Managing Projects in the Organization: A Case Study of Jointing Tech

Verified

Added on  2024/07/12

|21
|5026
|202
AI Summary
This report explores the application of project management tools and techniques through a case study of Jointing Tech, a leading distributor of power cables and accessories. It examines the implementation of a project plan for their Trace Heating division, analyzing the strengths and weaknesses of the approach. The report also includes a critical evaluation of the author's own management abilities and a self-development plan to enhance their skills.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Managing Projects in the Organization

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
Introduction
......................................................................................................................................4
1. Project management tools and techniques.
.................................................................................. 5
2. A Plan for implementation of project:
......................................................................................... 6
3. Relevant steps for implementation
............................................................................................ 10
4. Implementation of the plan
........................................................................................................ 12
5. Project outcome
.........................................................................................................................15
6. Critical evaluation of own- management abilities
.....................................................................15
7. Self –development plan
............................................................................................................. 18
Conclusion
..................................................................................................................................... 21
Reference List
................................................................................................................................ 22
Document Page
Introduction
The unit helps to understand the advantages of project management tools and techniques. A case

study of
Jointing Tech will be prepared, for implement plans and managing project. In addition,
necessary steps will be followed for executing the plan in the project. Jointing Tech is a leading

distributor of power cables and accessories developing power cable accessories of Cleat

terminate and join MV and LV cables. It maintains electrical infrastructure of UK and recently

Jointing Tech have target to develop a project for Trace heating division. This project will also

identify the strength and weakness and will develop a plan to improve the performance in the

project. As a project development manager, implementing project plan and communicating the

project plans with colleagues and stakeholders are necessary to conduct during plan

development.
Document Page
1. Project management tools and techniques.
A project is series of sequenced plan, which are interrelated and managed by any

organisational manager for achieving specifying goals within limited time and monetary

resource. A methodology used to provide minimal framework to assist the manager of the

project. Therefore, the manager can make work in easy and effective way. They are using

various tool or techniques to facilitate efficient work management. The tool of the project

managements helps to display a roadmap, for easy communication, between team members

and the management body. The tools of the project development help to develop and increase

efficiency of product development management. The following tools will be used for this

project:-

Project Libre/Ms Project- It is project management software consists of Java
programming language. Jointing Tech will use this software for procuring an

estimate of labor cost, time and amount of material usage. It has a ribbon style menu,

which helps to construct the project plan. Project libre and Microsoft project have

similar interface and usage. This software will help to estimate costing features like

labor, work time, usage of material and others.

WBS- The work breakdown structure or WBS is used to deliver the plans of project
in to smaller and detailed components.WBS helps to schedule the estimated cost and

provide guidelines for project development. Jointing Tech is an electricity application

distribution, therefore it have different plans to execute. Therefore, work breakdown

structure will help to the firm to divide the activities into smaller components for

efficient outcome.

Gantt Chart- Gantt Chart also helps to schedule the project, but it provides data in
form of bar chart. Through Gantt chart, a firm can estimate the start and end day of

the planned project. It also illustrates the relationship between involved activities of

plan. Jointing Tech has developed a project of trace heating service and equipment

provider. Therefore, Gantt chart will help to estimate the start date of installing

equipment of trace heating. It will also show the relationship of service provided

along with installed equipment. With the help of statistical bar chart Joint tech can

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
estimate the statically outcome from performed series of activities before executing
the plan practically.

Critical Path- the Critical path is a tool used for analyzing the mathematical relation
between program evaluation and review techniques. It helps to calculate the longest

plan activity with required logistic, and discriminate between ‘critical’ and ‘float’

activities. It will help Jointing Tech to estimate the time of complementing the

project. The organization will use the program if required, as the tool is used when

any firm falls in a critical or in any complex situation. It helps to show actual slack

time distinguishing between real time of the activity and available time for the

activity. In long run, if Jointing Tech faces any complication during performing

activity, then Critical path will be best tool for implementation.

