Fmedia%2Flogo.6d15ce61.png&w=640&q=75)
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.