Development of ERP System for Health Industry

   

Added on  2023-06-16

4 Pages1471 Words375 Views
Statement of Work Student Name:
Project Summary
Service Description
Deliverables
Deliverables Schedule:
Serial No. Project Deliverables Duration Start Finish
1 Initial Phase 12 days Wed 11/22/17 Thu 12/7/17
2 Planning Phase 6 days Fri 12/8/17 Fri 12/15/17
3 System Development 108 days Mon 12/18/17 Wed 5/16/18
4 Designing of the system 22 days Mon 12/18/17 Tue 1/16/18
5 Coding Phase 34 days Wed 1/17/18 Mon 3/5/18
6 Programming Phase 44 days Tue 3/6/18 Fri 5/4/18
7 System Integration 8 days Mon 5/7/18 Wed 5/16/18
8 Project Closure and 9 days Thu 5/17/18 Tue 5/29/18
The project is development of an ERP system for managing the information of the services, equipments, and
medicines in the health industry. The project would provide the development of the improvement of the
activities of the data and service delivery in the organization. The analysis of the project management
concepts would be implied for forming the development of the information system. The health organization
would require the use of advanced technology and process for the management of the huge amount of data
and information processing in the organization. The management of the operations would be eased due to the
implication of the effective and improved processing and development. The integrated data system would be
helpful in implying the effective data management for the health organization. The project would form the
integration of the operation and formation of the support and development for the health industries.
The scope of the project would involve the management of the large amount of data and information present
in the health industry on a single platform and the management of the effective and improved project
operations. The development of the project scope can be developed for the deployment of smart project
management concepts and principles for the development of the operations. The hardware requirements of
the project are the computer devices, network components, testing tools, storage database, equipments, and
basic infrastructure. The software requirements of the project are the network application, testing software,
programming platform, and operating system. The nature of work required for the project is IT based
software application development project and all activities are technology based. The waterfall methodology
would be followed for the completion of the project and development of the effective and improved
processes. The development of the project plan would include the following sub-components,
Project Planning
Project Resource Planning
Project Risk Management
System Designing
System Development
System Testing
Final Documentation

Documentation
Period of Performance:
The project is developed for completing the development of the ERP system for the health industry and it would
involve the following activities,
WBS Task Name Working hours Number of hours Start Finish
1 Initial Phase 8 hours 96 hours Wed 11/22/17 Thu 12/7/17
2 Planning Phase 8 hours 48 hours Fri 12/8/17 Fri 12/15/17
3 System
Development 3 hours 324 hours Mon 12/18/17 Wed 5/16/18
3.1 Designing of the
system 4 hours 88 hours Mon 12/18/17 Tue 1/16/18
3.2 Coding Phase 2 hours 68 hours Wed 1/17/18 Mon 3/5/18
3.3 Programming
Phase 2 hours 88 hours Tue 3/6/18 Fri 5/4/18
3.4 System
Integration 6 hours 48 hours Mon 5/7/18 Wed 5/16/18
4
Project Closure
and
Documentation
3 hours
27 hours
Thu 5/17/18 Tue 5/29/18
The project would carry on at the premise of the health industry and it would run from Wed 11/22/17 to Tue
5/29/18 (135 days).
Payment Schedule
The project is scheduled for the development of the effective and improved ERP system development and it is
based on fixed price term project contract. The software development projects require the cost payment at the
milestones.
The resources required for the project include project manager, developer, IT engineer, planner, budgeter,
analyst, database administrator, computer system, software, and hardware components. The overall cost of the
project comprises of the fixed cost of the materials and the salary given to the human resources of the project.
Sub-Contractors
The materials (computer system, network devices, and storage) and their delivery to the organization are being
outsourced to an external contractor.
Representatives
The project team representative includes,
Name Designation Signature
<<name of the student>> Project Manager <<name of the student>>
John Lewis IT engineer John Lewis
Andrew Evans Project Sponsor Andrew Evans
Katherine Beta Supplier (Contractor) Katherine Beta
SUB SECTIONS

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management: Work Breakdown Structure, Network Diagram, Gantt Chart, Budget, Risk, Communication, Status Report, Reflection
|32
|3729
|498

Implementing Cloud Computing for Increased Storage Space in Retail Store
|5
|1079
|181

System Analysis and Design
|12
|1152
|263

Project Management Assignment - Willowbrook School
|8
|1107
|109

Project Management Project Management 22 Project Management: Victoria Construction Pty Ltd
|24
|2591
|319

Implementation of Electronic Record Informatics - Desklib
|5
|951
|307