The project manager for effective outcome will execute Gantt chart, Work Breakdown structure,

network diagram, critical path. These components are required for conducting overall project in

disciplinary manner. The systematic structure of work breakdown will provide support to

conduct overall project within committed deadline. Jointing Technology will apply the above

mentioned project development tools for providing electricity sector service to core

customer .The main motto of the organization is to provide best technical advice to each

consumer (www.businessmag.co.uk).

2. A Plan for implementation of project:

In order to present the overall project plan and for the Jointing Technology can be explained by

the help of the Gantt chart and providing the overall framework for the planned activity. The

project has been estimated to start from 1
st November 2018 and will be continued for upcoming
five months and twenty-five days. The activities are as follows:

Work breakdown Structure:

Activity
Start date Time estimate (in
days)

End date

Step 1: Prepare the site

for Trace Heating
12-08-2018 15 27-08-2018
Document Page
Activity 1.1:Survey the
location
27-08-2018 2 29-08-2018
Activity 1.2: Permits

request
29-08-2018 1 30-08-2018
Activity 1.3:Evacuate

for foundation
30-08-2018 12 11-09-2018
Activity 1.4: Purchase

material
11-09-2018 16 27-09-2018
Step 2: Building setup

for Trace heating
27-09-2018 10 07-10-2018
Activity2.1: lay the

foundation
07-10-2018 5 12-10-2018
Activity2.2: Build the

protection wall
12-10-2018 2 14-10-2018
Activity2.3: Install

interior plumbing
14-10-2018 9 23-10-2018
Activity2.4: interior

electric work
23-10-2018 10 02-11-2018
Activity2.5: install

interior trace heating

equipment
02-11-2018 20 22-11-2018
Activity2.6: interior

siding
22-11-2018 5 27-11-2018
Step 3: Finishing the

exterior
27-11-2018 3 30-11-2018
Activity 3.1: install

exterior plumbing
30-11-2018 12 12-12-2018
Document Page
Activity 3.2: Install
exterior heating

equipments
12-12-2018 15 27-12-2018
Activity 3.3: Exterior

electric work
27-12-2018 9 05-01-2019
Activity 3.4:exterior

floor covering
05-01-2019 10 15-01-2019
Activity 3.5: exterior

protection
15-01-2019 5 20-01-2019
Step 1: Preparing site for trace heating:

In the initial stage of developing the project plan for the Jointing technology, it is the most

important factor to deliver all the necessary details for how the entire task will be aligned as per

meeting the demands of the project.

Activity 1.1: Survey the location

Before starting the actual project, the land should be surveyed and the corresponding issues need

to be solved.

Activity 1.2: Permits request:

Before starting the construction project, permission should be taken from the higher authority.

Activity 1.3: Evacuate for foundation

After completing all the steps, the land needs to be evacuated to start the constriction project.

Activity 1.4: Purchase material

Proper quality material needs to be purchased in order to start the construction project
.
Step 2: Building setup for Trace heating

Trace heating is the major constriction for this project. Therefore, workers need to construct the

set up for this project

Activity2.1: lay the foundation

After construction the entire set-up, it should be laid down for construction purpose.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Activity2.2: build the protection wall
In order to protect the set-up, protection wall need to continue the construction project

Activity2.3: Install interior plumbing

Plumbing work is done before any construction work is done. The workers will need 9 days for

this work.

Activity2.4: interior electric work

Interior electric work will need 10 days for this entire project.

Activity2.5: install interior trace heating equipment

As it has been mentioned that the trace heating is the most important construction for this

project, therefore, the workers need to implement the trace heating equipments properly.

Activity2.6: interior siding

After the constriction work is done of trace equipments installation, interior siding will be started

which will require 5 days.

Step 3: Finishing the exterior

Three days will be required in order to complete the exterior construction work.

Activity 3.1: install exterior plumbing

Exterior plumbing and the pipelining arrangement will be done for the 12 days duration.

Activity 3.2: Install exterior heating equipments

Fifteen day will be require to complete the overall exterior heating equipments as it will perform

accordingly with the trace heating equipments.

