logo

Information Technology Project Management

   

Added on  2022-11-13

11 Pages1965 Words496 Views
Running Head: INFORMATION TECHNOLOGY PROJECT MANAGEMENT
Information Technology Project Management
Name of the Student
Name of the University

1INFORMATION TECHNOLOGY PROJECT MANAGEMENT
Part A Question 1
The fully developed schedule as per the given data is shown in the following table.
WBS Task Name Duration Start Finish Predecessors
0 Mo Mo Factory Outlet Project 130 days Tue 6/11/19 Wed 12/11/19
1 Fund Raising 3 wks Tue 6/11/19 Mon 7/1/19
2 Securing Retail Spaces 40 days Tue 7/2/19 Mon 8/26/19
2.1 Determine Locations 2 wks Tue 7/2/19 Mon 7/15/19 1
2.2 Negotiate Rental Contract 4 wks Tue 7/16/19 Mon 8/12/19 3
2.3 Review and Sign Contracts 2 wks Tue 8/13/19 Mon 8/26/19 4
3 Retail Spaces Fit Out 75 days Tue 8/27/19 Tue 12/10/19
3.1 Carpentry 60 days Tue 8/27/19 Tue 11/19/19
3.1.1 Sydney 30 days Tue 8/27/19 Tue 10/8/19 5
3.1.2 Melbourne 30 days Wed 10/9/19 Tue 11/19/19 8
3.1.3 Brisbane 30 days Wed 10/9/19 Tue 11/19/19 8
3.2 Electrics 40 days Wed 10/9/19 Tue 12/3/19
3.2.1 Sydney 10 days Wed 10/9/19 Tue 10/22/19 8
3.2.2 Melbourne 10 days Wed 11/20/19 Tue 12/3/19 9
3.2.3 Brisbane 10 days Wed 11/20/19 Tue 12/3/19 10
3.3 Plumbing 35 days Wed 10/23/19 Tue 12/10/19
3.3.1 Sydney 5 days Wed 10/23/19 Tue 10/29/19 12
3.3.2 Melbourne 5 days Wed 12/4/19 Tue 12/10/19 13
3.3.3 Brisbane 5 days Wed 12/4/19 Tue 12/10/19 14
4 Systems Development 55 days Tue 7/2/19 Mon 9/16/19
4.1 Manufacturing Resource Processing 22 days Tue 7/2/19 Wed 7/31/19
4.1.1 Inventory Control 2 wks Tue 7/2/19 Mon 7/15/19 1
4.1.2 Modelling Production Lines 2 wks Tue 7/16/19 Mon 7/29/19 21
4.1.3 Capacity Planning 1 wk Tue 7/16/19 Mon 7/22/19 21

2INFORMATION TECHNOLOGY PROJECT MANAGEMENT
4.1.4 Live Production Reporting 3 days Tue 7/23/19 Thu 7/25/19 21,23
4.1.5 Integrations 2 days Tue 7/30/19 Wed 7/31/19 22,24
4.2 Logistics 15 days Tue 7/16/19 Mon 8/5/19
4.2.1 Requirements Analysis / Codes
Identification 3 days Tue 7/16/19 Thu 7/18/19 1,21
4.2.2 Process Configuration 1 wk Fri 7/19/19 Thu 7/25/19 27
4.2.3 System Population 1 wk Fri 7/26/19 Thu 8/1/19 28
4.2.4 Test 2 days Fri 8/2/19 Mon 8/5/19 29
4.3 Human Resource Roisterinng 28 days Tue 7/2/19 Thu 8/8/19
4.3.1 Requirements Analysis / Codes
Identification 2 wks Tue 7/2/19 Mon 7/15/19 1
4.3.2 Process Configuration 4 days Tue 7/16/19 Fri 7/19/19 32
4.3.3 System Population 2 wks Mon 7/22/19 Fri 8/2/19 33
4.3.4 Test 4 days Mon 8/5/19 Thu 8/8/19 34
4.4 Point of Sales System 55 days Tue 7/2/19 Mon 9/16/19
4.4.1 Requirements Analysis / Codes
Identification 4 wks Tue 7/2/19 Mon 7/29/19 1
4.4.2 Process Configuration 3 wks Tue 7/30/19 Mon 8/19/19 37
4.4.3 System Population 2 wks Tue 8/20/19 Mon 9/2/19 38
4.4.4 Test 2 wks Tue 9/3/19 Mon 9/16/19 39
4.5 Purchase Order 45 days Tue 7/2/19 Mon 9/2/19
4.5.1 Requirements Analysis / Codes
Identification 2 wks Tue 7/2/19 Mon 7/15/19 1
4.5.2 Process Configuration 1 wk Tue 7/16/19 Mon 7/22/19 42
4.5.3 System Population 3 wks Tue 7/23/19 Mon 8/12/19 43
4.5.4 Test 3 wks Tue 8/13/19 Mon 9/2/19 44
4.6 General Ledger 14 days Tue 7/2/19 Fri 7/19/19
4.6.1 Requirements Analysis / Codes
Identification 4 days Tue 7/2/19 Fri 7/5/19 1
4.6.2 Process Configuration 1 wk Mon 7/8/19 Fri 7/12/19 47

