Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start:

   

Added on  2022-10-02

115 Pages2991 Words4 Views
Start
Start: Mon 13/01/14ID: 2
Finish: Mon 10/02/14Dur: 25 days
Comp: 0%
Concrete
Start: Wed 19/02/14ID: 5
Finish: Mon 18/08/14Dur: 155 days
Comp: 0%
Masonry
Start: Tue 11/03/14ID: 13
Finish: Mon 25/08/14Dur: 144 days
Comp: 0%
Metalwork
Start: Wed 12/03/14ID: 21
Finish: Mon 27/10/14Dur: 197 days
Comp: 0%
Job Duration
Start: Mon 13/01/14ID: 1
Finish: Mon 10/11/14Dur: 259 days
Comp: 0%
Page 1
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _1
Hydraulics
Start: Tue 11/02/14ID: 34
Finish: Wed 29/10/14Dur: 224 days
Comp: 0%
Electrical
Start: Tue 11/02/14ID: 50
Finish: Sat 25/10/14Dur: 221 days
Comp: 0%
Page 2
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _2
Page 3
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _3
Mechanical
Start: Sat 05/04/14ID: 66
Finish: Fri 12/09/14Dur: 138 days
Comp: 0%
Waterproofing
Start: Mon 02/06/14ID: 83
Finish: Wed 10/09/14Dur: 87 days
Comp: 0%
Page 4
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _4
Plasterer
Start: Thu 20/03/14ID: 90
Finish: Tue 02/09/14Dur: 143 days
Comp: 0%
Carpenter Fitout
Start: Sat 30/08/14ID: 98
Finish: Sat 20/09/14Dur: 19 days
Comp: 0%
Painter
Start: Sat 30/08/14ID: 106
Finish: Thu 30/10/14Dur: 53 days
Comp: 0%
Ceramic Tiler
Start: Mon 08/09/14ID: 114
Finish: Thu 23/10/14Dur: 40 days
Comp: 0%
Carpet
Start: Wed 24/09/14ID: 120
Finish: Sat 08/11/14Dur: 40 days
Comp: 0%
Page 5
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _5
Cleaner
Start: Fri 03/10/14ID: 126
Finish: Mon 10/11/14Dur: 33 days
Comp: 0%
Page 6
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _6
Preliminaries
Start: Mon 13/01/14ID: 3
Finish: Fri 17/01/14 Dur: 5 days
Res:
Groundworks
Start: Sat 18/01/14 ID: 4
Finish: Mon 10/02/14Dur: 20 days
Res:
Page 7
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _7
Page 8
Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start: _8

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Assignment on Critical Summary Critical External
|33
|1153
|6

Gantt chart. Figure 1: Gantt chart showing Critical pat
|2
|235
|76

1 2 Start: 11-04-19 ID: 1 Start: 18-04-19 ID: 2 Finish: 17-04-19
|5
|457
|30

Project Management: Benefits Administration Software
|4
|811
|299

Designing Pharmacy App and Database Servers & Hardware
|11
|1662
|175

Project Management: Time Inc.
|16
|2347
|145