logo

Fitness Center Construction Project

   

Added on  2023-04-03

5 Pages623 Words421 Views
Running head: FITNESS CENTER CONSTRUCTION PROJECT
Fitness Center construction project
Name of the Student:
Name of the University:
Fitness Center Construction Project_1
1FITNESS CENTER CONSTRUCTION PROJECT
Project schedule : Fitness center construction
WB
S Task Name Duration Start Finish
Prede
cessor
s
Resource
Names Cost
%
Complet
e
0
Schedule for
construction of a
fitness center
142 days Mon
5/27/19
Tue
12/10/19
$27,776.0
0 85%
1 Project
initiation phase 31 days Mon
5/27/19
Mon
7/8/19 $5,912.00 100%
1.1
Project scope
statement
preparation
3 days Mon
5/27/19
Wed
5/29/19
project
manager $480.00 100%
1.2 Location
selection 5 days Thu
5/30/19
Wed
6/5/19 2 project
manager $800.00 100%
1.3
Design outline
of the fitness
center
6 days Thu
6/6/19
Thu
6/13/19 3 civil
engineer $1,152.00 100%
1.4 Developing
project team 4 days Thu
6/6/19
Tue
6/11/19 3 Resource
manager $576.00 100%
1.5 Bidding and
negotiation 5 days Fri
6/14/19
Thu
6/20/19 4,5
Contractor ,
sub
contractor
$1,080.00 100%
1.6
Signing
contract for the
fitness project
6 days Fri
6/21/19
Fri
6/28/19 6 project
manager $960.00 100%
1.7
Estimation of
time and budget
for the project
6 days Mon
7/1/19
Mon
7/8/19 7 Finance
manager $864.00 100%
2 Project
designing phase 102 days Tue
7/9/19
Wed
11/27/19
$18,600.0
0 88%
2.1
Developing
fitness center’s
blueprint
10 days Tue
7/9/19
Mon
7/22/19 8 architect $1,920.00 80%
Fitness Center Construction Project_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management
|10
|784
|60

Project Management for Moomba Festival Melbourne
|5
|625
|97

Development of a New Information Technology Centre – Stage 3
|9
|1217
|69

(Solved) Project Management Assignment
|5
|416
|48

Project Management And Analysis
|22
|3792
|32

Project Management: Tasks, WBS, Activity Durations, Cost Report
|11
|1124
|463