Development of Bespoke System for Project Estimating, Costing, and Budgeting System
Verified
Added on  2023/06/04
|13
|2341
|315
AI Summary
This project documentation outlines the development of a bespoke system for project estimating, costing, and budgeting. It includes a scope management plan, stakeholder register, WBS, Gantt chart, time phased budget, and procurement plan.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT DOCUMENTATION Project Documentation Development of Bespoke System for project estimating, costing, and budgeting system Name of the Student: Student ID: Name of the University:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT DOCUMENTATION Table of Contents 1. Scope Management Plan..............................................................................................................2 1.1 Project Overview including Owner, Sponsors, and Stakeholders.........................................2 1.2 Problem Statement.................................................................................................................2 1.3 Project Deliverables...............................................................................................................2 1.4 Milestones..............................................................................................................................3 1.5 Cost Estimates.......................................................................................................................4 1.6 Project Assumptions and Risks.............................................................................................4 1.7 Project Limitations.................................................................................................................5 1.8 Project Acceptance Criteria...................................................................................................5 1.9 WBS.......................................................................................................................................7 1.10 Network Diagram (showing critical path)...........................................................................7 1.11 Gantt Chart...........................................................................................................................8 1.12 Time Phased Budget............................................................................................................9 2. Stakeholder Register....................................................................................................................9
2PROJECT DOCUMENTATION 1. Scope Management Plan 1.1 Project Overview including Owner, Sponsors, and Stakeholders The project is developed for case study of Information System where a new information system (Bespoke system) would be developed using the programming language of C# that would be helpful for developing the effective implication management. The system would be developed considering the function of project cost estimating, budgeting, and schedule estimating. The completion of the system would result in developing the effective system for creation of the cost baseline, cash flow, earned value calculation, percentage complete proposal. The project owner is Jack Nicholson, proprietor of a consultancy firm that would require the system for his firm. The project sponsor is Diana Keith, CEO of State Bank and she would support the project with resources. The stakeholders of the project include the owner, sponsor, project manager, steering committee, and project team. 1.2 Problem Statement It is very crucial for calculating the project cost, budget, and schedule and with the growth of the project scale, the calculation have become very complex. Hence, the bespoke system would help the organization with creation of the cost baseline, cash flow, earned value calculation, percentage complete proposal. 1.3 Project Deliverables ThedeliverablesfortheprojectofDevelopmentofBespokeSystemforproject estimating, costing, and budgeting system include,
3PROJECT DOCUMENTATION a)Proper Documentation of the charter, plan, risk management, and final report b)Design of the Bespoke System and it simulation c)Program for the Bespoke System d)New Server merged with the existing server e)25 Client PCs configured with Windows 10, NIC card, and the system f)Proper Testing Results 1.4 Milestones The milestones for the project of Development of Bespoke System for project estimating, costing, and budgeting system are, WBSTask NameDurationStartFinish M1Kick off0 daysFri 10/12/18Fri 10/12/18 M2 Information Phase Completed 0 daysThu 10/11/18Thu 10/11/18 M3Design Approval0 daysTue 10/16/18Tue 10/16/18 M4System Developed0 daysMon 10/22/18Mon 10/22/18 M5PCs Configuration done0 daysMon 11/5/18Mon 