This report discusses the concept of innovative digital workspace and its significance in the context of Marks & Spencer. It covers the stages of project life cycle, factors to consider in project management plan, range of research methods and their importance. The report also includes a project management plan with a work breakdown structure and Gantt chart. The research methods discussed include qualitative and quantitative methods, as well as primary and secondary research. A questionnaire is also included to gather data on the challenges faced by Marks & Spencer in implementing digital technologies and innovation at the workplace.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Unit 6 Managing a Successful Business Project

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
Topic: What does an innovative digital workspace look like.......................................................................3
Introduction.................................................................................................................................................3
Aim:........................................................................................................................................................3
Research Objectives:...............................................................................................................................3
Research Questions.................................................................................................................................3
TASK 1.......................................................................................................................................................5
Stages of project life cycle along with their significance in success of a project.....................................5
Factors to consider as the time of completion of project management plan.............................................6
Range of research methods and their importance to project management...............................................7
Questionnaire..............................................................................................................................................9
TASK 2.....................................................................................................................................................10
Produce a project management plan......................................................................................................10
Work break down structure and timeframe to complete the research....................................................12
Conduct a business project as stated within the PMP and communicate findings..................................14
Present data to draw valid and meaningful conclusion and recommendations from data analysis.........21
TASK 4.....................................................................................................................................................23
Reflect on the values of undertaking the business project to fulfill the pre-defined objectives..............23
Conclusion.................................................................................................................................................24
References.................................................................................................................................................25
Document Page
Topic: What does an innovative digital workspace look like
Introduction
Transformation refers to using new, advance and updated techniques at workplace. It is a
method to enhance the skills, abilities of employees so that they can easily cope up with constant
changes within the organization. In other words, workplace transformation is about rethinking of
flexible workplaces so that different kinds of works, technology and workers can be
accommodate significantly. Presently, transformation is highly important in order to ensure
future growth and success of a company (Meske, 2019). The present research work is based on
innovative and digital workplace. This will cover project planning including different stages &
factors of project life cycle. Further, different methods of research has also been covered in the
report. Along with this, it will include a complete PMP with WBS and Gantt chart. At end,
necessary recommendations will also drawn in order to undertake necessary improvements in the
overall project.
Aim: “To analyze what does an innovative digital workspace look like”. A study on Marks &
Spencer.
Research Objectives:
ď‚· To understand the concept of innovative and digital workplace.
ď‚· To analyze how an innovative digital workspace look like in context of Marks and
Spencer.
ď‚· To identify the significance of innovative and digital workplace to get better outcomes
within Marks and Spencer.
Research Questions
ď‚· What is the concept of innovative and digital workplace?
ď‚· How an innovative digital workspace look like in context of Marks and Spencer.
ď‚· What is the significance of innovative and digital workplace to get better outcomes
within Marks and Spencer?
Document Page
Literature Review
Concept of innovative and digital workplace
According to Hinings, Gegenhuber and Greenwood (2018), innovative digital workplace
is related with implementation of advance techniques at workplace so that the organization can
grow in future period of time. Transformation refers to using new, advance and updated
techniques at workplace. It is a method to enhance the skills, abilities of employees so that they
can easily cope up with constant changes within the organization. In other words, workplace
transformation is about rethinking of flexible workplaces so that different kinds of works,
technology and workers can be accommodate significantly.
How an innovative digital workspace look like in context of Marks and Spencer
According to Torous and Roberts, (2017), in case of innovative and digital workplace
latest and advance techniques are used. Here, the main aim of business entity is to make the
process simple by using technology. In context of Marks & Spencer, they provide appropriate
training to the employees so that they gain significant knowledge to work in an advance work
atmosphere. Further, they are also likely to support employees so that they can work in change
environment in significant manner.
Significance of innovative and digital workplace to get better outcomes within Marks and
Spencer
According to Trott, (2017), implementation of innovative digital techniques is crucial to
make the work simpler and easier for workforce. With the help of advance techniques, it is
possible for the employees to perform the assign work with greater efficiency. In context of
Marks and Spencer, implementing latest technology is helpful in fostering growth of the
company. Further, it also helps in enhancing the overall production so that the entity can earn
significant amount of profit in future period of time. Additionally, the company can maintain
competitive brand image by implementing innovation and digital techniques at workplace

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
TASK 1
Stages of project life cycle along with their significance in success of a project.
