Technical Upgradation of Archives Website - Project Management

Verified

Added on  2023/06/11

|21
|2761
|57
AI Summary
This project management report focuses on the technical upgradation of the archives website destination in Australia. It includes project charter, planning, design processes, execution, control, and closure phases.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Topic- Technical upgradation of the website
Name of the Student
Name of the University
Author’s Note

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
Table of Contents
Project charter............................................................................................................................3
A) Project background...........................................................................................................3
B) Project purpose and justification.......................................................................................3
C) High level scope statement................................................................................................3
D) Project Methodology and Approach.................................................................................4
E) Project structure.................................................................................................................6
F) Project stakeholders and Authority....................................................................................6
G) High level risks.................................................................................................................7
H) Project schedule/Milestones..............................................................................................8
I) Budget summary.................................................................................................................8
Project planning and design processes.....................................................................................10
1) Tools and techniques needed for developing project management plan.........................10
2) Project execution for accomplishing objectives..............................................................10
3) Organization’s environmental factors that is needed for planning and delivering the
project...................................................................................................................................14
4) Organizational processes that is needed for developing project management plan........14
5) Maintaining integrity of project baseline.........................................................................15
6) Getting project approval..................................................................................................15
7) Triple constraint...............................................................................................................15
Execute project in work environment......................................................................................15
Manage project control............................................................................................................16
Document Page
2
PROJECT MANAGEMENT
1) Tools and techniques for analyzing status.......................................................................16
2) Need for updating and managing project work...............................................................16
Manage project finalization......................................................................................................16
Bibliography.............................................................................................................................18
Document Page
3
PROJECT MANAGEMENT
Project charter
A) Project background
The paper mainly focuses on the technical upgradation of the archives website
Destination in Australia. It is identified that the National archives of Australia is mainly
responsible for preserving as well as storing Commonwealth records including different
types of archival resources.
B) Project purpose and justification
It is identified that technical upgradation of the website is mainly required for
ensuring proper value of money as well as appropriate functionality of the website. It is
identified that the website will generally help in enabling the National archives for gathering
various types of user contributed photographic collection which is mainly featured on the site.
C) High level scope statement
Project objectives
The objectives include:
To upgrade the website technically
To ensure proper value of money as well as appropriate functionality of the
website
To enable the National archives for gathering various types of user contributed
photographic collection
High level project scope and requirements
In-scope: In-scope includes:

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
Technical upgradation of the website
Wireframe and visual design
CMS implementation
Front-end and back-end development
Out scope: Out scope includes
Exclusion of trainings needs
Exclusion of project supplies details
Assumptions
The assumptions include:
The entire resources that are needed will be quite easily available
The technical upgradation of the website will be completed within 118 days
Constraints
Constraints are as follows:
Technical upgradation will be completed within 118 days
The upgradation must be finished within the budget $267,520
D) Project Methodology and Approach
It is identified that agile project methodology is mainly utilized in order to upgrade
the website successfully. It is identified that the steps or stages that are used for implementing
the website are listed below:
WB
S
Task Name
0 Technical upgradation of the website
Document Page
5
PROJECT MANAGEMENT
1 Initiation phase
1.1 Business case development
1.2 Cost benefit analysis
1.3 Project charter establishment
1.4 Team members appointment
1.5 Milestone 1: Completion of initiation phase
2 Planning phase
2.1 Project plan development
2.2 Resource plan development
2.3 Financial plan development
2.4 Development of quality plan
2.5 Development of risk plan
2.6 Development of acceptance plan
2.7 Development of communication plan
2.8 Milestone 2: Completion of planning phase
3 Design Phase
3.1 Wireframe Design
3.2 Visual design
3.3 Prototype design
3.4 Milestone 3: Completion of design phase
4 Development phase
4.1 CMS implementation
4.2 Front-end development
Document Page
6
PROJECT MANAGEMENT
4.3 Back-end development
4.4 Database development
4.5 Milestone 4: Completion of development phase
5 Testing phase
5.1 Black box testing
5.2 User acceptance testing
5.3 Compatibility testing
5.4 Milestone 5: Completion of testing phase
6 Closure phase
6.1 Hosting of the website
6.2 Post-project review
6.3 Stakeholder analysis
6.4 Documentation
6.5 Milestone 6: Completion of closure phase

