Fitness Center Construction Project

Verified

Added on  2023/04/03

|5
|623
|421
AI Summary
This document provides a project schedule for the construction of a fitness center, including tasks, durations, resources, and costs. It also includes a bibliography of project management resources.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: FITNESS CENTER CONSTRUCTION PROJECT
Fitness Center construction project
Name of the Student:
Name of the University:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1FITNESS CENTER CONSTRUCTION PROJECT
Project schedule : Fitness center construction
WB
S Task Name Duration Start Finish
Prede
cessor
s
Resource
Names Cost
%
Complet
e
0
Schedule for
construction of a
fitness center
142 days Mon
5/27/19
Tue
12/10/19
$27,776.0
0 85%
1 Project
initiation phase 31 days Mon
5/27/19
Mon
7/8/19 $5,912.00 100%
1.1
Project scope
statement
preparation
3 days Mon
5/27/19
Wed
5/29/19
project
manager $480.00 100%
1.2 Location
selection 5 days Thu
5/30/19
Wed
6/5/19 2 project
manager $800.00 100%
1.3
Design outline
of the fitness
center
6 days Thu
6/6/19
Thu
6/13/19 3 civil
engineer $1,152.00 100%
1.4 Developing
project team 4 days Thu
6/6/19
Tue
6/11/19 3 Resource
manager $576.00 100%
1.5 Bidding and
negotiation 5 days Fri
6/14/19
Thu
6/20/19 4,5
Contractor ,
sub
contractor
$1,080.00 100%
1.6
Signing
contract for the
fitness project
6 days Fri
6/21/19
Fri
6/28/19 6 project
manager $960.00 100%
1.7
Estimation of
time and budget
for the project
6 days Mon
7/1/19
Mon
7/8/19 7 Finance
manager $864.00 100%
2 Project
designing phase 102 days Tue
7/9/19
Wed
11/27/19
$18,600.0
0 88%
2.1
Developing
fitness center’s
blueprint
10 days Tue
7/9/19
Mon
7/22/19 8 architect $1,920.00 80%
Document Page
2FITNESS CENTER CONSTRUCTION PROJECT
2.2 Enclosing
single story 8 days Tue
7/23/19
Thu
8/1/19 10 Interior
design[1] $2,000.00 90%
2.3 Development
of one cardio area 9 days Fri
8/2/19
Wed
8/14/19 11 labours $1,440.00 90%
2.4 Construction
of a weights area 8 days Thu
8/15/19
Mon
8/26/19 12 labours $1,280.00 80%
2.5
Construction o
bathroom (make,
female and
disables access
bathroom)
9 days Tue
8/27/19 Fri 9/6/19 13 labours $1,440.00 90%
2.6
Construction
of a two separate
offices for the
personal trainer
5 days Mon
9/9/19
Fri
9/13/19 14 labours $800.00 95%
2.7 Design of one
locker room 8 days Mon
9/16/19
Wed
9/25/19 15 labours $1,280.00 85%
2.8 Construction
of a reception area 9 days Thu
9/26/19
Tue
10/8/19 16 labours $1,440.00 95%
2.9
Ceiling
construction for
(2.7M)
9 days Wed
10/9/19
Mon
10/21/19 17 labours $1,440.00 99%
2.10
Building
heights and
setbacks
9 days
Tue
10/22/1
9
Fri
11/1/19 18 labours $1,440.00 92%
2.11 Floor space
ration design 8 days Mon
11/4/19
Wed
11/13/19 19 Flooring [1] $2,200.00 90%
2.12
Design of open
space for local
environmental
plan
5 days
Thu
11/14/1
9
Wed
11/20/19 20 civil
engineer $960.00 80%
2.13
Floor area
designing (1240
Square Meter)
5 days
Thu
11/21/1
9
Wed
11/27/19 21 architect $960.00 70%
3 Project
execution phase
7 days Thu
11/28/1
Fri $2,944.00 0%
Document Page
3FITNESS CENTER CONSTRUCTION PROJECT
9 12/6/19
3.1 Electricity 2 days
Thu
11/28/1
9
Fri
11/29/19 22 electricity[1
] $600.00 0%
3.2 Plumbing 2 days Mon
12/2/19
Tue
12/3/19 24 plumbing[1] $200.00 0%
3.3
Fitness
instruments
installation
2 days Wed
12/4/19
Thu
12/5/19 25 Instrument
cost[1] $2,000.00 0%
3.4 Developing
trainers team 1 day Fri
12/6/19
Fri
12/6/19 26 Resource
manager $144.00 0%
4 Project closure
phase 2 days Mon
12/9/19
Tue
12/10/19 $320.00 0%
4.1 Stakeholder’s
signoff 1 day Mon
12/9/19
Mon
12/9/19 27 project
manager $160.00 0%
4.2
Opening of the
fitness center in
Australia
1 day
Tue
12/10/1
9
Tue
12/10/19 29 project
manager $160.00 0%
The work percentage completed till Wed 11/27/19 is 85%.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4FITNESS CENTER CONSTRUCTION PROJECT
Bibliography
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E.W. and Gray, C.F., 2017. Project management: The managerial process. McGraw-Hill
Education.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons.