Running head: PROJECT FINANCE AND PROCUREMENT PROJECT FINANCE AND PROCUREMENT Name of the Student Name of the University Authors Note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
2PROJECT FINANCE AND PROCUREMENT Table of Contents Introduction..........................................................................................................................3 Discussion............................................................................................................................3 Procurement and financial action....................................................................................3 Risk management plan.....................................................................................................6 Timeframe of the project.................................................................................................7 Conclusion.........................................................................................................................10 References..........................................................................................................................11
3PROJECT FINANCE AND PROCUREMENT Introduction Big Dig project officially known as central Artery/ tunnel project was considered to be a megaproject in Boston. It is considered to have pass through the heart of the city through 1.5 miles(Ahmadiet al.2017). The project is inclusive of construction of Ted Williams tunnel which is extended to heart of the city. After that there was a plan to establish railway connection between two train terminal of Boston(Hamid & Kehinde, 2017). The whole construction project was carried out in between the year of 1991 and 2006. In the end this project was concluded on 31stDecember when the partnership the project manager and Massachusetts temple ended. In the coming pages of the report financial and procurement in a Big Dig project has been discussed in details. Various kinds of issues with respect to Boston Big Dig project has been discussed in details. After that its impact of various issues on project has been discussed in the above pages of the report. Discussion Procurement and financial action WBSTask NameDurationCost 0Boston Big Dig Project5840 days$13,006,288,280.00 1Initiation phase166 days$126,200.00 1.1Development of business case35 days$26,600.00 1.2Undertaking easibility study40 days$28,800.00 1.3Establishing charter50 days$38,000.00 1.4Appointing project team41 days$32,800.00
4PROJECT FINANCE AND PROCUREMENT members 1.5 Milestone 1: Completion of initiation phase 0 days$0.00 2Planning phase434 days$333,680.00 2.1Creation of project plan50 days$38,000.00 2.2Creation of resource plan60 days$62,400.00 2.3Development of financial plan70 days$50,400.00 2.4Creation of quality plan56 days$40,320.00 2.5Development of risk plan76 days$54,720.00 2.6Creation of acceptance plan65 days$46,800.00 2.7 Development of communication plan 57 days$41,040.00 2.8 Milestone 2: Completion of planning phase 0 days$0.00 3Design phase1700 days$1,328,000.00 3.1Creation of rough sketch300 days$216,000.00 3.2Integrated design process450 days$270,000.00 3.3Architect drawing500 days$500,000.00 3.4 Arrangement of meetings for permit 450 days$342,000.00 3.5 Milestone 3: Completion of design process 0 days$0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
5PROJECT FINANCE AND PROCUREMENT 4Construction phase3400 days$13,004,432,000.00 4.1 Construction of Ted Williams tunnel 1200 days$6,001,152,000.00 4.2 Extending interstate 90 to Logan international Airport 1000 days$1,001,360,000.00 4.3 Rail connection between Boston two major train terminals 1200 days$6,001,920,000.00 5Closure phase140 days$68,400.00 5.1Post project review40 days$14,400.00 5.2Stakeholder sign off45 days$34,200.00 5.3Documentation55 days$19,800.00 5.4 Milestone 5: Completion of closure phase 0 days$0.00
6PROJECT FINANCE AND PROCUREMENT Risk management plan Risk eventImpactRisk LevelConsequence Shortage of laborHighHighDelay in completion of project. Unexpectedincrease incostofvarious materials highHighWill affect the overall budget of the project. Poorlywritten contracts highHighWillaffectthe stakeholdersduring legal activities. Unknownsite contracts lowLowWillcreatemess among the employees oftheorganization (Zhang, Minchin Jr & Agdas, 2017). Incompletedrawing andimproper drawing scope HighHighWillaffectallthe stakeholders who are associatedwiththe project. Propermanagement of change orders. HighlowChange in orders will resultindelayof submissionof project.
