logo

Soil and Materials Lab Report on Concrete Mixing Ratio and Strength Testing

   

Added on  2023-04-22

16 Pages2506 Words328 Views
Running head: LAB REPORT 1
Soil and Materials 1/ U22293
First Name Last Name
Institution

LAB REPORT 2
INTRODUCTION
During the process of making concrete for any construction work, it very important to
employ the suitable concrete mixing ratio since this will enable the construction teams to achieve
a very strong and highly durable concrete mix. During the concrete mix there are four very
significant materials required that is sand, cement, aggregate as well as water (Abrams, 2010). A
concrete mixture ratio of 1 part cement, 3 parts sand, and 3 parts aggregate will produce a
concrete mix of approximately 3000 psi. After the mixing there need to be curing of the concrete
to ensure that the resultant of the concrete. The curing may include the pouring water, using
steels among others (Materials, 2010). This can be done through flow test on fresh concrete
which is out according to BS EN 12350-5. After preparing trial mixes, the mounds were filled
with concrete in three layers, each layer being compacted using a standard rounded rod to
remove as much entrapped air as possible and to produce full compaction of concrete without
segregation Some of the aims of this experiment is given as below;
Aims of the experiment
To describe methods of testing concrete
To discuss the properties of fresh and hardened concrete and their dependence on the mix
proportions
Procedure
Preparations of both cubic and cylindrical concrete moulds

LAB REPORT 3
The moulds surfaces were first cleaned and oiled on their inside surfaces to prevent development
of bond between the mould and the concrete (Joseph, 2013). The moulds were then assembled
and tightened with bolts and nuts to prevent leakage of cement paste and to avoid the plastic
concrete from dismantling during the vibration process while using the vibrator machine (Bartos,
2013).
Preparation of concrete
The ingredients were poured into a clean earth surface starting with ballast, sand and then cement
in the right mix proportions for the respective mix designs. Mixing was done with a spade for
about 5 minutes, after that, water was poured as the mixing continues at control intervals to avoid
excess water into the mix (Klieger, 2014).
After mixing all the ingredients, they were tested while still plastic, put in the moulds to dry and
harden for 24 hours before curing them in a basin of water.
Casting of cubes and cylinders
The cube specimens were cast in iron moulds generally 100x100x100mm for cubes and cylinder
moulds of height 300mm by 150mm diameter, which conforms to the specifications of BS 1881-
3:1970.
After preparing trial mixes, the moulds were filled with concrete in three layers, each layer being
compacted using a standard rounded rod to remove as much entrapped air as possible and to
produce full compaction of concrete without segregation (Marrs, 2012). The moulds were filled
to overflowing and excess concrete removed by scraping off the surface of the moulds.
The test specimens were then left in the moulds undisturbed for 24 hours and protected against
shock, vibration and dehydration.

LAB REPORT 4
De-molding the cast concrete cubes and cylinders
The cast cubes and cylinders were left in the moulds for 24 hours and then they were de-molded.
De-molding is done after setting of the concrete as shown in figure 10.
Before placing the cast cubes and cylinders in the water basin, they were marked with a water
proof chalk.
Curing of concrete
The cast cubes and cylinders after being de-molded are left in a water basin with the aim of
keeping the concrete saturated so that there is adequate water for the hydration of cement and
also to prevent shrinkage cracking as shown in figure 11 (Marrs, 2012). The cubes were cured
for 28days.
FLOW TEST
To study the workability of different concrete mixes, flow test on fresh concrete was carried out
according to BS EN 12350-5.
Slump test
The test moulds used to do the slump test consists of a cone frustum 300mm high and is placed
on a smooth surface and filled with concrete in 3 layers each being tampered 25 times with a
standard rod with a rounded end (Tamimi, 2013).
The excess concrete is scraped off the surface and the cone is slowly lifted up. The height of the
slump is noted down and compared with the height of the cone initially. The decrease in height
was the slump height and was noted.
TESTS FOR THE COMPRESSIVE STRENGTH OF CONCRETE

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Civil Engineering | Assignment
|19
|2655
|15

Design and Build of Proposed Halls of Residence Project by L&D Contracting Company
|17
|3740
|18

Concrete Strength: Effects of Water/Cement Ratio on Workability and Compressive Stress
|9
|1795
|319

Effect of Size and Shape on Compressive Strength of Concrete
|40
|6160
|204

Concrete Mix & Cast Report - Design, Constituents, Results
|7
|1051
|442

Substructure: Foundation, Ground Floor and DPC
|13
|2438
|450