Running Head: PROJECT MANAGEMENT
BN205: Project Management
Name of the Student
Name of the University
Assignment On Implementation Of Erp System For Jyotivic_1
1PROJECT MANAGEMENT
Executive Summary
JyotiVIC has been facing certain operational problems and hence, the management
was looking to implement a new ERP system that will solve the system issues and
problems. Accordingly, a project charter was provided earlier to the management.
The charter has been approved and in this document, a project plan has been
developed for the project. As per the estimations, the project will require around
164 working days and a budget of approximate $90,000.
Assignment On Implementation Of Erp System For Jyotivic_2
2PROJECT MANAGEMENT
Table of Contents
Introduction................................................................................................................ 3
Project Scheduling...................................................................................................... 3
Project Budgeting....................................................................................................... 7
Project Quality Planning............................................................................................. 9
Leading and Managing Project Team........................................................................10
Project Communications........................................................................................... 11
Bibliography............................................................................................................. 13
Assignment On Implementation Of Erp System For Jyotivic_3
3PROJECT MANAGEMENT
Introduction
This project involves implementation of ERP system for JyotiVIC in which, all
the various departments can be integrated within one common system that will not
only enhance the communication between the various departments but will also
provide the organisation to have more centralised control over all the departments.
In addition, it is expected that a lot of manual work can be replaced by automated
processes that require manual handling only. This paves the way for faster and
error free work output that is desired by the company.
In this report, a project plan has been developed for JyotiVIC regarding the
implementation of the ERP system within the existing operations.
Project Scheduling
As per the plan of the company, the entire project needs to be delivered and
the ERP system needs to be fully functional by 2020. Accordingly, the project
schedule has been developed as shown in the following table.
WBS Task Name Duration Start Finish
0 ERP System Implementation for JyotiVIC 164 days Mon 04-11-19 Thu 18-06-
20
1 Project Initiation Phase 18 days Mon 04-11-19 Wed 27-
11-19
1.1 Current Manual System Review and Develop
Requirements 2 days Mon 04-11-19 Tue 05-11-
19
1.2 Identify Issues to be Addressed by the System 4 days Wed 06-11-19 Mon 11-11-
19
1.3 Conduct Root Cause Analysis of the Identified
Issues 2 days Tue 12-11-19 Wed 13-11-
19
1.4 Suggest Possible Solutions for the Identified 2 days Thu 14-11-19 Fri 15-11-19
Assignment On Implementation Of Erp System For Jyotivic_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Development of CRM System for Medium Organization
|5
|596
|58

Project Management Isn't Just For Project
|10
|1445
|19

Software Engineering
|20
|1954
|359

Assignment (doc) on Project Business Management
|9
|1199
|13

System Analysis and Design for Desklib Online Library
|19
|2589
|334

Project Management: Risk Assessment, Cost Estimation, and Schedule
|17
|3177
|439