Running head: DESIGN THINKING IN MANAGEMENT Design Thinking in Management Name of Student- Name of University- Author’s Note-
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1DESIGN THINKING IN MANAGEMENT PR2: ProposalReport Project Name: Project proposal to implement a Mobile Application for AB Bbank in Australia Proposal Author Name and Student number: Campus and Tutor: 1. ProjectDescription 1.1 Opportunity/Problem The AB Bank of Australia wants to expand its business processes and wants to increase the activities that are associated with the bank. The bank needs to implement all the latest technologies that other banks are following in Australia so that they can give a tough competition in the banking sector in Australia. This project aims to implement a mobile application for the bank that will be useful for both the android users and iOS users. This project offers the bank to implement an application that helps organization to maintain its business processes. The key stakeholders associated with the project are the project manager who is of ager 37 and he needs to manage all the activities in the project. There are other stakeholders as well that specifies the bank, other business partners and the suppliers or the vendors. The age of the bank is two years. The opportunity or the target of the application that is being built is the citizens of Australia and the customers who are associated with the bank. The opportunity that is involved in this project is to have an application that improves the business opportunities of the organization.
2DESIGN THINKING IN MANAGEMENT 1.2 Proposed Project The project in this report is developing a mobile application for the AB Bank. The goal of this project is to evaluate the estimated schedule, the total time taken to complete the project, the scope that is included for designing the project, and lastly deploying the mobile application in the banking firm. The software that is to be implemented is to go through software development life cycle that includes phases like planning, analysis of the requirements, designing, developing, testing as well as implementing the application and the last phase is closing of the project. This proposed framework describes outline of the project. 1.3 Strategic Alignment Strategic DirectionProject alignment (a) TheCQUniversityStrategic Intent 2017-2027 This project satisfies the engagement and innovation that is intended in the CQUniversity. The project includes growth of the innovation and helps the project developer to have leadership quality. (b) Unit learning outcomesThis project is application for post graduate and the learning outcome of the project is able to develop a project that can lead to a successful completion of the project. 2. Alternative Alternative solution for enhancing the business process of the bank is implementing cloud computing concept in the bank to store their data securely in the cloud.
3DESIGN THINKING IN MANAGEMENT Stakeholders Stakeholder NameStakeholder Category Role in the stakeholder Project Impact to Stakeholder Project managerInternal StakeholderNeeds to manage the activitiesthatare involvedinthe project and fulfils the scope of the project andproject deliverablesare completed within the due date. Insuccessful completionofthe project manager will maintainits leadership qualityin completingthe projectsuccessfully. The project manager alsoschedulethe activitiesandnotes that all the work are donewiththetime frame. Banking FirmSponsorThisstakeholder providesthefund neededforthe project. The bank will be able toenhanceits business process after successful completionofthe
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4DESIGN THINKING IN MANAGEMENT project. GovernmentExternal StakeholderGovernmentmakes sure that the project areas are maintained andtheproject deliverables are done accordingtothe regulationofthe project. The government can get more number of customersforthe bank.The government increases the technology of the countryby implementingthe applicationinthe bank. Vendors and Suppliers SupplierThis stakeholderprovides theequipmentthat arerequiredfor completingthe project. Thevendorscan supplier will be paid for the materials they provideforthe projectafters successful completionofthe project. Project Approach