Project management life cycle shows higher level processes in order to deliver a project
successfully. Through effective project management, it is possible to make significant use of the
available resources. Further, it also helps in minimizing the wastage out of the project. To
complete a project successfully, it is imperative to follow the project life cycle in significant
manner. This cycle includes four major steps such as initiation, planning, execution and closure.
The project life cycle is related with inclusion of these four steps from starting of project to
closure (Galli, 2018). These all steps are interrelated with each-other and need to complete
appropriately to complete the project work successfully. In present context, different steps of
PLC are mentioned as under:
Initiation Phase: It is the first step of PLC where it is important to identify the need of
business, problem and opportunities. For this purpose, one can do brainstorming and accept the
ideas of team members to resolve the issue or get the opportunity. Here, an objective is found out
and further the feasibility of such objective is evaluated significantly. In addition, the major
deliverables of the project have also been identified during this phase (Azhar, Khan and Zafar,
2019). In context of current situation, the project managers is going to undertake a project based
on workplace transformation. This project will be carried out to facilitate transformation at
workplace so that the business entity can grow & succeed in future period of time. The
respective project will help in enhancing the overall skills and capabilities of workforce in
significant manner.
Planning Phase: This is the second step of PLC where the larger project is break down
into smaller components. Here, team is build and scheduled is prepared for the completion of
project work in timely manner. By creating small goals, it is possible to complete the entire
project successfully in future period of time. Here, smaller goals are likely to motivate the
project manager and team members to put efforts for the success of entire project (Vuorinen and
Martinsuo, 2018). In context of the existing project, there is requirement to undertake planning
by breaking down the entire project into smaller components. Through planning, the project
manager will be able to assign different duties to different people for proceeding with the project
further.
Document Page
Execution Phase: After receiving approval or develop a plan, the next step is to get the
actual work done. Here, plans are turned into actions. Project manager play an important role
here by assessing the success of project, keeping the work on track, organizing team members,
managing timelines etc. This is one of the significant steps of project planning as it helps in
effective execution of project (Nguyen and Garvin, 2019). In this context, the project manager of
current project needs to create the tasks and organize workflows. Further, they need to brief the
team members appropriately. Further, they need to maintain regular communication with the
team members for future success of project work.
Closure: When the team has been completed work on a particular project, the next step is
closing of the project. Here, the final deliverables are provided by the project manager in terms
of releasing the project resource significantly. This is the most important stage in terms of
evaluating the success and failure of the overall project (Ermakova, Kaloshina and Dianova,
2019). In current context, the project manager is required to analyze the overall project
performance in terms of meeting the project goals. Further, they need to assess the performance
of team for making further improvements. In next step, the documents need to put on closure to
ensure that all the aspects of project has been completed successfully without any loop. Here,
post-implementation reviews are also covered to learn from the project and implement those
lessons in future projects in an appropriate manner.
Factors to consider as the time of completion of project management plan
While structuring a project management plan, there is requirement to consider ample of
factors so that the entire project can be completed successfully. In present context, the important
factors need to be considered during project planning are mentioned below:
Experienced project managers and professional project team leaders: Experience is
highly important in order to complete a complex project successfully. No matter how many
resources have been acquired but experience is the most significant factor to contribute in the
success of project management plan (Cicmil and et. al., 2017). The current project is based on
transformation at workplace. Here, the experience project managers and individuals will be able
to contribute towards the success of project significantly.
Document Page
Proper planning: There is no need to hurry at any stage of project management plan. To
ensure success of project, there is requirement to put sufficient time in planning through
scheduling. Planning is highly important in order to complete a project successfully.
Additionally, planning also makes the project manager enable to make most of the opportunities
and deal with future problems significantly.
Monitoring and control: This is also a crucial element to check the results efficiently.
To understand if the project is on track, there is requirement to measure the performance
regularly. For this purpose, there is requirement to use KPIs and other such reports (Bjorvatn and
Wald, 2018). With the help of these reports, it is possible to measure the performance constantly
so that further improvements can be done in an efficient manner.