3INFORMATION TECHNOLOGY PROJECT MANAGEMENT
4.6.3 System Population 3 days Mon 7/15/19 Wed 7/17/19 48
4.6.4 Test 2 days Thu 7/18/19 Fri 7/19/19 49
5 Hardware 80.5 days Tue 7/2/19 Wed 10/23/19
5.1 Hardware Order 18 days Tue 7/2/19 Thu 7/25/19
5.1.1 Develop Tender Document 6 days Tue 7/2/19 Tue 7/9/19 1
5.1.2 Open Tender 2 wks Wed 7/10/19 Tue 7/23/19 53
5.1.3 Award Tender 1 day Wed 7/24/19 Wed 7/24/19 54
5.1.4 Review and Sign Contract 1 day Thu 7/25/19 Thu 7/25/19 55
5.2 Hardware Acquisition 10 days Fri 7/26/19 Thu 8/8/19
5.2.1 Hardware Shipping 2 wks Fri 7/26/19 Thu 8/8/19 56
5.2.2 Hardware Received and Checked 0 days Thu 8/8/19 Thu 8/8/19 58
5.3 Food Court Outlet Configuration 52.5 days Fri 8/9/19 Wed 10/23/19
5.3.1 Warmer Cabinet Assembly 34 days Fri 8/9/19 Wed 9/25/19
5.3.1.1 Melbourne 2 wks Fri 8/9/19 Thu 8/22/19 58
5.3.1.2 Sydney 12 days Thu 8/22/19 Mon 9/9/19 62
5.3.1.3 Brisbane 12 days Mon 9/9/19 Wed 9/25/19 63
5.3.2 Servers / Network 17.5 days Tue 9/10/19 Thu 10/3/19
5.3.2.1 Melbourne 2.5 days Tue 9/10/19 Thu 9/12/19 67,62
5.3.2.2 Sydney 0.5 days Tue 9/10/19 Tue 9/10/19 63
5.3.2.3 Brisbane 5.5 days Thu 9/26/19 Thu 10/3/19 66,64
5.3.3 POS Assembly 24 days Tue 9/10/19 Tue 10/15/19
5.3.3.1 Melbourne 4 days Fri 9/13/19 Wed 9/18/19 71,58,66
5.3.3.2 Sydney 2 days Tue 9/10/19 Thu 9/12/19 58,67
5.3.3.3 Brisbane 7 days Thu 10/3/19 Tue 10/15/19 58,68,70
5.3.4 LED Screen Installation 6 days Tue 10/15/19 Wed 10/23/19
5.3.4.1 Melbourne 2 days Tue 10/15/19 Thu 10/17/19 65,69
5.3.4.2 Sydney 2 days Thu 10/17/19 Mon 10/21/19 65,69,74
5.3.4.3 Brisbane 2 days Mon 10/21/19 Wed 10/23/19 65,69,75

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
ICT Project Management
|20
|2439
|276

Project Management: Tasks, WBS, Activity Durations, Cost Report
|11
|1124
|463

Managing Operations and Projects
|3
|458
|68

Project Schedule and Cost Estimation
|17
|2907
|394

Development of a New Information Technology Centre – Stage 3
|9
|1217
|69

Network Diagram for Solar Power Project
|10
|955
|81