Fitness Center Construction Project

Verified

Added on  2023/04/03

|5
|623
|421
AI Summary
This document provides a project schedule for the construction of a fitness center, including tasks, durations, resources, and costs. It also includes a bibliography of project management resources.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: FITNESS CENTER CONSTRUCTION PROJECT
Fitness Center construction project
Name of the Student:
Name of the University:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1FITNESS CENTER CONSTRUCTION PROJECT
Project schedule : Fitness center construction
WB
S Task Name Duration Start Finish
Prede
cessor
s
Resource
Names Cost
%
Complet
e
0
Schedule for
construction of a
fitness center
142 days Mon
5/27/19
Tue
12/10/19
$27,776.0
0 85%
1 Project
initiation phase 31 days Mon
5/27/19
Mon
7/8/19 $5,912.00 100%
1.1
Project scope
statement
preparation
3 days Mon
5/27/19
Wed
5/29/19
project
manager $480.00 100%
1.2 Location
selection 5 days Thu
5/30/19
Wed
6/5/19 2 project
manager $800.00 100%
1.3
Design outline
of the fitness
center
6 days Thu
6/6/19
Thu
6/13/19 3 civil
engineer $1,152.00 100%
1.4 Developing
project team 4 days Thu
6/6/19
Tue
6/11/19 3 Resource
manager $576.00 100%
1.5 Bidding and
negotiation 5 days Fri
6/14/19
Thu
6/20/19 4,5
Contractor ,
sub
contractor
$1,080.00 100%
1.6
Signing
contract for the
fitness project
6 days Fri
6/21/19
Fri
6/28/19 6 project
manager $960.00 100%
1.7
Estimation of
time and budget
for the project
6 days Mon
7/1/19
Mon
7/8/19 7 Finance
manager $864.00 100%
2 Project
designing phase 102 days Tue
7/9/19
Wed
11/27/19
$18,600.0
0 88%
2.1
Developing
fitness center’s
blueprint
10 days Tue
7/9/19
Mon
7/22/19 8 architect $1,920.00 80%
Document Page
2FITNESS CENTER CONSTRUCTION PROJECT
2.2 Enclosing
single story 8 days Tue
7/23/19
Thu
8/1/19 10 Interior
design[1] $2,000.00 90%
2.3 Development
of one cardio area 9 days Fri
8/2/19
Wed
8/14/19 11 labours $1,440.00 90%
2.4 Construction
of a weights area 8 days Thu
8/15/19
Mon
8/26/19 12 labours $1,280.00 80%
2.5
Construction o
bathroom (make,
female and
disables access
bathroom)
9 days Tue
8/27/19 Fri 9/6/19 13 labours $1,440.00 90%
2.6
Construction
of a two separate
offices for the
personal trainer
5 days Mon
9/9/19
Fri
9/13/19 14 labours $800.00 95%
2.7 Design of one
locker room 8 days Mon
9/16/19
Wed
9/25/19 15 labours $1,280.00 85%
2.8 Construction
of a reception area 9 days Thu
9/26/19
Tue
10/8/19 16 labours $1,440.00 95%
2.9
Ceiling
construction for
(2.7M)
9 days Wed
10/9/19
Mon
10/21/19 17 labours $1,440.00 99%
2.10
Building
heights and
setbacks
9 days
Tue
10/22/1
9
Fri
11/1/19 18 labours $1,440.00 92%
2.11 Floor space
ration design 8 days Mon
11/4/19
Wed
11/13/19 19 Flooring [1] $2,200.00 90%
2.12
Design of open
space for local
environmental
plan
5 days
Thu
11/14/1
9
Wed
11/20/19 20 civil
engineer $960.00 80%
2.13
Floor area
designing (1240
Square Meter)
5 days
Thu
11/21/1
9
Wed
11/27/19 21 architect $960.00 70%
3 Project
execution phase
7 days Thu
11/28/1
Fri $2,944.00 0%
Document Page
3FITNESS CENTER CONSTRUCTION PROJECT
9 12/6/19
3.1 Electricity 2 days
Thu
11/28/1
9
Fri
11/29/19 22 electricity[1
] $600.00 0%
3.2 Plumbing 2 days Mon
12/2/19
Tue
12/3/19 24 plumbing[1] $200.00 0%
3.3
Fitness
instruments
installation
2 days Wed
12/4/19
Thu
12/5/19 25 Instrument
cost[1] $2,000.00 0%
3.4 Developing
trainers team 1 day Fri
12/6/19
Fri
12/6/19 26 Resource
manager $144.00 0%
4 Project closure
phase 2 days Mon
12/9/19
Tue
12/10/19 $320.00 0%
4.1 Stakeholder’s
signoff 1 day Mon
12/9/19
Mon
12/9/19 27 project
manager $160.00 0%
4.2
Opening of the
fitness center in
Australia
1 day
Tue
12/10/1
9
Tue
12/10/19 29 project
manager $160.00 0%
The work percentage completed till Wed 11/27/19 is 85%.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4FITNESS CENTER CONSTRUCTION PROJECT
Bibliography
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E.W. and Gray, C.F., 2017. Project management: The managerial process. McGraw-Hill
Education.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
1 out of 5
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]