Effective communication: Communication is the key of business success. It helps in
terms of maintaining regular flow of information within the organization. By maintaining proper
communication, it is possible to avoid the conflicts in an efficient manner (Dinnik, Grigoryeva
and Galoyan, 2019). In context of the project management plan, project manager and team
members are required to maintain proper flow of information so that appropriate decisions can be
taken.
Range of research methods and their importance to project management
Research is an important part of the overall project as it helps in collection and analysis
of data. During research, several methods are adopted so that adequate amount of data can be
collected for future success of project. Every method has its own importance in terms of
gathering and analyzing the data efficiently. In context of present project, different research
methods are given below:
Qualitative method: In research, qualitative method plays a crucial role in collection of
detailed and in-depth information. By using the respective method, it is possible for the
researcher to collect detailed information from respondents. Basically, this is a useful method to
deal with non-numeric information (Bigorra Puente, 2017). The major sources of collecting
qualitative information are focus groups, interviews, group discussion and more.
Justification: By adopting qualitative method, the investigator can easily collect in-depth
information on a particular topic. This method is useful in terms of gathering detailed

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
information from respondents to complete the research project in successful manner. Further, it
helps in developing effective knowledge based on a particular research topic.
Quantitative method: In research project, quantitative method is used to collect and
analyze numerical information. In this, mathematical, statistical and other such techniques are
used so that the data can be evaluated in numerical form. Due to use of statistical tools and
techniques, this method is appropriate to get valid results.
Justification: The main rational of using qualitative method is to analyze the data using
numerical tools. This method is considered suitable for collection and analysis of numerical
information so that authentic results can be gathered.
Secondary research method: To collect vast amount of information, this method is
often adopted by researcher. In this, already available information is used by the researcher
rather collecting the new data (Clevenger, 2018). However, it helps in collecting vast
information but it is less reliable and authentic. Previous used data is collected in secondary
research methods to develop understanding regarding a specific topic.
Justification: The main rational to use secondary research method is to collect huge
amount of information within limited period of time. It helps in collection of vast amount of
information using different sources like websites, journals, publications and more. It minimizes
the efforts of researchers as they can utilize the already available data for completion of research
project.
Primary research method: Here, the data is gathered by investigator by own efforts so
that appropriate information can be gathered. This is an important way to collect first handed and
raw information so that the project can be completed with authenticity (Lientz, 2017). Further,
primary research is time taking as the data is gathered by the researcher either by personal
interaction with respondents or telephonic conversation with them.
Justification: This is a crucial method of data collection as it helps in completing the
research project with authenticity. It helps in collecting raw information based on the response of
participants. By adopting primary method, it is possible to complete the project work with
authenticity & reliability for future betterment.
Document Page
Questionnaire
Questions Frequency
Q1.) Do you have basic knowledge regarding the concept of
transformation at workplace?
a) Yes 24
b) No 6
Q2.) In your opinion, what is the significance of innovation and digital
technology within Marks & Spencer?
a) Fosters growth 18
b) Provide competitive advantage 7
c) Helps in resolving the issues 5
Q3.) As per your consideration, what are the challenges faced by Marks
& Spencer while implementing digital technologies and innovation at
work place
a) Resistance of workforce 16
b) Lack of knowledge of employees 7
c) c) Lack of funds 7
Q4.) In your opinion, does digital technology and innovation helps in
enhancing the brand reputation of company?
a) Yes 28
b) No 2
Q5.) According to you, does implementing workplace transformation
generate competitive advantage for the company
a) Yes 26
b) No 4
Document Page
Q6.) As per your consideration, how Marks & Spencer can implement
digital technologies and innovation at workplace significantly
a) Training & development 16
b) Motivation 6
c) By maintaining proper communication 8
Q7) Does, digital technology and innovation techniques helps in
ensuring long-term growth & success of the brand?
d) Yes 25
e) No 5
TASK 2
Produce a project management plan
Project management plan is a crucial part of the overall project. It includes various
elements such as resources, risks, communication, scope and more. While preparing a project
management plan, it is important to consider various aspects so that the project management plan
can be completed in an appropriate way (Silvius and et. al., 2017). In this context, different
elements of project management plan are given below:
Scope: The scope of the respective project is wide based on analyzing the role of
transformation in business success. This will help to analyze how the companies can implement
transformation within business organization. Along with this, the project will also include
significance of transformation activities for the company.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Cost: While undertaking a project, it is imperative to consider the overall cost in
significant manner. It is one of the major crucial aspects of project work. By pre-defining the
cost, it is possible to complete the project within the set budget to get adequate amount of profit
in future period of time (Kerzner, 2017). This helps investigator to conduct research activities in
systematic manner.