7PROJECT FINANCE AND PROCUREMENT Timeframe of the project WBSTask NameDurationStartFinishPredecessors 0Boston Big Dig project5840 days Mon 03- 12-91 Fri 20- 04-14 1Initiation phase166 days Mon 03- 12-91 Mon 21- 07-92 1.1 Development of business case 35 days Mon 03- 12-91 Fri 18- 01-92 1.2 Undertaking easibility study 40 days Mon 21- 01-92 Fri 14- 03-92 2 1.3Establishing charter50 days Mon 17- 03-92 Fri 23- 05-92 3 1.4 Appointing project team members 41 days Mon 26- 05-92 Mon 21- 07-92 4 1.5 Milestone 1: Completion of initiation phase 0 days Mon 21- 07-92 Mon 21- 07-92 5 2Planning phase434 days Tue 22- 07-92 Fri 19- 03-94 2.1Creation of project plan50 days Tue 22- 07-92 Mon 29- 09-92 6 2.2Creation of resource plan60 days Tue 30- 09-92 Mon 22- 12-92 8 2.3Development of financial70 daysTue 23-Mon 30-9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
8PROJECT FINANCE AND PROCUREMENT plan12-9203-93 2.4Creation of quality plan56 days Tue 31- 03-93 Tue 16- 06-93 10 2.5Development of risk plan76 days Wed 17- 06-93 Wed 30- 09-93 11 2.6Creation of acceptance plan65 days Thu 01- 10-93 Wed 30- 12-93 12 2.7 Development of communication plan 57 days Thu 31- 12-93 Fri 19- 03-94 13 2.8 Milestone 2: Completion of planning phase 0 days Fri 19- 03-94 Fri 19- 03-94 14 3Design phase1700 days Mon 22- 03-94 Fri 24- 09-00 3.1Creation of rough sketch300 days Mon 22- 03-94 Fri 13- 05-95 15 3.2Integrated design process450 days Mon 16- 05-95 Fri 01- 02-97 17 3.3Architect drawing500 days Mon 04- 02-97 Fri 02- 01-99 18 3.4 Arrangement of meetings for permit 450 days Mon 05- 01-99 Fri 24- 09-00 19 3.5Milestone 3: Completion of0 daysFri 24-Fri 24-20
9PROJECT FINANCE AND PROCUREMENT design process09-0009-00 4Construction phase3400 days Mon 27- 09-00 Fri 06- 10-13 4.1 Construction of Ted Williams tunnel 1200 days Mon 27- 09-00 Fri 01- 05-05 21 4.2 Extending interstate 90 to Logan international Airport 1000 days Mon 04- 05-05 Fri 01- 03-09 23 4.3 Rail connection between Boston two major train terminals 1200 days Mon 04- 03-09 Fri 06- 10-13 24 5Closure phase140 days Mon 09- 10-13 Fri 20- 04-14 5.1Post project review40 days Mon 09- 10-13 Fri 01- 12-13 25 5.2Stakeholder sign off45 days Mon 04- 12-13 Fri 02- 02-14 27 5.3Documentation55 days Mon 05- 02-14 Fri 20- 04-14 28 5.4 Milestone 5: Completion of closure phase 0 days Fri 20- 04-14 Fri 20- 04-14 29
10PROJECT FINANCE AND PROCUREMENT Conclusion From the above discussion it can be easily stated that this report is all about Big Dig project. A financial and procurement action plan has been prepared with respect to Big Dig project.Ariskmanagementplanhasbeenpreparedwithrespecttogivenproject.The development phase of the project is provided in details in above pages of the report. Big Dig is considered to be most expensive kind of highway project inunited states. But it was plagued by cost overruns, risk, charges, flaws in design, leaks. Some issues of substandard materials, criminal cases and issues of death were also encountered.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
11PROJECT FINANCE AND PROCUREMENT References Ahmadi,M.,Behzadian,K.,Ardeshir,A.,&Kapelan,Z.(2017).Comprehensiverisk managementusingfuzzyFMEAandMCDAtechniquesinhighwayconstruction projects.Journal of Civil Engineering and Management,23(2), 300-310. Elmhedwi, T. R., Elmabrouk, S. K., & Sherif, M. A. (2015, March). Practical risk management plan of Wi-Fi network deployment; case study. InIndustrial Engineering and Operations Management (IEOM), 2015 International Conference on(pp. 1-10). IEEE. Hamid, R. A., & Kehinde, F. J. (2017). CHOOSING AN APPROPRIATE CONTINGENCY SUM ESTIMATING METHODS FOR HIGHWAY CONSTRUCTION PROJECTS IN NIGERIA: A LITERATURE REVIEW.PLANNING MALAYSIA JOURNAL,15(1). Hubicki, M. (2014). Risk Management Plan. Monghasemi, S., Nikoo, M. R., Fasaee, M. A. K., & Adamowski, J. (2015). A novel multi criteria decision making model for optimizing time–cost–quality trade-off problems in construction projects.Expert systems with applications,42(6), 3089-3104. Tomita, T., Ono, Y., Nejihashi, K., Taogoshi, T., & Matsuo, H. (2016). Description of important potential risks of Japanese risk management plan on each package insert.Iyakuhin Johogaku,18(3), 214-217. Urban,M.E.(2016).EnhancedCapabilitiesforSubcriticalExperiments(ECSE)Risk Management Plan(No. LA-UR--16-22988). Los Alamos National Lab.(LANL), Los Alamos, NM (United States).
12PROJECT FINANCE AND PROCUREMENT Zhang, Y., Minchin Jr, R. E., & Agdas, D. (2017). Forecasting completed cost of highway constructionprojectsusingLASSOregularizedregression.Journalof Construction Engineering and Management,143(10), 04017071.