11/5/18 M6Testing Results Documented0 daysTue 11/6/18Tue 11/6/18 M7Training Completed0 daysThu 11/1/18Thu 11/1/18 M8Project Closure0 daysThu 11/15/18Thu 11/15/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT DOCUMENTATION 1.5 Cost Estimates The cost estimates for the project of Development of Bespoke System for project estimating, costing, and budgeting system are, Project Budget Estimation Project Name: Development of Bespoke System for project estimating, costing, and budgeting system Resource NameTypeDuration/UnitsStandard RateTotal Cost Project ManagerHuman40$125.00$5,000.00 PlannerHuman40$40.00$1,600.00 Network EngineerHuman136$100.00$13,600.00 Data AdminHuman88$85.00$7,480.00 ProgrammerHuman152$110.00$16,720.00 DesignerHuman24$90.00$2,160.00 System EngineerHuman80$120.00$9,600.00 TesterHuman96$70.00$6,720.00 TrainerHuman80$50.00$4,000.00 Support teamHuman64$45.00$2,880.00 Server CostMaterial1$4,000.00$4,000.00 Design SoftwareMaterial1$1,000.00$1,000.00 Database StorageMaterial1$1,500.00$1,500.00 Programming SoftwareMaterial1$1,300.00$1,300.00 Windows 10Material10$100.00$1,000.00 NIC CardMaterial10$55.00$550.00 Testing toolsMaterial4$200.00$800.00 DocumentsMaterial3$30.00$90.00 Total Budget$80,000.00 1.6 Project Assumptions and Risks
5PROJECT DOCUMENTATION TheassumptionsfortheprojectofDevelopmentofBespokeSystemforproject estimating, costing, and budgeting system are, Project would be completed in the estimated time and budget Project Plan would be feasible for the organization Testing Results are positive and supportive Improvement Plan would be helpful for analysing the development factors The risks for the project of Development of Bespoke System for project estimating, costing, and budgeting system are, RiskLikelihood (L) Impact (I)Rating (L*I) Delay in Completion5210 Over budget339 Issues in Server Installation2510 Compiling Errors in Codes3515 Installation Issues248 1.7 Project Limitations The limitations for the project of Development of Bespoke System for project estimating, costing, and budgeting system are, Time Bounded by the duration of 34 days Cost Bounded by a budget of $80,000.00 Quality Bounded by the functions of automatic 1.8 Project Acceptance Criteria
6PROJECT DOCUMENTATION The acceptance criteria for the project of Development of Bespoke System for project estimating, costing, and budgeting system are, Project had been completed in the estimated time and budget Project Plan had been feasible for the organization Testing Results were positive and supportive for implementation
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT DOCUMENTATION 1.9 WBS Development of Bespoke System for project estimating, costing, and budgeting system Requirement Gathering Requirement Analysis Information Collection Project Planning Kick off Technical Specification Analysis of Server Requirements Data Analysis Purchasing of Server Selection of Programming Language Information Phase Completed Development Design UI designing Programming Structure development Database Designed Design Approval Function Programming the system Data import via XML Server Configuration Existing Network is connected to new server System Developed Client PC Set up 25 PCs configuration with Windows 10 NIC card is installed Software Installation PCs Configuration done Testing Network Testing System Function Testing Simulation of Server User Acceptance Testing Testing Results Documented Training Training Manuals Proper Training is given Training Evaluation Training Completed Closing Go Live Support Final Documentation Project Review Project Closure 1.10 Network Diagram (showing critical path) 234 7 8 9 10 11 14 15 16 17 19 20 2122 23 25 2627 28 30 31 32 33 34 36373839 41424344 5
8PROJECT DOCUMENTATION 1.11 Gantt Chart IDTask Mode WBSTask NameDuration 00Development of Bespoke System for project estimating, costing, and budgeting system 34 days 11Requirement Gathering10 days 21.1Requirement Analysis2 days 31.2Information Collection3 days 41.3Project Planning5 days 5M1Kick off0 days 62Technical Specification7 days 72.1Analysis of Server Requirements3 days 82.2Data Analysis4 days 92.3Purchasing of Server2 days 102.4Selection of Programming Language1 day 11M2Information Phase Completed0 days 123Development13 days 133.1Design9 days 143.1.1UI designing3 days 153.1.2Programming Structure development 3 days 163.1.3Database Designed3 days 17M3Design Approval0 days 183.2Function10 days 193.2.1Programming the system8 days 203.2.2Data import via XML4 days 213.2.3Server Configuration6 days 223.2.4Existing Network is connected to new server 3 days 23M4System Developed0 days 244Client PC Set up10 days 254.125 PCs configuration with Windows 1010 days 264.2NIC card is installed3 days 274.3Software Installation7 