Time: This is also an important component of the overall research study. While starting a
project, it is important to determine the time. Here, a proper schedule needs to prepare so that the
project work can be completed in significant manner (Dinnik, Grigoryeva and Galoyan, 2019).
For this purpose, the researcher needs to set time for each and every activity so that the laid aims
& objectives can be attained. In context of the present project, there will be requirement of 20
weeks to complete the project work.
Quality: Quality demonstrates the importance of conducting different activities
efficiently so that a quality study can be conducted in significant manner (Andres Imaz, 2020). In
this context, the data will be gathered from various authentic sources in order to drive high
quality in the project.
Communication: Communication is an important component of project work. It is a
process of exchanging the information between individuals. It helps in making people understand
regarding the aims & objectives of the project (Bjorvatn and Wald, 2018). In context of the
present project, different forms of non-verbal communication have been considered to maintain
appropriate communication with the stakeholders.
Risk: In project completion, risk also incurs. Here, different forms of risks are
considered. In present context, the project includes risk in terms of lack of participants, lack of
communication, lack resources and more.
Resources: To complete the project work, there is requirement of ample of resources like
technology, manpower, capital and more. Here, resources play an imperative role in completion
of project work in successful manner (Bigorra Puente, 2017). With the help of adequate amount
of resources, it is possible to complete the project work in timely manner. In case of current
project, the major resources used are stationery, internet, access of books suitable articles,
journals and more.
Document Page
Deliverables: The current project will include various deliverables regarding the impact
of technological advancements within company. Further, this will also help to know the
challenges face by the company while implementing advance technologies at workplace.
Work break down structure and timeframe to complete the research
Work Break down structure:
It is an important element of project management wherein all project related activities are
divided into small components. Main aim of Work break down structure is to make the project
simple so that each and every individual can contribute towards completion of project work.
Further, WBS is helpful in minimizing the complexities of research project. Further, it also helps
in defining roles and responsibilities of each individual in order to complete the project work
successfully. The main objective of WBS is to make a large project simple and manageable. By
using WBS, large projects can easily completed in multiple steps significantly. Basically, it is a
way to minimize the complexities and to get the things done promptly. Here, breaking down into
small components means that work will be completed regularly by different team members by
making the project easier for project manager. To create WBS, it is important to ensure that all
critical inputs and deliverables are gathered and prioritize in significant manner(Maraie, 2020).
After outlining the tasks, next step is to assign each tasks to different team members. In this, it is
important to ensure that the project work is divided among all the team members in equal
manner. Also, the competencies of individual member also need to consider while assigning
them duties. In context of current project work, WBS is given below:
Document Page
Gantt Chart:
Gantt chart is commonly used tool in project management. It is considered one of the
popular and useful ways of showing different activities against time. Here, the left chart includes
list of activities with suitable time scale at the top. Here, each activity is generally represented by
a bar. In this length as well as position of the bar demonstrates start date, duration and end date
of the activity. In the present time, Gantt chart is considered as one of the most important tool for
tracking the schedule of project. Through Gantt chart, it is easy to depict additional information
regarding various tasks of project. In other words, this is an effective tool of project management
which shows a project plan. In this, the activities are represented in graphical manner. Therefore,
it is easy to understand the tasks, activities and deadlines appropriately. Along with this, Gantt
chart also covers milestones, tasks, deliverables, start date and end date of tasks and more.
Preparing Gantt chart is suitable to deal with complex projects. It helps in minimizing the
complexities of large projects so that all the activities can be complete within pre-defined
schedule. By preparing gantt chart, the progress of project can be monitored in an efficient
manner. Additionally, it helps in calssfying the entire project into small activities (Alam, 2019).
Further, the tasks are assigned to team members as per their competencies. With this, it is easy to
complete the entire project within set deadlines by taking help of efficient individuals. In present
context, gantt chart for completion of current project is given below:

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Conduct a business project as stated within the PMP and communicate findings
Q1.) Do you have basic knowledge regarding the concept of
transformation at workplace?
