Running Head: BUSINESS AND MANAGEMENT TECHNIQUES
Business and Management Techniques
Name of the Student
Name of the University
Business and Management Techniques_1

1BUSINESS AND MANAGEMENT TECHNIQUES
Table of Contents
Task 1 – Project Cost.......................................................................................................................2
Task 2 – Resource Requirements....................................................................................................2
Task 3 – Project Plan.......................................................................................................................4
Project Scope...............................................................................................................................4
Work Breakdown Structure.........................................................................................................5
Project Duration...........................................................................................................................6
Quality Assurance and Standards................................................................................................8
Bibliography....................................................................................................................................9
Business and Management Techniques_2

2BUSINESS AND MANAGEMENT TECHNIQUES
Task 1 – Project Cost
The overall total project cost for the requirements in the project is shown in the following
table.
Requirement Projected Cost
Jaw Crusher £275,000
Training £17,500
Delivery £3,500
Installation (£600 per day * 6 days) £3,600
Engineering (£500 per day * 2 days) £1,000
Modification £28,500
Machining (£18.50 per hour * 35 hours) £647.50
Welding (£15 per hour * 20 hours) £300
TOTAL COST £330,047.50
Task 2 – Resource Requirements
The training and on sight work that are required to be performed for the project are
shown in the following table.
WBS Task Name Duration Start Finish Predecessors
Project for Tain Rock Plc 24.19 wks Wed Wed
Business and Management Techniques_3

3BUSINESS AND MANAGEMENT TECHNIQUES
5/8/19 10/23/19
A
Initial Design and Customer
Quotation
1.17 wks
Wed
5/8/19
Wed
5/15/19
B
Obtain Customer Approval and
Authorisation
1.17 wks
Wed
5/15/19
Thu
5/23/19
1
C Completion of Design 3 wks
Wed
5/15/19
Wed
6/5/19
1
D
Purchasing and Lead Time of Raw
Materials
5 wks
Thu
5/23/19
Thu
6/27/19
2
E Machining of Castings 1.17 wks
Thu
6/27/19
Fri 7/5/19 3,4
F
Mechanical Fabrication and
Assembly
6.17 wks Fri 7/5/19
Mon
8/19/19
5
G
Electrical and Electronics
Installation
2 wks
Mon
8/19/19
Mon
9/2/19
6
H Factory Testing of Machine 2 wks
Mon
9/2/19
Mon
9/16/19
7
I
Customer Operator Training In-
House
1.17 wks
Mon
9/2/19
Tue
9/10/19
7
Business and Management Techniques_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Development of a New Information Technology Centre – Stage 3
|9
|1217
|69

Project Management: Tasks, WBS, Activity Durations, Cost Report
|11
|1124
|463

Implementation of Information Technology - Project Charter and Budget
|7
|1491
|458

Project Crashing in Project Management
|7
|1752
|60

Information Technology Project Management
|11
|1965
|496

Construction Management
|10
|1682
|88