Running head: SYSTEM IMPLEMENTATION PROJECT PLAN System Implementation Project Plan Name of the Student: Student ID: Name of the University: Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1SYSTEM IMPLEMENTATION PROJECT PLAN Table of Contents Introduction......................................................................................................................................2 1. Title..............................................................................................................................................2 2. Scope overview............................................................................................................................2 3. Business case...............................................................................................................................2 4. Project Background.....................................................................................................................3 5. Milestone schedule with acceptance criteria...............................................................................3 6. Risks, assumptions and constraints..............................................................................................7 7. Stakeholder list............................................................................................................................8 Conclusion.......................................................................................................................................9 Bibliography..................................................................................................................................10
2SYSTEM IMPLEMENTATION PROJECT PLAN Introduction TheprojectcharteddocumenthasbeenmadefortheprojectofTOSIG'sCRM implementation for customer information system. The completion of all project activities would result in forming the achievement of the final deliverable for the project. The project has comprised ofanalysis and documentation phase completion, design phase completion, system development completion, deployment phase completed, test phase completed, and closure of project.The analysis of the risk factors had tended for forming the development of the effective mitigation strategies. 1. Title Project Title:‘TOSIG's CRM implementation for customer information system’ 2. Scope overview The development of the project documents, design deployment, system development, system deployment, and final test results are included in the scope of the TOSIG's CRM implementation for customer information system project. The project planning has included the use of the effective project management for the execution of project activities and attainment of final project deliverable. 3. Business case The organization of TOSIG requires the implementation of the effective CRM suysyem for the management of the information of the various customers. The TOSIG provides insurance to various customers for buildings, fencing, stock yards, storage silos and machinery, and even
3SYSTEM IMPLEMENTATION PROJECT PLAN crops. They had been following their simple information processing and the 150 agents would have to manage the information. However, it would require the use of CRM system for improving the management of information for the customers. 4. Project Background The project of TOSIG's CRM implementation for customer information system is developed for the aligning effective project activities. The completion of all these phases would result in forming the achievement of the final deliverable for the project. The completed project would be divided into 6 phases. The analysis and document phase would include the activities of requirement analysis, accumulation of resources, charter documentation, documents submission, signing of the documents, and analysis and documentation phase completion. The ui and system design would include the activities of platform selection, outline of ui and system is developed, development of UI design, development of system design, feasibility analysis, and design phase completion. The development of system would include the activities of database creation, development of UI, development of functions, development of programs, integration of the system, and system development completion. The deployment of system would include the activities of planning of the system development, implementing the system, integrating the system, training the staff, and deployment phase completed. The test of system would include the activities of alpha test, white box testing, simulation testing, UI operatibility testing, and test phase completed. The documentation for project would include the activities of final reports are made, submission of reports, signing of the documents, and closure of project. 5. Milestone schedule with acceptance criteria
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4SYSTEM IMPLEMENTATION PROJECT PLAN The project of TOSIG's CRM implementation for customer information system is developed for the aligning the six phases of Analysis and Document Phase, UI and system design, Development of System, Deployment of System, Test of System, and Documentation for project. The completion of all these phases would result in forming the achievement of the final deliverable for the project. The milestones of the project is shown in the following project schedule by highlighting it, WBSTask NameDurationStartFinish 0TOSIG's CRM implementation for customer information system 100 days Mon 7/16/18 Fri 11/30/18 1Analysis and Document Phase11 daysMon 7/16/18 Mon 7/30/18 1.1Requirement Analysis2 daysMon 7/16/18 Tue 7/17/18 1.2Accumulation of Resources4 daysWed 7/18/18 Mon 7/23/18 1.3Charter Documentation3 daysTue 7/24/18Thu 7/26/18 1.4Documents Submission1 dayFri 7/27/18Fri 7/27/18 1.5Signing of the documents1 dayMon 7/30/18 Mon 7/30/18 M1Analysis and Documentation Phase Completion0 daysMon 7/30/18 Mon 7/30/18 2UI and system design20 daysTue 7/31/18Mon 8/27/18 2.1Platform Selection2 daysTue 7/31/18Wed 8/1/18 2.2Outline of UI and system is developed4 daysThu 8/2/18Tue 8/7/18 2.3Development of UI design5 daysWed 8/8/18Tue 8/14/18 2.4Development of System design5 daysWedTue 8/21/18