Activity 3.3: exterior electric work

Exterior electric work will be done based on supplying adequate power to the trace heating

equipments and it will require nine days to complete.

Activity 3.4: exterior floor covering

Ten days will be needed to do this job.

Activity 3.5: Exterior protection

Exterior protection will be required for plumbing and electrical equipments. Five days is

sufficient to do this job.
Document Page
3. Relevant steps for implementation
In order to determine and implement the steps, a wide range of techniques can be used. One such

tool is PRINCE2. The PRINCE2 model or Projects IN Controlled Environment is the technique

that is process based. This tool is used for an effective and efficient project management. The toll

is widely used by many private sectors. According to the PRINCE2 model, there are certain

parameters that one needs to follow. The very first step is to determine and plan the possible

outcomes and present a structured plan before initiating the project. The next and the most

significant part is to maintain and control the procedure. The next is to address all the loopholes

and consider the ending of the project. In a PRINCE2 model the project manager, consumer,

supplier and the project board have segregated roles on which the project functions (
Tomanek
and Juricek, 2015
)
Using the PRINCE2 model, the construction project can be determined. Usually such

methodology is implied project to understand the basic building blocks required for

accomplishing any project in an effective manner. This framework always follows three steps

Controlled Start in an organize manner

Controlled Middle in an organize manner

Controlled End in an organize manner

This is the backbone of executing any task in a proper way. Jointing Tech is an organization that

tries to produce electrically modified products. The organization has brand name in the market

due to its LV/MV products. Those cables are used to secure household from any kind of hazards.

The main objective of the organization is to produce such cables that can protect the household

from such technical fault. The PRINCE 2 model is divided into four sub stages

Pre Project
Initiation stage
Subsequent delivery stages
Final delivery stage (Krysiński and Miller, 2016)
In all these stages, the organization has to take necessary steps for directing a project on a right

path. In
Pre-Project, Jointingtech has to define its goal properly. In field of soldering
technologies, this organization tries to be innovative. An innovative design pattern is required to

implement in business structure for better construction purposes. So in this stage, the
Document Page
organization has to take necessary steps required for financial and business growth (Harrison and
Lock, 2017
). Therefore, in this stage the organization has to know about the proper quality
products. Here it is necessary to control and manage the resources properly for organizational

success. Here one has to survey the location properly before putting the cable fibers. Survey of

the location is also necessary before taking any action. Requesting for permit should also be done

in this stage only. For trace heating, it is necessary that pipe should be insulated thermally for

retaining heat loss. The heat generation should be controlled by the temperature of pipe. In

Initiation stage,
the organization has to be particular in buying those materials required for trace
heating. For trace heating, it is necessary to understand that pipes should include common stages

like

Freeze protection
Maintaining temperature scale
Melting of snow during driveways (Kerzner and Kerzner, 2017)
In this stage the organization has to build up necessary structure for setting up trace heating. In

the initial stage the protection wall should be done. Here the engineers have to be posted in the

site to understand the proper plumbing technology. In this stage, interior plumbing has to be

done. If the construction site faces any kind of difficulty here, then in this stage, Jointingtech has

to take strategies to mitigate such problems. After going through the initial plan of interior

plumbing, the next step is to complete interior electric work (
Yang et al., 2016). In subsequent
delivery stage,
here the organization has to make the construction site well equipped with interior
trace heating products. The workers also have to understand the proper plan of action before

engaging in work process. Here the organization has to install trace equipments at construction

site. At the same time, interior siding has to be initiated. In
final delivery stage, Jointingtech has
to complete the exterior construction work. In this stage, the plan has to be implemented in

proper course of action. Exterior plumbing and pipelining have to be installed. Exterior heating

equipments have to be installed for better performance. Such heating equipments are installed for

controlling heat (
Lai et al., 2016). In this stage adequate power supply has to be done to the trace
heating equipments. In final stage, exterior floor covering has to be done. Apart from this,

exterior protection has to be done for securing equipments of plumbing and electrical purposes.