Frequency
a) Employee training and development 24
b) Application of motivation techniques 6
Document Page
80%
20%
Chart Title
a) Employee training and development b) Application of motivation techniques
Interpretation: From the above diagram, it is analyzed that 24 out of 30 respondents are well
familiar with the concept of transformation at workplace whereas 6 respondents do not have
knowledge regarding the respective concept. Therefore, majority of participants have knowledge
regarding the concept of transformation at workplace.
Q2.) In your opinion, what is the significance of innovation and digital
technology within Marks & Spencer?
Frequency
a) Fosters growth 18
b) Provide competitive advantage 7
c) Helps in resolving the issues 5
Document Page
60%
23%
17%
Chart Title
a) Fosters growth b) Provide competitive advantage
c) Helps in resolving the issues
Interpretation: The above chart shows significant of implementing innovation and digital
technologies at workplace. It is monitored that as per 18 respondents fostering the growth is the
major significance of innovation and digital technologies at workplace whereas 7 participants
consider providing competitive advantage is the most effective significance of digital
technologies and innovation within organization. Rest 5 respondents consider helping in
resolving issues as the major significance of implementing innovation and digital technology at
workplace. It is found that the majority of the respondents are in favor of fostering growth as the
major significance of innovation and digital technology.
Q3.) As per your consideration, what are the challenges faced by Marks
& Spencer while implementing digital technologies and innovation at
work place
Frequency
a) Resistance of workforce 16
b) Lack of knowledge of employees 7
c) c) Lack of funds 7

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
53%
23%
23%
Chart Title
a) Resistance of workforce b) Lack of knowledge of employees
c) c) Lack of funds
Interpretation: It is monitored that the company has to face several challenges while
implementing innovation and digital technologies at workplace. Through the above pie-chart, it
is analyzed that Marks and Spencer face challenges as resistance of employees as per 16
respondents whereas 7 participants consider that lack of knowledge of employees is one of the
major challenge face by Marks & Spencer. Rest 7 participants consider that lack of funds is the
major issues that is being face by the respective company. According to the majority of
respondents resistance of workforce is the most significant challenge face by the company during
implementation of innovation and digital technologies at workplace.
Q4.) In your opinion, does digital technology and innovation helps in
enhancing the brand reputation of company?
Frequency
c) Yes 28
d) No 2
Document Page
93%
7%
Chart Title
a) Yes b) No
Interpretation: From the above pie-chart, it is found that 28 respondents are in favor of the fact
that implementing innovation and digital technologies help in enhancing the brand reputation of
the company. Rest, 2 respondents have not shown consent with the same fact.
Document Page
Q5.) According to you, does implementing workplace transformation
generate competitive advantage for the company
Frequency
a) Yes 26
b) No 4
87%
13%
Chart Title
a) Yes b) No
Interpretation: After interviewing 30 respondents, it is found that 26 respondents consider that
implementing innovative and digital technologies will contribute in generating competitive
advantage on other side 4 respondents consider that digital techniques and innovation does not
play significant role in terms of generating competitive advantage for business organization.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Q6.) As per your consideration, how Marks & Spencer can implement
digital technologies and innovation at workplace significantly
Frequency
a) Training & development 16
b) Motivation 6
c) By maintaining proper communication 8
53%
20%
27%
Chart Title
a) Training & development b) Motivation
c) By maintaining proper communication
Interpretation: After analyzing the above pie-chart, it is analyzed that 16 participants consider
that training & development is an important way to implement transformation at workplace. As
per 6 participants, the company needs to motivate the workforce in order to implement
innovation & digital technologies at workplace. Rest 8 participants consider that the company
cam maintain implement workplace transformation by maintaining proper communication within
the organization in significant manner.
Document Page
Q7.) Does, digital technology and innovation techniques helps in
ensuring long-term growth & success of the brand?
Frequency
a) Yes 25
b) No 5
83%
17%
Chart Title
a) Yes b) No
Interpretation: Through the above pie-chart, it is analyzed that as per 25 respondents digital
transformation and innovation helps in ensuring long-term growth and success of the respective
company. As per rest 5 participants, innovation and digital technologies do not play significant
role in long term growth and success of the entity.
