logo

ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

   

Added on  2022-10-01

2 Pages670 Words5 Views
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 Construction of ALLAM HOMES Pty Limited 26.25 days Mon 15/04/19 Tue 21/05/19
2 Preliminary Processes 10 days Mon 15/04/19 Fri 26/04/19
3 Paper work 10 days Mon 15/04/19 Fri 26/04/19
4 Preliminary Design 1 day Mon 15/04/19 Mon 15/04/19
5 Detailed design 2 days Tue 16/04/19 Wed 17/04/19 4
6 Preparation of Contract documents 3 days Thu 18/04/19 Mon 22/04/19 5
7 Signing of Contracts 4 days Tue 23/04/19 Fri 26/04/19 6
8 Approvals 2 days Tue 23/04/19 Wed 24/04/19
9 Meeting the local authority 1 day Tue 23/04/19 Tue 23/04/19 6
10 Approval of drawings 1 day Wed 24/04/19 Wed 24/04/19 9
11 Site Clearance 1 day Mon 29/04/19 Mon 29/04/19 10,7
12 Demolisions 1 day Thu 25/04/19 Thu 25/04/19 10
13 Ground works 12 days Mon 15/04/19 Tue 30/04/19
14 Marking layouts 12 days Mon 15/04/19 Tue 30/04/19
15 Excavation 1 day Mon 15/04/19 Mon 15/04/19
16 Foundation Works 2 days Tue 16/04/19 Wed 17/04/19 15
17 Compacting 3 days Thu 18/04/19 Mon 22/04/19 16
18 PCC 4 days Tue 23/04/19 Fri 26/04/19 17
19 Floor concrete pouring 2 days Mon 29/04/19 Tue 30/04/19 18
20 Superstructure Construction 20 days Mon 15/04/19 Fri 10/05/19
21 Wall construction 4 days Mon 15/04/19 Thu 18/04/19
22 Lintel 3 days Mon 15/04/19 Wed 17/04/19
23 Plastering 1 day Thu 18/04/19 Thu 18/04/19 22
24 Services fittings 1 day Mon 15/04/19 Mon 15/04/19
25 Electrical works 1 day Mon 15/04/19 Mon 15/04/19
26 Plumbing works 1 day Mon 15/04/19 Mon 15/04/19
27 Roofing expert 2 days Mon 15/04/19 Tue 16/04/19
28 Wood work for the roof 1 day Mon 15/04/19 Mon 15/04/19
29 Iron sheets fixing 1 day Tue 16/04/19 Tue 16/04/19 28
30 Painting 2 days Mon 15/04/19 Tue 16/04/19
31 First coat 1 day Mon 15/04/19 Mon 15/04/19
32 Second coat 1 day Tue 16/04/19 Tue 16/04/19 31
33 Finishing 1 day Wed 17/04/19 Wed 17/04/19 32
34 Windows 2 days Fri 19/04/19 Mon 22/04/19 23,29
35 Doors 2 days Mon 22/04/19 Tue 23/04/19 23FS+1 day
36 Hydraulics 3 days Tue 16/04/19 Thu 18/04/19 26
37 Floor screeding 2 days Wed 01/05/19 Thu 02/05/19 19
38 Miscallaneous 6 days Fri 03/05/19 Fri 10/05/19 37
39 Exterior element 4 days Fri 03/05/19 Wed 08/05/19
40 Landscaping 2 days Fri 03/05/19 Mon 06/05/19 37
41 Roadworks 2 days Tue 07/05/19 Wed 08/05/19 40
Architect
Architect
Architect,Client
Electricians,Plumber,Architect,QS,Client,Main contractor
Client,Local authority
Local authority
Main contractor
Main contractor
Main contractor
Main contractor
Architect,Main contractor
Main contractor
Main contractor
Electricians
Plumber
Roofing expert
Roofing expert
Main contractor,Painter
Painter
Painter
Main contractor
Main contractor
S T M F T S W S T M F T S W S T M F T
07 Apr '19 21 Apr '19 05 May '19 19 May '19 02 Jun '19 16 Jun '19
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1
Project: ALLAM HOMES Pty Lim
Date: Tue 08/10/19
ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23_1

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Plan : Doc
|3
|1027
|59

ICT Project Management
|20
|2439
|276

Project Management Techniques
|8
|2107
|64

Assignment on Design and Implementation
|15
|2862
|58

Project Management: Case Study of AT&T Project
|32
|4812
|87

Project Management Schedule and Cost Estimation for Construction Project
|10
|955
|170