Running head: IMPLEMENTATION OF ELECTRONIC RECORD INFORMATICS
IMPLEMENTATION OF ELECTRONIC RECORD INFORMATICS
Name of the Student
Name of the University
Author Note
Implementation of Electronic Record Informatics - Desklib_1
1IMPLEMENTATION OF ELECTRONIC RECORD INFORMATICS
Task Name Duration Start Finish Predecessors Resource Names
Implementation of
Electronic Record
Informatics
261 days Mon 08-
10-18
Mon 07-
10-19
Development of the
System 10 days Mon 08-
10-18
Fri 19-
10-18
Plan Development 6 days Mon 08-
10-18
Mon 15-
10-18
Group
Leader,Information
Manager,Plan
Coordinator
Team Selection 4 days Tue 16-
10-18
Fri 19-10-
18 3
Group
Leader,Information
Manager,Plan
Coordinator
Team selected 0 days Fri 19-10-
18
Fri 19-10-
18 3,4
Requirement Collection 39 days Mon 08-
10-18
Thu 29-
11-18
Business Requirement 7 days Mon 22-
10-18
Tue 30-
10-18 4
Information
Manager,Plan
Coordinator
Functional Requirement 5 days Wed 31-
10-18
Tue 06-
11-18 7
Information
Manager,Plan
Coordinator
Non-Functional
Requirement 3 days Wed 31-
10-18
Fri 02-11-
18 7
Information
Manager,Plan
Coordinator
Summarising
Requirement 5 days Wed 07-
11-18
Tue 13-
11-18 7,8,9
Information
Manager,Plan
Coordinator
List of key Requirements 5 days Wed 14-
11-18
Tue 20-
11-18 10
Information
Manager,Plan
Coordinator
Strategy Development 7 days Wed 21-
11-18
Thu 29-
11-18 11
Group
Leader,Information
Manager,Plan
Coordinator
Requirement Collection
Completed 0 days Mon 08-
10-18
Mon 08-
10-18 10,11
Development Phase 10 days Wed 21-
11-18
Tue 04-
12-18
Programming 10 days Wed 21-
11-18
Tue 04-
12-18 11 Information
Manager
UI designing 6 days Wed 21-
11-18
Wed 28-
11-18 11 Information
Manager
System Development
Completed 0 days Tue 04-12-
18
Tue 04-12-
18 15,16
Testing 17 days Wed 05- Thu 27-
Implementation of Electronic Record Informatics - Desklib_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management for Boeing's Supersonic Commercial Planes
|5
|583
|392

Project Management: Time Inc.
|16
|2347
|145

Project-Risk Assessment and Project Schedule
|13
|1498
|69

Project Management Isn't Just For Project
|10
|1445
|19

Use of Blockchain in Healthcare: MedRec System
|12
|1304
|343

ICT Project Management
|20
|2439
|276