Present data to draw valid and meaningful conclusion and recommendations from data analysis
The present report is based on innovative and digital technologies implemented by the
company to ensure future growth. It is analyzed that currently, it has become important to use
innovative and digital ways. Through this, it is possible to perform the organizational tasks
effectively. However, the organization has to face numerous challenges while implementing
innovation and digital technologies. They have to face resistance of workforce that put direct
Document Page
impact on the organizational performance. To deal with the challenges, necessary
recommendations are mentioned below:
ď‚· It is suggested that training & development is important to enhance the skills of
employees. In this context, business managers of the respective company needs to
arrange necessary training & development programs in order to make the workers
familiar with organizational environment. Further, they need to arrange on-the-job
training programs so that the employees can learn while earning. Here, training will help
in improving the knowledge base of workers so that they can perform assign duties
effectively.
ď‚· Motivation plays a crucial role in developing willingness among workforce. Motivated
employees are likely to perform assigned duties in significant manner. For this purpose,
business managers of Marks & Spencer need to adopt monetary and non-monetary ways
to keep the employees inspired. In terms of monetary techniques, they need to adopt
necessary ways such as incentives, bonus and more. Apart from the monetary ways, they
are also required to adopt non-monetary ways such as appreciation, performance
appraisal, recognition and more to motivate the workforce. This will help the company in
implementing innovation & digital technologies at workplace in significant manner.
ď‚· It is recommended that communication is important to facilitate changes within company.
In this regard, Marks & Spencer needs to maintain regular communication with
workforce in order to implement necessary changes within the company. Here,
communication will help them in maintaining proper flow of information within business
in significant manner.
ď‚· It is analyzed that employees are likely to resist while implementing innovation and
digital techniques within company. Therefore, it is suggested to give proper orientation to
workforce so that they get familiar with the change. This will further help in getting
support of workforce so that company will be able to implement changes at work place
significantly.
ď‚· Maintaining positive environment at workplace is imperative to implement innovative
and digital techniques at workplace. Here, positive environment is likely to strengthen the
relationship of workers and their seniors so that changes can be implemented within the
company in significant manner.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
TASK 4
Reflect on the values of undertaking the business project to fulfill the pre-defined objectives
Through the present project, I gained ample of information and knowledge that will help
me in future career growth. The current project is related with implementation of innovative and
digital ways to perform the assigned duties in an appropriate way. During the project, I got to
know significance of workplace transformation which is important to gain success in the current
competitive world. Further, implementation of innovative digital techniques is crucial to make
the work simpler and easier for workforce. With the help of advance techniques, it is possible for
the employees to perform the assign work with greater efficiency. Additionally, I came across
with the challenges face by the companies while implementing changes. I found that employees
are likely to resist changes as they also need to make changes in their working practices. After
implementing changes, the employees cannot continue with the pre-defined practices any longer.
This affects the success of the company in profound manner. Further, the business entity face
challenges of lack of funds, resources and more. To implement new techniques at workplace, it is
important to have adequate amount of funds. Without having sufficient number of resources, it is
quite complex to implement changes at workplace. This knowledge will help me in contributing
towards change management practices of the company. With this, I am able to make an enriching
career to grow in future period of time.
During the current project, I also got communication skills that is important in order to
exchange the information with different people at workplace. While working on the project, I
used to interact with ample of people in terms of respondents, staff and more. This helped me in
conquering over my fear of public speaking. As a result, I am able to communicate with others
effectively. This skill will make me enable to communicate with other people in better way while
working within the organization. Further, I also developed presentation skills during the project.
While working on the project, I need to deliver presentation. This helped me in improving my
capabilities to deal with the facts & figures. As a result, I am able to prepare and deliver effective
presentation at workplace. With this, I am able to make impressive image in front of my seniors.
This will help me in getting promotion in future. Further, I also need to collect and analyze the
data during the project work. This improved my capabilities of collecting and analyzing the data.
Document Page
These all skills and capabilities will help me in ensuring career growth in future. By having such
skills, I can easily make an enriching career in long-run.
Conclusion
Out of the above-mentioned information, it is analyzed that Innovative digital workplace
is related with implementation of advance techniques at workplace so that the organization can
grow in future period of time. Transformation refers to using new, advance and updated
techniques at workplace. Implementation of innovative digital techniques is crucial to make the
work simpler and easier for workforce. With the help of advance techniques, it is possible for the
employees to perform the assign work with greater efficiency. However, the company faces
significant challenges while implementing innovation and digital technologies in terms of
resistance of workforce, lack of funds, resources and more. There is requirement to implement
appropriate strategies to deal with the challenges significantly.