5SYSTEM IMPLEMENTATION PROJECT PLAN 8/15/18 2.5Feasibility Analysis4 daysWed 8/22/18 Mon 8/27/18 M2Design Phase Completion0 daysMon 8/27/18 Mon 8/27/18 3Development of System35 daysTue 8/28/18Mon 10/15/18 3.1Database Creation5 daysTue 8/28/18Mon 9/3/18 3.2Development of UI8 daysTue 9/4/18Thu 9/13/18 3.3Development of functions6 daysFri 9/14/18Fri 9/21/18 3.4Development of Programs10 daysMon 9/24/18 Fri 10/5/18 3.5Integration of the system6 daysMon 10/8/18 Mon 10/15/18 M3System Development Completion0 daysMon 10/15/18 Mon 10/15/18 4Deployment of System16 daysTue 10/16/18 Tue 11/6/18 4.1Planning of the system development3 daysTue 10/16/18 Thu 10/18/18 4.2Implementing the system2 daysFri 10/19/18Mon 10/22/18 4.3Integrating the system4 daysTue 10/23/18 Fri 10/26/18 4.4Training the staff7 daysMon 10/29/18 Tue 11/6/18 M4Deployment Phase Completed0 daysTue 11/6/18Tue 11/6/18 5Test of System12 daysWed 11/7/18 Thu 11/22/18 5.1Alpha Test3 daysWed 11/7/18 Fri 11/9/18
6SYSTEM IMPLEMENTATION PROJECT PLAN 5.2White Box Testing3 daysMon 11/12/18 Wed 11/14/18 5.3Simulation Testing3 daysThu 11/15/18 Mon 11/19/18 5.4UI Operatibility Testing3 daysTue 11/20/18 Thu 11/22/18 M5Test Phase Completed0 daysThu 11/22/18 Thu 11/22/18 6Documentation for project6 daysFri 11/23/18Fri 11/30/18 6.1Final Reports are made4 daysFri 11/23/18Wed 11/28/18 6.2Submission of reports1 dayThu 11/29/18 Thu 11/29/18 6.3Signing of the documents1 dayFri 11/30/18Fri 11/30/18 M6Closure of Project0 daysFri 11/30/18Fri 11/30/18 Table 1: Project Milestones in Project Schedule The acceptance criteria for the completion of each of the milestones ofanalysis and documentation phase completion, design phase completion, system development completion, deployment phase completed, test phase completed, and closure of project. These milestones must meet some specific criteria for achievement of the final project deliverable. The acceptance criteria for the milestones are, Criteriaforanalysisanddocumentationphasecompletion:Theanalysisand documentation phase completion would be dependent on the project manager signing the documents and approving the initiation of the project. Criteriafordesignphasecompletion:Thedesignphasecompletionwouldbe dependent on the implication of the effective simulation of the design developed for the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7SYSTEM IMPLEMENTATION PROJECT PLAN Criteria forsystem development completion:The functionsof TOSIG must be compatible with the CRM system developed for the implication of the improved operation development. Criteria fordeployment phase completed:The implementation of the CRM system would be based on the effective integration of the activities favoring the organization’s activities. Criteria fortest phase completed:The test phase would be based on the implication of the activities forming the analysis of the quality and achievement of the expected test results. Criteria forclosure of project:The final reports would be deployed for the effective alignment of the operations and documentation process that can be utilized for future projects. 6. Risks, assumptions and constraints The project of TOSIG's CRM implementation for customer information system is an IT based project and the completion of the project would have to face several issues and problems. The analysis of the risk factors had tended for forming the development of the effective mitigation strategies. The following table would show the various risk factors for the project, Risk FactorRisk ClassificationRisk Mitigation Strategy Equipments FailureTechnicalReduce Shortage of the ResourcesFinancialAvoid Overtime of the activitiesOperationalAccept Design FlawsTechnicalTransfer Loss of dataAccidentalMitigate
8SYSTEM IMPLEMENTATION PROJECT PLAN The project of TOSIG's CRM implementation for customer information system would align with the use of the effective IT management principles and operations. The assumptions of the project are, a.Resources required for the completion of the project would be available and can be aligned with the implication of the effective alignment of the operations b.Project would be completed in the estimated time and resources accumulated in the project c.The team members would not face any quarrel or conflict among each other The estimated budget, calculated time, and the expected quality of the system operations are the constraints of the project of TOSIG's CRM implementation for customer information system. 7. Stakeholder list TypeStakeholdersRole GovernanceSponsor, Client, Steering Committee,Making decisions in the project ManagerialProject Manager and Contractor Management of the project activities Operational Complete project team, suppliers, and some external workers Carrying out all the activities of the project
9SYSTEM IMPLEMENTATION PROJECT PLAN Conclusion The project charted had been developed in the project and it had been helpful for conveying information to other stakeholders. The project of TOSIG's CRM implementation for customer information system was developed for the aligning the six phases of Analysis and Document Phase, UI and system design, Development of System, Deployment of System, Test of System, and Documentation for project. The completion of all these phases had resulted in forming the achievement of the final deliverable for the project. The charted had highlighted the acceptance criteria required for the completion of each of the milestones ofanalysis and documentation phase completion, design phase completion, system development completion, deployment phase completed, test phase completed, and closure of project.The analysis of the risk factors had tended for forming the development of the effective mitigation strategies.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10SYSTEM IMPLEMENTATION PROJECT PLAN Bibliography Boud, D., Cohen, R. and Sampson, J. eds., 2014.Peer learning in higher education: Learning from and with each other. Routledge. Chen, Y.S., Wu, C., Chu, H.H., Lin, C.K. and Chuang, H.M., 2018. Analysis of performance measures in cloud-based ubiquitous SaaS CRM project systems.The Journal of Supercomputing, 74(3), pp.1132-1156. Eichorn, F.L., 2018. Internal customer relationship management (IntCRM) a framework for achieving customer relationship management from the inside out.Management,2, p.1. Heagney, J., 2016.Fundamentals of project management. AMACOM Div American Mgmt Assn. Jaber, F. and Simkin, L., 2017. Unpicking antecedents of CRM adoption: a two-stage model. Journal of Strategic Marketing,25(5-6), pp.475-494. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kerzner, H., 2017.Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons. Laudon, K.C. and Laudon, J.P., 2016.Management information system. Pearson Education India. Orenga-Roglá, S. and Chalmeta, R., 2016. Social customer relationship management: taking advantage of Web 2.0 and Big Data technologies.SpringerPlus,5(1), p.1462.
11SYSTEM IMPLEMENTATION PROJECT PLAN Verzuh, E., 2015.The fast forward MBA in project management. John Wiley & Sons.