5DESIGN THINKING IN MANAGEMENT IDTask NameSchedule 1.1Project Initiation8 days 1.1.1Project Kick-Off Meeting1stweek 1.1.2Technical Feasibility Analysis1stweek 1.1.3Operational Feasibility Analysis1stweek 1.1.4Project proposal and approval2ndweek 1.2Requirements Analysis & Project Planning22 days 1.2.1Study of the Business Case2ndweek and 3rdweek 1.2.2Data Collection for Defining Requirements3rdand 4thweek 1.2.3User Requirements Specification5thweek 1.2.4Project Scope Definition & Management6thweek 1.2.5Project Estimations - Schedule, Costs6thweek and 7th week 1.2.6Risk Assessment & Management8thweek 1.2.7Milestone 1: Project Plan8thweek 1.3Project Design & Development74 days 1.3.1Procurement of tools and equipment9thweek and 10thweek 1.3.2Development of design diagrams10thweek and 11thweek 1.3.3System interfaces11th, 12th, 13thand 14thweek 1.3.4Source code development15thand 16thweek 1.3.5Unit testing of the code16thand 17thweek 1.3.6Review and analysis17thand 18thweek 1.3.7Release the build18thweek 1.3.8Milestone 2: Source code18thweek 1.4Application Testing120 days 1.4.1Testing Methodology & Approach19thweek 1.4.2Test scenarios and test case creation20thand 21stweek 1.4.3Test execution22ndweek 1.4.4Milestone 3: Defect Report22ndweek 1.5Project control & implementation7days 1.5.1Application reviews and inspections23rdweek 1.6Project Closure34 days 1.6.1Application deployment24th, 25thand 26thweek 1.6.2System Documentation6days 1.6.2.1User-manual27thweek 1.6.2.2Assistance documents27thand 28thweek 1.6.3Final Project Documentation10 days 1.6.3.1Project Closure Report29thweek 1.6.3.2Project Review Report30thweek 1.6.3.3Final Status Report31stweek 1.6.3.4Milestone 5: Project Closure Report31stweek
7DESIGN THINKING IN MANAGEMENT Network EngineerHuman Resource$65.00/hrBank Implementation Engineer Human Resource$60.00/hrBank Finance OfficerHuman Resource$80.00/hrBank Legal AdvisorHuman Resource$80.00/hrBank Ethics and Risk Management (3 marks) Risk CategoryConsiderations for this ProjectMitigation Fails in understanding the requirement related to the project All the requirements that are included in the project are to be considered and there should be clear understanding of all the projects that are included in the project. The project requirements are to be cleared by the project manager and all requirements are to be done. The requirement of the project should be made clear so that the team members of the project development team will be able to understand the requirement and scope of the project. Increasing the schedule of the project and the time schedule The time schedule of the project and the budget of the project is increased for the project. All activities included in the project should be divided in to small parts so that the time and the cost evaluation can be done from time to time.
8DESIGN THINKING IN MANAGEMENT Resource shortage The resource that are to be included in the project should be made available in successful completion of the project. There should be availability other vendors and suppliers for one fails. Changing design of the project The design of the application is not user friendly and the team members are not able to decode it. The design of the project should be done so that the team members are able to analyze the design of the application. Non research project I confirm that this project willNOT require the collection of data from humans for the purposes of research. YES
9DESIGN THINKING IN MANAGEMENT References Bourne, L. (2016).Stakeholder relationship management: a maturity model for organisational implementation. Routledge. Giannakis, M., & Papadopoulos, T. (2016). Supply chain sustainability: A risk management approach.International Journal of Production Economics,171, 455-470. Kolios, A., Read, G., & Ioannou, A. (2016). Application of multi-criteria decision-making to risk prioritisation in tidal energy developments.International Journal of Sustainable Energy,35(1), 59-74. Li, C. Z., Hong, J., Xue, F., Shen, G. Q., Xu, X., & Mok, M. K. (2016). Schedule risks in prefabrication housing production in Hong Kong: a social network analysis.Journal of Cleaner Production,134, 482-494. Loucks, D. P., & Van Beek, E. (2017).Water resource systems planning and management: An introduction to methods, models, and applications. Springer. Miles, S. (2017). Stakeholder theory classification: A theoretical and empirical evaluation of definitions.Journal of Business Ethics,142(3), 437-459. Souza, R. G., Rosenhead, J., Salhofer, S. P., Valle, R. A. B., & Lins, M. P. E. (2015). Definition of sustainability impact categories based on stakeholder perspectives.Journal of Cleaner Production,105, 41-51. Yang, R. J., Zou, P. X., & Wang, J. (2016). Modelling stakeholder-associated risk networks in green building projects.International journal of project management,34(1), 66-81.