days 28M5PCs Configuration done0 days 295Testing14 days 305.1Network Testing3 days 315.2System Function Testing3 days 325.3Simulation of Server3 days 335.4User Acceptance Testing3 days 34M6Testing Results Documented0 days 356Training10 days 366.1Training Manuals2 days 376.2Proper Training is given7 days 386.3Training Evaluation1 day 39M7Training Completed0 days 407Closing8 days 417.1Go Live Support2 days 427.2Final Documentation4 days 437.3Project Review2 days 44M8Project Closure0 days Project Manager Project Manager,Documents[1] Planner 10/12 Network Engineer Data Admin Network Engineer,Server Cost[1] Programmer 10/11 Designer,Design Software[1] Programmer,Programming Software[1] Data Admin,Database Storage[1] 10/16 Programmer Data Admin Network Engineer Network Engineer 10/22 System Engineer,Windows 10[10] Network Engineer,NIC Card[10] Programmer 11/5 Tester,Testing tools[1] Tester,Testing tools[1] Tester,Testing tools[1] Tester,Testing tools[1] 11/6 Trainer,Documents[1] Trainer Trainer 11/1 Support team Support team,Documents[1] Support team 11/15 MWFSTTSMWFSTTSMWFSTTSMWFSTTSMWFST Sep 30, '18Oct 7, '18Oct 14, '18Oct 21, '18Oct 28, '18Nov 4, '18Nov 11, '18Nov 18, '18Nov 25, '18Dec 2, '18
9PROJECT DOCUMENTATION 1.12 Time Phased Budget September 30, 2018October 7, 2018October 14, 2018October 21, 2018October 28, 2018November 4, 2018November 11, 2018 $0.00 $5,000.00 $10,000.00 $15,000.00 $20,000.00 $25,000.00 $10,936.67 $21,493.33 $13,588.33$14,698.33 $13,180.00 $4,648.33 $1,455.00 1.13 Procurement Plan The procurement of the project would be done following the Fixed Cost Contract between the contractors (including sub contractors) and the project owner. The contractor would deliver the project requirements and implementing the effective development management. The information development would be effectively managed with the consideration and formation development. 1.14 Communication Plan The communication plan would be effectively managed for integrating the development of the information management and utilization development. The communication of the project plan would be developed for involving the management of the communication means and implying themanagementofthesuccessfulprojectplandevelopment.Theimplicationwouldbe developed for considering the development of communication operations.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT DOCUMENTATION 1.15 Budget Cost Estimates Resource NameTypeDuration/UnitsStandard RateTotal Cost Project ManagerHuman40$125.00$5,000.00 PlannerHuman40$40.00$1,600.00 Network EngineerHuman136$100.00$13,600.00 Data AdminHuman88$85.00$7,480.00 ProgrammerHuman152$110.00$16,720.00 DesignerHuman24$90.00$2,160.00 System EngineerHuman80$120.00$9,600.00 TesterHuman96$70.00$6,720.00 TrainerHuman80$50.00$4,000.00 Support teamHuman64$45.00$2,880.00 Server CostMaterial1$4,000.00$4,000.00 Design SoftwareMaterial1$1,000.00$1,000.00 Database StorageMaterial1$1,500.00$1,500.00 Programming SoftwareMaterial1$1,300.00$1,300.00 Windows 10Material10$100.00$1,000.00 NIC CardMaterial10$55.00$550.00 Testing toolsMaterial4$200.00$800.00 DocumentsMaterial3$30.00$90.00 1.16 S-Curve of Cost Estimates
11PROJECT DOCUMENTATION Project Manager Planner Network Engineer Data Admin Programmer Designer System Engineer Tester Trainer Support team Server Cost Design Software Database Storage Programming Software Windows 10 NIC Card Testing tools Documents $0.00 $10,000.00 $20,000.00 $30,000.00 $40,000.00 $50,000.00 $60,000.00 $70,000.00 $80,000.00 $90,000.00 Budget Estimates Cummulative Budget 1.17 Parametric/Bottom up The cost estimation has been done using parametric/bottom up estimation and it would help in ensuring that the cost estimates of the project procurement processes. The estimation of the
12PROJECT DOCUMENTATION bottom up estimation would be implied for easing the management of the processes. The resource analysis would be helpful for entailing the development of the improved budget resources and forming effective and influential development model. 2. Stakeholder Register The stakeholder register for the project of Development of Bespoke System for project estimating, costing, and budgeting system are, NamePositionRoleContact Informati on Requireme nts Expectati ons Influen ce Classificat ion Jack Nichols on CEOof Consulta ncy Firm Owner+41- XXXX- XXXX Bespoke System HighHighInternal Diana Keith CEOof State Bank Sponsor+41- XXXX- XXXX Revenue Generation HighHighExternal <<nam e of the student >> Manager ofthe Project Firm Project Manager +41- XXXX- XXXX Completion of project LowHighInternal Teddy Lewis Head Engineer Program mer +41- XXXX- XXXX Execution of the codes LowLowExternal Katie McQue en Quality Head Analyst+41- XXXX- XXXX Functions ofthe System HighLowExternal