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
7
PROJECT MANAGEMENT
E) Project structure
Figure 1: Project Structure
(Source: Created by author)
F) Project stakeholders and Authority
Name Title Authority level
<Please Fill> Project manager Tell
<Please Fill> Project planner Tell
<Please Fill> Supervisor Advice, Inquire
<Please Fill> Technical engineer Tell, Advice
<Please Fill> Developer Consult
<Please Fill> Financial manager Delegate
<Please Fill> System analyst Consult
<Please Fill> Risk analyst Inquire
Document Page
8
PROJECT MANAGEMENT
G) High level risks
Risk No Category Risk
description
Likelihood Impact
1 Technical risk If the design for
the website is
not created
properly then it
will quite
difficult to work
within the
project.
High Very High
2 Financial risk Inappropriate
budget
estimation can
lead to shortage
of budget
Very high High
3 Resourcing Absence of
proper resources
can cause
obstruction in
project progress.
High Medium
Document Page
9
PROJECT MANAGEMENT
H) Project schedule/Milestones
Milestones Completion date Dependencies
Milestone 1: Completion of initiation phase Fri 15-06-18 5
Milestone 2: Completion of planning phase Fri 13-07-18 13
Milestone 3: Completion of design phase Fri 03-08-18 19
Milestone 4: Completion of development phase Mon 24-09-18 25
Milestone 5: Completion of testing phase Wed 24-10-18 30
Milestone 6: Completion of closure phase Tue 06-11-18 36
I) Budget summary
Task Name Duration Cost
Technical upgradation of the website 118 days $267,520.00
Initiation phase 16 days $21,680.00
Business case development 4 days $8,000.00
Cost benefit analysis 3 days $2,880.00
Project charter establishment 4 days $4,800.00
Team members appointment 5 days $6,000.00
Milestone 1: Completion of initiation
phase
0 days $0.00
Planning phase 20 days $68,320.00
Project plan development 5 days $17,600.00
Resource plan development 4 days $8,000.00
Financial plan development 5 days $3,600.00
Development of quality plan 6 days $11,520.00

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
Development of risk plan 4 days $8,640.00
Development of acceptance plan 5 days $13,200.00
Development of communication plan 6 days $5,760.00
Milestone 2: Completion of planning
phase
0 days $0.00
Design Phase 15 days $39,680.00
Wireframe Design 5 days $8,000.00
Visual design 4 days $13,440.00
Prototype design 6 days $18,240.00
Milestone 3: Completion of design phase 0 days $0.00
Development phase 36 days $68,240.00
CMS implementation 7 days $12,320.00
Front-end development 8 days $23,040.00
Back-end development 9 days $7,920.00
Database development 12 days $24,960.00
Milestone 4: Completion of development
phase
0 days $0.00
Testing phase 22 days $48,800.00
Black box testing 5 days $10,000.00
User acceptance testing 8 days $29,440.00
Compatibility testing 9 days $9,360.00
Milestone 5: Completion of testing phase 0 days $0.00
Closure phase 9 days $20,800.00
Hosting of the website 3 days $8,160.00
Document Page
11
PROJECT MANAGEMENT
Post-project review 2 days $4,000.00
Stakeholder analysis 2 days $3,360.00
Documentation 2 days $5,280.00
Milestone 6: Completion of closure phase 0 days $0.00
Project planning and design processes
1) Tools and techniques needed for developing project management plan
The tools and techniques that are generally required for developing the management plan
are as follows:
Gantt chart
Critical path method
Pert Chart
2) Project execution for accomplishing objectives
The project can be executed successfully for accomplishing the objectives by using
the plan that is provided below along with the project dependencies.
Task Name Duration Start Finish Dependencies
Technical upgradation of the
website
118 days
Fri 25-05-
18
Tue 06-11-
18
Initiation phase 16 days
Fri 25-05-
18
Fri 15-06-
18
Document Page
12
PROJECT MANAGEMENT
Business case development 4 days
Fri 25-05-
18
Wed 30-05-
18
Cost benefit analysis 3 days
Thu 31-05-
18
Mon 04-06-
18
2
Project charter establishment 4 days
Tue 05-06-
18
Fri 08-06-
18
3
Team members appointment 5 days
Mon 11-
06-18
Fri 15-06-
18
4
Milestone 1: Completion of
initiation phase
0 days
Fri 15-06-
18
Fri 15-06-
18
5
Planning phase 20 days
Mon 18-
06-18
Fri 13-07-
18
Project plan development 5 days
Mon 18-
06-18
Fri 22-06-
18
5
Resource plan development 4 days
Mon 25-
06-18
Thu 28-06-
18
6
Financial plan development 5 days
Mon 25-
06-18
Fri 29-06-
18
8
Development of quality plan 6 days
Fri 29-06-
18
Fri 06-07-
18
9
Development of risk plan 4 days
Mon 02-
07-18
Thu 05-07-
18
10
Development of acceptance
plan
5 days
Mon 09-
07-18
Fri 13-07-
18
11

