Section 1
1.1 Justification of Project
A Sentry aircraft incident relating to a failure of the portable fire fighting oxygen supply during an
emergency resulted in insufficient oxygen for the crew when dealing with the emergency. This led
to an urgent modification being issued by the Sentry Delivery Team (DT). Mitigation has been put
in place until this modification can be installed, but the mitigation has limitations on the amount and
type of passengers our platform can carry. The author is the desk officer who has the responsibility
for all aspects of the platform and capability and will be by default the Project Manager (PM). This
project was to find a permanent solution to ensure the risk was As Low As Reasonably Possible
(ALARP), thus providing assurance to our safety chain.
1.2 Project Deliverable
The plan of this safety modification based on the alignment of the successful integration of a new
oxygen system on the aircraft, which would provide a safer environment to fly in.
The deliverables of the project are:
Fully functional and adequate emergency oxygen system
System design
Updated aircraft documentation set
Trial plan
Implementation plan
The completion of the project would allow the aircraft to operate to its maximum capability and
adhere to latest safety guidance.
1.3 Project Descriptions
Budget: The project budget would include the cost and expenses of the budget for the finishing of
the installation of the oxygen system. This will come from aircraft program costs and will have to be
budgeted and prioritised accordingly. Since this is a safety modification, it will be a top priority.
Duration:
Phase one: Define what the problem is and Produce a Statement of Requirement (SOR)
Phase two: Distribute the SOR, bring together internal and commercial stakeholders. This will
allow a better understanding of the route to contract.
Phase three: Delivery of modification. Detailed Statement of work, interweaved into aircraft
availability.
Main Stakeholders: The stakeholders of the project would include the Customer, project manager,
sponsor, end users and project team members. They are the crucial stakeholders of the project
aligning the finishing of the works successfully. They are;
Main Stakeholders. There are eight key stakeholders:
The Station Commander (Delivery Duty Holder)
DE&S commercial lead - Delivery Team
Project manager – Project Team Lead
Aircraft Authority
Sponsor
Project Subject Experts
Requirements manager
Operators
Roles and responsibilities of stakeholders
2
Project Development and Implementation_2
Project manager: One of the most important stakeholder who has the overall responsibility for the
completion of the project from initiation to closure. He is also liable to meet the cost estimation and
development of a budget and monitoring the progress of the project as well. In addition to this, they
also control the time management and make sure that the define project help to meet the define
aim and objectives in better manner.
Sponsor: The project sponsors were responsible for providing the resources to the project team
for executing their works. The project sponsors would enable the monetary support to the project
works. The sponsor would be the Force Commander, who owns the asset. He is the person who
raise find for the project and also accountable for the project as well. Basically he is act as a link
between the project, business community and strategic level decision making group. As per the
define project, sponsor also provide the direction and guidance for the project empowerment and
assist to meet the define aim.
Project team members: They work under the guidance of the project manager and also make
sure that they perform the technical work for the project in order to meet the define aim of the
project. In addition to this, it is also analysed that they are responsible for carrying out the task that
is assigned to them and also then report to the project manager as well. The project team
members would enable the finishing of the works required in the project and aligning the
management of the advanced work alignment. All the activities developing the final project
deliverable were the responsibility of the team members. They are;
PM
Requirements Manager
Project Management Assistant
Logistics
Section 2
2.1 Detailed Stakeholder Negotiation Strategies
Timescales and targets
PM present route to success to the Project Sponsor, this needs to take place in XXXXXXX so
that authority can be granted in order to commence work ASAP.
Tranche 1 by 07 May 2021: The PT should engage through capability integration working
groups to fully understand the problem though detailed, planning and analysis. This should
include reaching out to internal delivery teams and other operators of the Boeing 707. The
should culminate in an aligned SOR that can be endorsed by the PM and taken forward to
commercial for consideration.
Tranche 2 by 20 Aug 2021: Presentation of the SOR to the Delivery Team (DT) stakeholders.
This will allow the DT to have a full understanding of the requirement to enable the drafting of a
Business Case. During this process the PT should fully support the DT, this will allow the DT to
fully consider the following areas;
o Impact on front line operations
o Priorities
o Trial period
o Modification restrictions
o Security implications
o Safety concerns
o Training courses
3
Project Development and Implementation_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Communication Plan Assignment
|7
|927
|29

Developing Cloud Service Management Software
|2
|579
|82

Project Charter for XYZ Revamp Project
|10
|2521
|437

Measurable Project Objectives Assesment
|2
|321
|20

Code of Conduct And Legislation Report
|5
|606
|16

Project Management in Telco Industry
|9
|1609
|57