0Running head:INFORMATION SYSTEMS PROJECT MANAGEMENT Assignment 3: Information Systems Project Management Name of the student: Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1INFORMATION SYSTEMS PROJECT MANAGEMENT Project Plan 1. Project assumptions with necessary justification After analyzing the details project requirements and expected objectives it is assumed that, the project will be completed within 170 days with an estimated budget of $55,000.In order to fix the security the project manager and the project team members are responsible. The voice recognition technology should maintain accurate input speech approach so that it can avoid unwanted system access. The project plan should maintain a balance between the capital invested and the expected outcomes. 2. Summary for expanding ICT unit to incorporate voice recognition It is expected that, over next two to three decades the telecommunication industries are evolving drastically. The R&D team of the nominated tourist company is responsible to design and develop the system to attract the consumers all over. Different key technologies are currently becoming the commonplace which provides services and products to the willing consumers within the estimated budget and time. The automatic speech recognition technology gives the users more functionalities through which they can synthesis all necessary information. In current telephone network path the abilities of such systems are increasing rapidly. The operator services of such system and their application are also evolving day by day. However, the technical challengesassociatedtothisapplicationshouldexpandtheICTunitforsuccessfully incorporating voice recognition.
2INFORMATION SYSTEMS PROJECT MANAGEMENT 3. Initial estimated cost and resource structure with justification In order to reduce the work burden from the project team members based on project requirements this large project is segmented in small parts and depending on the skills and knowledge of the assigned resources for individual activities resources are allocated. It is their responsibility to accomplish assigned job roles within the estimated budget. The net budget and time estimated for this project are elaborated in the below section: Task NameResource NamesCost Information System Management project scheduling$51,798.00 Project initiation phase$14,064.00 Defining project scopeProject manager ,project sponsor$5,280.00 Identifying project objectivesProject manager$2,400.00 Incorporation of voice recognition technology to a tourist businesssystem designer$1,280.00 Risk management planbusiness analyst$1,824.00 Cost management planFinance manager$1,280.00 Setting project aim and other assumptionsProject manager$2,000.00 Milestone 1: Submission of initial project documentProject manager$0.00 Project planning$10,512.00 Procurement planningprocurement planner$1,200.00 Risk managementbusiness analyst$2,432.00 Contingency planprocurement planner$1,200.00 Communication management programHR manager$1,120.00 Stakeholders management planproject sponsor$2,880.00 Consideration of additional technologiesothers$1,680.00 Milestone 2: Submission of plan outline to the sponsorsProject manager$0.00 Project implementation phase$16,086.00 Identifying functional requirementsHardware requirements [1],software requirements [1]$130.00 Identifying non functionalHardware requirements$130.00
3INFORMATION SYSTEMS PROJECT MANAGEMENT requirements[1],software requirements [1] Hardware designHardware requirements [1]$60.00 Software designsoftware requirements [1]$70.00 Development of the prototypebusiness analyst$1,824.00 Identification of working operation practicesystem developer$1,536.00 Input of the speech signaling approach$12,336.00 Frame blockingsystem designer$1,280.00 Feature extractionsystem developer$2,304.00 Analysis of the spectrumProject manager$3,200.00 Decision treebusiness analyst$2,736.00 Implementation of necessary algorithmssystem designer$1,280.00 Result analysissystem developer$1,536.00 Milestone 3: System design outline submissionProject manager$0.00 Monitoring and control phase$5,360.00 Analysis of the security approaches$5,360.00 Simple matching of patternProject manager$2,000.00 Statistical analysisbusiness analyst$1,824.00 System testingsystem developer$1,536.00 Milestone 4: Submitting the testing result to the developersProject manager$0.00 Closure phase$5,776.00 Post maintenance planningProject manager$2,000.00 Stakeholders signoffHR manager$1,344.00 IS project management planbusiness analyst$2,432.00 Milestone 5: post maintenance programProject manager$0.00 4. Development of time sheet with the key project aspects The total time that will be taken for the completion of the project is 167 days. 5. Complete project plan WBSTask NameDurationStartFinishPredecessorsResource NamesCost
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7INFORMATION SYSTEMS PROJECT MANAGEMENT direction or the flow of the project though which the project will reach the final end point or the ultimate objectives. The interdependencies among the activities are defined with the help of te PERT chart. Figure 1: PERT chart for the ICT voice recognition technology (Source: created by author)
8INFORMATION SYSTEMS PROJECT MANAGEMENT 5.2 Gantt chart Figure 2: Gantt chart for the ICT voice recognition technology (Source: created by author)