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
13
PROJECT MANAGEMENT
Development of communication
plan
6 days
Fri 06-07-
18
Fri 13-07-
18
12
Milestone 2: Completion of
planning phase
0 days
Fri 13-07-
18
Fri 13-07-
18
13
Design Phase 15 days
Mon 16-
07-18
Fri 03-08-
18
Wireframe Design 5 days
Mon 16-
07-18
Fri 20-07-
18
14
Visual design 4 days
Mon 23-
07-18
Thu 26-07-
18
17
Prototype design 6 days
Fri 27-07-
18
Fri 03-08-
18
18
Milestone 3: Completion of
design phase
0 days
Fri 03-08-
18
Fri 03-08-
18
19
Development phase 36 days
Mon 06-
08-18
Mon 24-09-
18
CMS implementation 7 days
Mon 06-
08-18
Tue 14-08-
18
19
Front-end development 8 days
Wed 15-
08-18
Fri 24-08-
18
22
Back-end development 9 days
Mon 27-
08-18
Thu 06-09-
18
23
Database development 12 days
Fri 07-09-
18
Mon 24-09-
18
24
Document Page
14
PROJECT MANAGEMENT
Milestone 4: Completion of
development phase
0 days
Mon 24-
09-18
Mon 24-09-
18
25
Testing phase 22 days
Tue 25-09-
18
Wed 24-10-
18
Black box testing 5 days
Tue 25-09-
18
Mon 01-10-
18
26
User acceptance testing 8 days
Tue 02-10-
18
Thu 11-10-
18
28
Compatibility testing 9 days
Fri 12-10-
18
Wed 24-10-
18
29
Milestone 5: Completion of
testing phase
0 days
Wed 24-
10-18
Wed 24-10-
18
30
Closure phase 9 days
Thu 25-10-
18
Tue 06-11-
18
Hosting of the website 3 days
Thu 25-10-
18
Mon 29-10-
18
30
Post-project review 2 days
Tue 30-10-
18
Wed 31-10-
18
33
Stakeholder analysis 2 days
Thu 01-11-
18
Fri 02-11-
18
34
Documentation 2 days
Mon 05-
11-18
Tue 06-11-
18
35
Milestone 6: Completion of
closure phase
0 days
Tue 06-11-
18
Tue 06-11-
18
36
Document Page
15
PROJECT MANAGEMENT
3) Organization’s environmental factors that is needed for planning and delivering the
project
The organization’s environmental factors that are generally required for planning as
well as delivering the project are listed below:
Economic landscapes: The economic landscape must be considered properly while
planning as well as delivering the project.
Consumer needs: It is quite necessary to reflect on the needs and demands of the
customers while planning the project.
Regulatory environment: The regulatory environment must be followed properly
while delivering and planning the project.
4) Organizational processes that is needed for developing project management plan
The organizational processes that are required for developing the project management
plan are listed below:
Standard guidelines: Proper standard guidelines would be helpful in developing the
plan for project management.
Change control processes: It is necessary to follow proper change control processes
for the project while implementing the plan
Performance measurement criteria: The performance measurement criteria must be
properly followed while implementing the project management plan.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
16
PROJECT MANAGEMENT
5) Maintaining integrity of project baseline
The integrity of the project baseline is mainly maintained by tracking the schedule of
the project on a regular basis for ensuring that the entire project is on the project and it will be
completed on time.
It is identified that the project manager is mainly responsible of maintaining the
integrity of the project baseline.
6) Getting project approval
The approval for the project management plan will be achieved from the higher
authorities of the organization when they will make sure that the website upgradation will be
advantageous for them it will be helpful in bringing some return value from the investment.
7) Triple constraint
The triple constraint can be applied by utilizing steps that are as follows:
Time: The required time for the completion of the project will be around 11 days.
Cost: The entire project must be completed within the budget of around $267,520
Quality: Proper quality of the project must be maintained within the entire lifecycle
of the project.
Execute project in work environment
It is analyzed that the entire activities of the project are successfully completed for
upgrading the website while determining performance data in the closure phase of the project.
It is identified that if the project gets delayed then the entire cost that is associated
with the project gets increased and as result the project will face financial crisis. In order to
Document Page
17
PROJECT MANAGEMENT
resolve this issue, proper management budget is done so that the budget can be properly used
for completing the project.
Manage project control
1) Tools and techniques for analyzing status
The tools ad techniques that are used for analyzing status include:
Pert chart
Risk management plan
Financial plan
Resource analysis plan
2) Need for updating and managing project work
Project status log must be utilized in order to update as well as manage the project
work effectively.
It is identified that they generally changes due to the progress within the project.
Manage project finalization
Activities Status
Handover Completed
Financial, legal and contractual
documentation
Completed
Report finalization Completed
Organization knowledge management Completed
Document Page
18
PROJECT MANAGEMENT

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
19
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Conforto, E.C., Salum, F., Amaral, D.C., da Silva, S.L. and de Almeida, L.F.M., 2014. Can
agile project management be adopted by industries other than software development?. Project
Management Journal, 45(3), pp.21-34.
Costantino, F., Di Gravio, G. and Nonino, F., 2015. Project selection in project portfolio
management: An artificial neural network model based on critical success
factors. International Journal of Project Management, 33(8), pp.1744-1754.
Fernandes, G., Ward, S. and Araújo, M., 2015. Improving and embedding project
management practice in organisations—A qualitative study. International Journal of Project
Management, 33(5), pp.1052-1067.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley &
Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
pp.291-298.
Ika, L.A., 2015. Opening the black box of project management: Does World Bank project
supervision influence project impact?. International Journal of Project Management, 33(5),
pp.1111-1123.
Document Page
20
PROJECT MANAGEMENT
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Marcelino-Sádaba, S., González-Jaen, L.F. and Pérez-Ezcurdia, A., 2015. Using project
management as a way to sustainability. From a comprehensive review to a framework
definition. Journal of cleaner production, 99, pp.1-16.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
1 out of 21