Gantt Chart to show the work structure break down and implementation of plan.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Step 1: Prepare the site for Trace Heating
Activity 1.1:Survey the location

Activity 1.2: Permits request

Activity 1.3:Evacuate for foundation

Activity 1.4: Purchase material

Step 2: Building setup for Trace heating

Activity2.1: lay the foundation

Activity2.2: Build the protection wall

Activity2.3: Install interior plumbing

Activity2.4: interior electric work

Activity2.5: install interior trace heating equipment

Activity2.6: interior siding

Step 3: Finishing the exterior

Activity 3.1: install exterior plumbing

Activity 3.2: Install exterior heating equipments

Activity 3.3: Exterior electric work

Activity 3.4:exterior floor covering

Activity 3.5: exterior protection

12-08-2018
01-10-2018 20-11-2018 09-01-2019 28-02-2019
Figure 1: Gantt Chart

(Created by learner)

4. Implementation of the plan

For success of any plan, it is necessary to understand how to utilize resources in a proper way. In

this way, the project manager can easily analyze how to direct the plan in a proper way. In recent

times extreme season is bringing down bad impacts. Trace heating is a technology that is

necessary all over the years. For installing an improved heat tracing process, it is necessary to

implement such ensured operation that can withstand any harsh weather conditions. If one is

unable to protect any industrial process properly, then it can cause damage to the equipment

(
Hermans et al., 2015). Therefore, proper safety measures have to be taken to prevent such
damage. Proper management of equipment is needed for better understanding of work process.

One has to understand the cost effectiveness of trace heating. Therefore, installing such

technology can not cause large damage on project.
Document Page
Risk Analysis: In any power plant, trace heating can cause lots of risk. One can face inadequate
stoppage of power due to lack of thermodynamic engineering process. Weak control over

resources and lack of engineering process can cause a huge damage to the plant. It is necessary to

install proper management structure. The performance can be affected with incorrect temperature

control in the process (
Aven, 2015). Inadequate requirement of electric supply is the prime
objective of the organization. Without such continuous power supply, the organization can face

huge investment loss.

Stakeholder analysis:
this entire matrix can be explained by following certain stages. For
Jointingtech the major stakeholders are consumers, employees, suppliers, shareholders. So the

success of the organization is dependent how well the management are being beneficial to these

stakeholders.
Document Page
Interests of Stakeholders
The main objective of stakeholders is

to get maximum outcome from the

ongoing process. Without proper

assessment, the stakeholders can be

affected a lot. Whether it is suppliers,

shareholders, consumers, the

management always has to keep

control over each performance

thoroughly (
Power, 2016). Uncut
power supply is needed, because

without that trace heating of the

power plant can be affected.

Close Management

Whether the benefits of stakeholders

are meeting up or not, it is the duty of

management to look at. The

organization can be take prominent

steps by taking proper assessment of

process.

Monitoring

The supervision of management is

required for proper monitoring

purposes. It is a two way process,

both the stakeholders and employers

must know about the strategies.

Therefore it is necessary to think

about this properly.

Proper Information

The stakeholders have to well

informed about any proceedings of

work process. Without such

information the stakeholders will be

uninformed.

Figure 2: Stakeholder analysis

(Created by learner)

Power

Interest

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
5. Project outcome
In this report, the main objective is to manage the project in a positive manner. Outcomes of the

project are defined as some changes or benefits that will be the resultant product. In this project,

it is necessary to find out necessary outcomes that are possible from the project. This heat tracing

market in recent times is cost effective. As it requires minimum maintenance cost, therefore,

people are implementing this kind of electric system. Since 19
th century, primary forms of
industrial heat are coming in form of tars, waxes. This is termed as stream tracing. Around 70%

of industrial heat is coming up form stream tracing. Therefore, this reliable method is used to

minimize this kind of industrial stream tracing. One also has to understand, that this kind of

tracing system is comparatively less costly. The installation and operative methods of this tracing

system is also very easy. As there are no exposed circuits therefore, there is no chance of risk in

this kind of tracing system. This kind of system aims to reduce heat loss and control temperature

in the plant (
Lund et al., 2017). This system nowadays is utilized as freeze protection also. For
high voltage plant, this kind of system will ensure such kind of power operation that can prevent

any kind of electric shock. Therefore, for commercial purposes this type of heat tracing system

can be helpful. Jointing Tech is one of the leading names in electrical infrastructure. Therefore,

the products of this organization are to prevent society due to lack of power supply. This

organization always aims to produce products that have proper tapes, earthing and cable fibers.

