Running head: PROJECT MANAGEMENT
Designing pharmacy App and database servers & hardware
Name of the Student:
Name of the University:
Designing Pharmacy App and Database Servers & Hardware_1

1PROJECT MANAGEMENT
Table of Contents
1. Project schedule..................................................................................................................2
2. Assign milestones...............................................................................................................4
3. Assign resources.................................................................................................................4
4. Assign project cost for staffing...........................................................................................6
5. Project budget.....................................................................................................................7
6. Project Gantt chart..............................................................................................................9
Bibliography.............................................................................................................................10
Designing Pharmacy App and Database Servers & Hardware_2

2PROJECT MANAGEMENT
1. Project schedule
Outline
Number Task Name Duration Start Finish
0 Designing of Pharmacy Application 61 days Thu 28-02-19 Mon 29-04-
19
1 Start of Project 0 days Thu 28-02-19 Thu 28-02-19
2 Project Initiation Phase 10 days Thu 28-02-19 Sun 10-03-19
2.1 Preparing of a project plan 2 days Thu 28-02-19 Fri 01-03-19
2.2 Allocation of stakeholders 2 days Sat 02-03-19 Sun 03-03-19
2.3 Preparing financial plan 2 days Mon 04-03-
19 Tue 05-03-19
2.4 Feasibility study 1 day Wed 06-03-
19
Wed 06-03-
19
2.5 Discussion on project overview 3 days Thu 07-03-19 Sat 09-03-19
2.6 Approval of Project 0 days Sun 10-03-19 Sun 10-03-19
3 Project Planning Phase 6 days Sun 10-03-19 Fri 15-03-19
3.1 Design of Project Charter 1 day Sun 10-03-19 Sun 10-03-19
3.2 Planning on technical requirements 1.5 days Mon 11-03-
19 Tue 12-03-19
3.3 Making a final budget plan based on project
requirements 1.5 days Tue 12-03-19 Wed 13-03-
19
3.4 Sanction of budget for procuring technical
aspects and project developers 0.5 days Thu 14-03-19 Thu 14-03-19
3.5 Procuring technical requirements and
developers 1.5 days Thu 14-03-19 Fri 15-03-19
3.6 Completion of Planning Phase 0 days Fri 15-03-19 Fri 15-03-19
4 Performing of Project Execution 9 days Sat 16-03-19 Sun 24-03-19
4.1 Designing of the project layout 1 day Sat 16-03-19 Sat 16-03-19
4.2 Arranging network and Database hardware
and server requirements 2 days Sun 17-03-19 Mon 18-03-
19
4.3 Performing of software development for the
Appication 1 day Tue 19-03-19 Tue 19-03-19
4.4 Testing of compiled code 5 days Wed 20-03-
19 Sun 24-03-19
4.4.1 Testing cases 1 day Wed 20-03-
19
Wed 20-03-
19
4.4.2 Execute the testing 2 days Thu 21-03-19 Fri 22-03-19
4.4.3 Testing the software 2 days Sat 23-03-19 Sun 24-03-19
4.5 Completion of Execution Phase 0 days Sun 24-03-19 Sun 24-03-19
5 Project Close-out Phase 29 days Mon 25-03-
19
Mon 22-04-
19
5.1 Identification of raised issues during testing
phase 2 days Mon 25-03-
19 Tue 26-03-19
5.2 Resolving over issues and final checkout of 2 days Wed 27-03- Thu 28-03-19
Designing Pharmacy App and Database Servers & Hardware_3

3PROJECT MANAGEMENT
project code 19
5.3 Laying out of servers and hardware 2 days Fri 29-03-19 Sat 30-03-19
5.4 Design of network plan 3 days Sun 31-03-19 Tue 02-04-19
5.5 System analysis and design 8 days Wed 03-04-
19
Wed 10-04-
19
5.5.1 Analysing existing system 1 day Wed 03-04-
19
Wed 03-04-
19
5.5.2 Analysing the system requirements 2 days Thu 04-04-19 Fri 05-04-19
5.5.3 Design of database 3 days Sat 06-04-19 Mon 08-04-
19
5.5.4 System modelling 2 days Tue 09-04-19 Wed 10-04-
19
5.6 System implementation 12 days Thu 11-04-19 Mon 22-04-
19
5.6.1 Documentation of system 4 days Thu 11-04-19 Sun 14-04-19
5.6.2 Hardware requirements 2 days Mon 15-04-
19 Tue 16-04-19
5.6.3 Database specifications 1 day Wed 17-04-
19
Wed 17-04-
19
5.6.4 Description of system module 2 days Thu 18-04-19 Fri 19-04-19
5.6.5 Maintenance of the system 3 days Sat 20-04-19 Mon 22-04-
19
5.7 Completion of close phase 0 days Mon 22-04-
19
Mon 22-04-
19
6 Project completion phase 7 days Tue 23-04-19 Mon 29-04-
19
6.1 Final project plan document 2 days Tue 23-04-19 Wed 24-04-
19
6.2 Handling over project documentation 1 day Thu 25-04-19 Thu 25-04-19
6.3 Training of employees 1 day Fri 26-04-19 Fri 26-04-19
6.4 Releasing the project resources 2 days Sat 27-04-19 Sun 28-04-19
6.4.1 Communicate the closure to project
stakeholders 1 day Sat 27-04-19 Sat 27-04-19
6.4.2 Terminating the supplier contracts 1 day Sun 28-04-19 Sun 28-04-19
6.5 Gaining feedback 1 day Mon 29-04-
19
Mon 29-04-
19
6.6 Completion of final phase 0 days Mon 29-04-
19
Mon 29-04-
19
Designing Pharmacy App and Database Servers & Hardware_4

End of preview