9INFORMATION SYSTEMS PROJECT MANAGEMENT Written report 1. Complete cost benefit analysis Cost Benefit Analysis for incorporating voice recognition technologies cost estimated for hardware$6,000.00 cost estimated for Software$5,000.00 assigned resource cost$5,000.00 technical Training cost$10,000.00 Total Development Cost$26,000.00 post cost for Maintenance$5,000.00 Change management cost$10,000.00 labour cost$10,000.00 Total Operational Cost$25,000.00 salary savings (Approximate)$20,000.00 Reduced waste$20,000.00 Total Benefit$40,000.00 Discount Rate Used2.00% 2. Recommendations for the project Foravoidingapplication,operationalandfunctionalerrorstheperfectchange management practice must incorporate governmental policies, law, competitive conditions, economic structure and new technologies as well. Based on the complexity the project timeline, cost and other specifications are needed to be adopted and designed by the project manager before its final implementation. 3. Implementation plan for detailing cost, time and resources Based on the project objectives and goals in details it is determined that, the total cist needed for the successful implementation of the project is $55,000 and time is 170. It is possible
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10INFORMATION SYSTEMS PROJECT MANAGEMENT that a difference occurs between the planned cost-time and the actual cost and time. In order to avoid budget over allocation and over running time at the project initiation phase the details project plan should be prepared by the project manager. Again the project plan should be approved by the project sponsors to avoid further system failure and application errors as well. 4. Comprehensive post implementation plan In order to support the system until it ends this is mandatory for the project manager to design a post support and maintenance implementation program. Though, it is an ongoing activity that covers a wider activity variety including design errors, program removal, document update etc but for this specific project the maintenance program that should be considered include adaptive maintenance. This is nothing different from the change management program moreover it can be said that based on the organizational procedures, project goals, policy, security practices, system control and security requirements the post implementation plan should be evaluated. 5. Recommendations and conclusion From the overall discussion it can be concluded that, with the successful incorporation of voice recognition technology the tourist company will be able to serve secured services to their consumers. The project case for incorporating the voice recognition technologies is illustrated in this business plan. With their effective and efficient services the company is capable to attract around 200,000 families each year. Not only this but also, the different business information system are dated, coming with numbers of legacy systems and system efficiency as well while producing the processional project management reports. The business plan developed for this
11INFORMATION SYSTEMS PROJECT MANAGEMENT ICT project management practice is comprises of financial modeling aspects, human resource requirements, scheduling tasks, customer relationship system requirements etc. In addition to this, for this business many franchises are available. In order to operate both the local and remote potential consumers, how the voice recognition system is effective is also elaborated in this above business plan. However, for this specific voice recognition technology implementation project, there are some sections which needs further focus and the recommendations for this parts are elaborated in the below section. Highlevelbusinessstrategies:Thebusinessanalystassociatetotheprojectis responsible to develop high level business strategies so that it can give competition to the rest similar type of organization. It will give competitive advantages and structured commercial revenue to the owners. Encryption technology:Advance encryption technology will give security to the ICT system to make sure that, only the authorized users are allowed to access information from the server. The encryption should never be shared among the third parties to keep the system security. Training and development program: In order to keep the project team members familiar with the features of voice recognition technology the project managers are responsible to take necessary actions in terms of technical training and development program.
12INFORMATION SYSTEMS PROJECT MANAGEMENT References Albliwi, S., Antony, J., Abdul Halim Lim, S., and van der Wiele, T. 2014. Critical failure factors ofLeanSixSigma:asystematicliteraturereview.InternationalJournalofQualityand Reliability Management,31(9), 1012-1030. Bodily, R., Nyland, R., and Wiley, D. 2017. The RISE Framework: Using Learning Analytics to AutomaticallyIdentifyOpenEducationalResourcesforContinuousImprovement.The International Review of Research in Open and Distributed Learning,18(2). Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., and Wang, Q. 2015. Implementing educational innovations at scale: Transforming researchers into continuous improvement scientists.Educational Policy,29(1), 257-277. Conger, S. 2015. Six sigma and business process management. InHandbook on Business Process Management 1(pp. 127-146). Springer, Berlin, Heidelberg. First, M. B. 2016. Adopting a continuous improvement model for future DSM revisions.World Psychiatry,15(3), 223-224. Goetsch, D. L., andDavis, S. B. 2014.Quality management for organizational excellence. Upper Saddle River, NJ: pearson. Goldratt, E. M., and Cox, J. 2016.The goal: a process of ongoing improvement. Routledge. Hambach,J.,Tenberg,R.,andMetternich,J.2015.Guideline-basedvideoanalysisof competencies for a target-oriented continuous improvement process.Procedia CIRP,32, 25-30.