So it is hopeful the impact can bring positive effect in power control.

6. Critical evaluation of own- management abilities

The project plan provided above determines the ideas and objectives of the overall

developmental plan. This management plan describes the segmented functions and processes of

the project. My colleagues and peers have reported my project and these advices and suggestions

have been a lesson.

Peer Feedback
According to my peers, the overall idea of the project is transparent and approachable; however,

there are certain limitations of the project which one needs to consider. One of my peers noted

that the work breakdown structure was quite fair and rational but on a realistic approach the work
Document Page
breakdown structure was not followed. This was one of the principle issues resulting in
disruption of certain sectors of the project.

Another issue that has been observed by one of my peers is that the initial budget of the project

exceeded with a considerable difference. This issue led to degradation of other necessary

segments of the project.

One of my colleagues reviewed the overall quality of the project, the availability of the resources

and raw materials and the quality of labor was abundant, however, the coordination among the

workers and the leadership quality of the management was highly flawed which affected the

quality of the project.

Another colleague also noted the loophole in the risk strategy and the issues regarding the

segregating the investors. For any project, it is necessary to assess the possible risks and

strategies and in this project, the possible risks were not addressed properly. This might affect

the overall project and the business process.

Strength and weakness
According to the peers, the overall idea and approach of the project was appreciable, however,

there were certain limitations of the project, which affected the project.

Strengths:

The quality and amount of the resources and raw materials were good, along with this; the

machineries were updated and maintained in order to avoid any kind of disruption. The initial

blueprint of the project was noteworthy. Therefore, according to my peers, I am quite responsible

and have a realistic approach. The work breakdown structure was transparent and all the

parameters like finance, operations and management of labor were discussed in detail. Along

with this, the selection procedures of the workers were just and according to their capabilities,

therefore the quality of the work done in the project was above average. According to them, I am

quite responsible and steady.
Document Page
Disadvantages:
The most significant disadvantage of this project is time management. The process did not

function according to the work breakdown structure. There have been severe delays and the

process while 30 percent of the work was done, because of lack of finances the project was shut

down for about a week. My peers believe that I was quite naïve and due ot lack of experience I

did not consider the key parameters. Along with this, the finances were much higher as

compared to the presented ones. The expected expenditure was far below the actual cost. The

project blueprint did not include the expenses based on the current economy of the nation. The

next issue that has been observed is that the possible risk factors that the organization might

witness have been overlooked. The risk factors presented in the blueprint of the project is quite

vague and therefore might affect the project.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7. Self –development plan
Goals
Specific Measurable Achievable Realistic Timescale
1. To Focus

on my

management

skills

It is necessary

to improve

my

management

skills in order

to improve the

effectiveness

and efficiency

of the

business

process, along

with this, it is

necessary to

focus on this

drawback

because a bad

management

will affect the

work setting

of the

employees.

The current

situation and

quality of

my

management

skill is

below

average and

it needs to

be

improved. A

good

management

skill is

necessary so

that I can

improve the

business

process.

After I will

be able to

present a

flawless

project, only

then I will

be able to

understand

that my

management

The idea of

improving my

management

skills is quite

necessary and

a better

approach is

necessary.

The idea of

improving my

management

skills is quite

a realistic

approach and

is necessary

for a better

business

process.

Better idea of

the business,

handling

responsibility

and a more

stringent

approach is

needed.

I believe the

idea of

improving my

management

skills is quite

realistic and

necessary

approach.

Being a part of

the business it

is necessary

that I am able

to manage my

employees and

staffs. My

current quality

of the project

I was a part of

determined my

lack of

management

skills as noted

by my peers,

Therefore,

now is the

time to focus

on the

improvement.