Document Page
References
Books and journals
Alam, S., 2019, August. An Innovative Project Management System. In 2019 International
Conference on Information Management and Technology (ICIMTech) (Vol. 1, pp. 180-
185). IEEE.
Andres Imaz, A., 2020. Project management plan definition for the implementation of a
European Railway Traffic Management System in Australia (Master's thesis, Universitat
Politècnica de Catalunya).
Azhar, M.T., Khan, M.B. and Zafar, M.M., 2019, December. Architecture of an enterprise
project life cycle USING HYPERLEDGER PLATFORM. In 2019 13th International
Conference on Mathematics, Actuarial Science, Computer Science and Statistics
(MACS) (pp. 1-5). IEEE.
Bigorra Puente, D., 2017. Project management plan of the creation of a travellers-oriented
mobile application (Master's thesis, Universitat Politècnica de Catalunya).
Bigorra Puente, D., 2017. Project management plan of the creation of a travellers-oriented
mobile application (Master's thesis, Universitat Politècnica de Catalunya).
Bjorvatn, T. and Wald, A., 2018. Project complexity and team-level absorptive capacity as
drivers of project management performance. International Journal of Project
Management, 36(6), pp.876-888.
Bjorvatn, T. and Wald, A., 2018. Project complexity and team-level absorptive capacity as
drivers of project management performance. International Journal of Project
Management, 36(6), pp.876-888.
Cicmil and et. al., 2017, April. Exploring the complexity of projects: Implications of complexity
theory for project management practice. Project Management Institute.
Clevenger, C.M., 2018. Development of a Project Management Certification Plan for a
DOT. Journal of Management in Engineering, 34(4), p.06018002.
Dinnik, D.I., Grigoryeva, N.S. and Galoyan, Y.E., 2019, August. Improving project management
of socio-economic development of the region with the use of soft computing.
In International Conference on Theory and Application of Soft Computing, Computing
with Words and Perceptions (pp. 214-220). Springer, Cham.
Dinnik, D.I., Grigoryeva, N.S. and Galoyan, Y.E., 2019, August. Improving project management
of socio-economic development of the region with the use of soft computing.
In International Conference on Theory and Application of Soft Computing, Computing
with Words and Perceptions (pp. 214-220). Springer, Cham.
Ermakova, O.V., Kaloshina, M.N. and Dianova, E.V., 2019. Management of innovative projects
over the life cycle of distributed aviation systems. Russian Engineering Research, 39(5),
pp.439-442.
Galli, B.J., 2018. How to Effectively Use Economic Decision-Making Tools in Project
Environments and Project Life Cycle. IEEE Transactions on Engineering
Management, 67(3), pp.932-940.
Hinings, B., Gegenhuber, T. and Greenwood, R., 2018. Digital innovation and transformation:
An institutional perspective. Information and Organization, 28(1), pp.52-61.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Lientz, B., 2017. Project management: A problem-based approach. Bloomsbury Publishing.
Maraie, M.A., 2020. Guidelines for a Standard of Work Breakdown Structure for Construction
Planning. International Journal of Construction Project Management, 12(1), pp.33-60.
Meske, C., 2019. Digital workplace transformation–on the role of self-determination in the
context of transforming work environments.
Nguyen, D.A. and Garvin, M.J., 2019. Life-cycle contract management strategies in US highway
public–private partnerships: Public control or concessionaire empowerment?. Journal of
management in engineering, p.04019011.
Silvius and et. al., 2017. Considering sustainability in project management decision making; An
investigation using Q-methodology. International Journal of Project Management, 35(6),
pp.1133-1150.
Torous, J. and Roberts, L.W., 2017. Needed innovation in digital health and smartphone
applications for mental health: transparency and trust. JAMA psychiatry, 74(5), pp.437-
438.
Trott, P., 2017. Innovation management and new product development. Pearson education.
Vuorinen, L. and Martinsuo, M.M., 2018. Lifecycle view of managing different changes in
projects. International Journal of Managing Projects in Business.