Name of University17Information Systems Project ManagementSocial CRM ProjectStudent’s Name

Social CRM ProjectTable of ContentAssumptions.............................................................................................................................................................21.Gantt chart........................................................................................................................................................22.Network Diagram..........................................................................................................................................33.SMART Milestones.........................................................................................................................................44.Resources Table.............................................................................................................................................55.Project Budget.................................................................................................................................................66.RACI Table........................................................................................................................................................97.Risk Register.................................................................................................................................................108.Probability/Impact Matrix......................................................................................................................12Reference.................................................................................................................................................................121

Social CRM ProjectAssumptionsNo holiday considered during the project lifecycleWeekends off daysDaily working hours = 8 hours / dayFrom 8:00 AM – 12:00 PM = 4 hours (Working Time)From 12:00 PM – 1:00 PM = 1 hour (Break/Lunch time)From 1:00 PM – 5:00 PM = 4 hours (Working Time)1.Gantt chart11 Agyei, Wallace. "Project Planning And Scheduling Using PERT And CPM Techniques With Linear Programming: Case Study2

Social CRM Project2.Network Diagram22 Usmani, Fahad. "Lead Time and Lag Time in Project Scheduling Network Diagram."3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Construction Management - Assignment
|8
|898
|22

Project Management Assignment 3: OSFMS
|20
|2287
|409

Project Management of Customer Relationship Program
|12
|1962
|32

Construction Project Plan with Microsoft Project Software | Desklib
|11
|1469
|276

Project Management Assignment 3: Unit Project Part B
|29
|4746
|459

Calculations and diagrams for project management
|7
|557
|84