I will be

working on

my

management

skills,

effective

immediately.

Considering

my current

situation I

believe 6 to

8 months

will be

enough to be

above

average.

However, I

need to be

better than

above

average and

therefore a

year will be

necessary.
Document Page
skills have
improved.

2. To

improve in

handling my

responsibilitie

s

I need to work

on handing

responsibilitie

s and duties.

This goal is

important to

me because

being a part of

a business

project and

the

management,

it is necessary

for me to

focus on my

responsibilitie

s and duties.

My behavior

and quality of

work will

determine a

major portion

of the work.

According to

my peers,

my current

scenario

determines

that my

responsibilit

y skills is

below

average, one

of the

principle

reasons

being my

lack of

knowledge

and

experience

and a rather

casual

approach.

I need to

work on it

and this goal

cannot be

achieved

quickly.

In order to

become

responsible, I

need to focus

on the

business

process and

functions of

the business

process.

Initially I

need to take

petty

responsibilitie

s and focus on

being more

serious on my

job. A casual

approach

needs to be

avoided.

Being a part of

the

management, I

need to focus

on the my

duties and

functions and

as a member

of the

managing

body I will be

subjected to

critical

decision

making

process and

heavy

responsibilities

.

The

approach of

improving

my skills

towards

responsibilit

y will need

about 12 to

15 months.
Document Page

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Conclusion
In this assignment the idea and strategy regarding development of a project has been considered.

Here, the ability and approach towards management of project has been determined and

evaluated. Along with this, the specified tools and techniques that are used in order to achieve a

project are analysed. PRINCE2 is one of the most significant and widely used project

management tools and in this project this tool is used in order to determine an effective and

efficient project management.

In this assignment, the case study of
Jointing Tech has been referred to and a project
management plan has been presented accordingly. The company is one of the leading power

cable manufacturer and distributor. The idea of this assignment is to present a possible project

management plan and the functions and duties of the concerned manager. Along with this, it’s

possible strengths and weaknesses has been determined using the review presented by the peers

and colleagues. Addressing the comments and review presented by the peers, a self–development

plan has been presented using SMART objectives.
Document Page
Reference List
Aven, T., 2015.
Risk analysis. John Wiley & Sons.
Harrison, F. and Lock, D., 2017.
Advanced project management: a structured approach.
Routledge.

Hermans, T., Wildemeersch, S., Jamin, P., Orban, P., Brouyère, S., Dassargues, A. and Nguyen,

F., 2015. Quantitative temperature monitoring of a heat tracing experiment using cross-borehole

ERT.
Geothermics, 53, pp.14-26.
Kerzner, H. and Kerzner, H.R., 2017.
Project management: a systems approach to planning,
scheduling, and controlling
. John Wiley & Sons.
Krysiński, M. and Miller, P., 2016. The Role of Conflict in Project Management in the PRINCE2

Methodology.
Ekonomika i Organizacja Przedsiębiorstwa, (6), pp.3-12.
Lai, J., Qiu, J., Fan, H., Chen, J. and Xie, Y., 2016. Freeze-proof method and test verification of

a cold region tunnel employing electric heat tracing.
Tunnelling and Underground Space
Technology
, 60, pp.56-65.
Lund, R.S., Østergaard, D.S., Yang, X. and Mathiesen, B.V., 2017. Comparison of low-

temperature district heating concepts in a long-term energy system perspective.
International
Journal of Sustainable Energy Planning and Management
, 12, pp.5-18.
Power, H.I.H., 2016. Stakeholder Analysis.

Tomanek, M. and Juricek, J., 2015. Project risk management model based on PRINCE2 and

SCRUM frameworks.
arXiv preprint arXiv:1502.03595.
Yang, X., Li, H. and Svendsen, S., 2016, April. Modelling and multi-scenario analysis for

electric heat tracing system combined with low temperature district heating for domestic hot

water supply. In
Building Simulation (Vol. 9, No. 2, pp. 141-151). Tsinghua University Press.