logo

Introduction to Risk Mitigation

17 Pages4584 Words161 Views
   

Added on  2020-05-28

Introduction to Risk Mitigation

   Added on 2020-05-28

ShareRelated Documents
Name:Student number:Unit number:Assessment number:
Introduction to Risk Mitigation_1
1. Executive Summary Risk mitigation is a key process for the construction project. In order to ensure proper project completion for the WSI Blue Mountains TAFE project (19735 Project 4) is attained, proper identification, analysis, evaluation and treatment of the risks will be important. This document will therefore analyze the risks which can be experienced during the project execution and provide the mechanism of mitigating the risks available (Jackson, 2010). Moreover, the levelof likelihood of the risks occurring is different from one risk to another. The order to action will determine the seriousness which can be awarded during the mitigation process. Different risks can occur at the same time and this will mean that the action taken will depend on the impact which the risk has on the progress on the project execution. In addition, project uncertainties due to the available risks are taken care of when the risk management plan is available. In this project, the key risks which will be addressed include the risk during contract awarding. Some ofthe key risks in this stage may include involvement of incompetent personnel during the negotiation process. This means a wrong deal which may hinder the implementation stage is achieved. 2. Introduction Risks are likely to occur during the project implementation stage. The only action which can be taken to ensure that the implementation stage continuous well is coming up with a perfect plan to mitigate the available risks. From the contract negotiation to the handover, risks are ever present. The risk plan therefore has to identify the risks available in the projects right from the contracting period (In Ratay, 2012). This will ensure that successful completion of the project is attained. Some of the key risks in the contractual documents include wrong contract sum awarding to the project. This will mean that the contract sum will not be able to complete the
Introduction to Risk Mitigation_2
project and lead to stalling of the project. Involving proper personnel with experience will ensurethat the project negotiation details are well done and ensure that the time allocation and project sum mare sufficient to complete the project. Another key risk which may be experienced is on the technical part of the project. Many construction projects are able to stall due to lack of workable technical details. The technical parts are important. The contract must be able to analyze all the technical details and ensure they are well workable. This will ensure that the progress on work is not hinders through evaluation of the technical details when found they cannot be implemented on field. In addition, in order to ensure work progress is maintained, proper logistics must be placed on board. The logistics ensures that all the requirements are delivered to the team for them to ensure they complete the work on allocated team (Bissonette, 2016). In addition, the logistics ensures that all the project details are well clarified and issues areaddressed on time. The logistics ensures that the contract period is well kept and works are completed on time for handover. Unclear plan on material deliver on site, payment of workers and poor quality materials are some of the logistical issues which may be experienced during the project execution. In addition, another area which has risks is the construction process. Lack of proper planning is one of the key risks which are experienced in the construction process. The WSI Blue Mountains TAFE project (19735 Project 4) is not different and likely to experience thesame risk. Therefore proper planning to solve such risk and mitigate them are needed. The planning for mitigation of the risks needs to be done early enough to ensure proper project completion. In addition, financial risks are key problems which affect construction projects during project implementation. Proper contract agreements must be arrived at on matters of payment. Securing financial assistance early enough is a key resolution which will ensure progress of works is done well. Financial difficulties are key risks which are able to make project
Introduction to Risk Mitigation_3
stall and lead to their incompletion. Proper address of the financial risks will ensure that the works continue well and completion timeline is met. In addition, addressing these risks will ensure that the workers are well motivated since they are able to receive their financial compensation on time. This paper will analyze all these risks and look at different ways which can be implemented to mitigate them in relation to the WSI Blue Mountains TAFE project (19735 Project 4) project. 3. Risk AssessmentAll processes are able to carry some level of risk in them. This is the same in constructionproject implementation. The major part for the projects is to identify the risks and be able to come up with a mitigation plan (Pritchard, 2015). The risk assessment is able to help in the risk identification in the different processes of the project implementation. This will be done in relation to the WSI Blue Mountains TAFE project (19735 Project 4) project. This part will identify the different risks which are likely to occur and assess their level of occurrence. The risks are likely to affect the project output and therefore their output is important to ensure that the work progress is not affected. 3.1 Identification The contractual process is important for any project implementation. There are key risks which are likely to affect the implementation or a project once the contractor is chosen. Proper detail analysis is one of the processes which must be done by the contract. This includes the site visitation to ensure that the working conditions in site are well laid off (In Fraser, In Simkins & In Narvaez, 2015). Land issues and risks are key risk which has been able to hinder the start off of projects at different site. This happens where the contractor is not aware of the working site and has not done any background check on the site. Proper site visitation and site background
Introduction to Risk Mitigation_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Experienced Project Engineer in Oil & Gas Field - Mohsin Javaid Bajwa
|4
|696
|416

Project Plan TABLE OF CONTENT For Retail Store Expansion
|11
|2997
|459

Implement Change Management Process
|14
|3020
|482

Technical Risk Analysis 2022
|11
|2777
|20

Project Development and Implementation
|9
|2809
|59