Running head: NEW BUILDING CONSTRUCTION IN NORTHERN VIRGINIA
New building construction in northern Virginia
Name of the Student:
Name of the University:
NEW BUILDING CONSTRUCTION IN NORTHERN VIRGINIA_1
1NEW BUILDING CONSTRUCTION IN NORTHERN VIRGINIA
Schedule of the project
WBS Task Name Duratio
n Start Finish Resource Names Cost
0 Building construction
schedule in Virginia 180 days 12/10/09 18/06/10 $600,000.00
1 Pre construction stage 30 days 12/10/09 20/11/09 $21,208.00
1.1 Site selection and
supervision 8 days 12/10/09 21/10/09 Site supervisor $5,120.00
1.2 Feasibility report
presentation 9 days 22/10/09 03/11/09 Finance manager $4,680.00
1.3 Resource allocation
and task distribution 7 days 04/11/09 12/11/09 Resource manager $3,920.00
1.4 Final bidding and
negotiation 6 days 13/11/09 20/11/09 Construction manager,
Contractor $7,488.00
2 Construction stage 141 days 23/11/09 07/06/10 $577,088.00
2.1 Signing contract and
permit processing 8 days 23/11/09 02/12/09 Construction manager $5,440.00
2.2 Blueprint design 18 days 03/12/09 28/12/09 Architect $10,080.00
2.3 Vendor selection 17 days 29/12/09 20/01/10 Contractor, sub
contractor[1] $9,701.00
2.4 Purchase material 15 days 29/12/09 18/01/10 Material cost[1] $100,000.00
2.5 Concrete work 34 days 21/01/10 09/03/10 Concrete [1],Labours $228,960.00
2.6 Flooring and tiles 25 days 10/03/10 13/04/10 flooring and tile
cost[1],Labours $127,547.00
2.7 Electricity and
plumbing 15 days 14/04/10 04/05/10 Plumbing and
electricity cost[1] $80,000.00
2.8 Final construction
draft submission 16 days 05/05/10 26/05/10 Construction manager $10,880.00
2.9 Time and schedule
management plan 8 days 27/05/10 07/06/10 Resource manager $4,480.00
3 Post construction stage 9 days 08/06/10 18/06/10 $1,704.00
3.1 Project closure 2 days 08/06/10 09/06/10 $0.00
3.2 Final delivery 3 days 10/06/10 14/06/10 Contractor $1,704.00
3.3 Stakeholder signoff 4 days 15/06/10 18/06/10 $0.00
NEW BUILDING CONSTRUCTION IN NORTHERN VIRGINIA_2
2NEW BUILDING CONSTRUCTION IN NORTHERN VIRGINIA
Figure 1: Schedule for the project
(Source: created by author)
Individual team member’s behavior impact
Individual team member’s behavior helps to determine the tasks. The project manager is
accountable to assign specific role to different team members based on the expertise, previous
knowledge and skills. A project is considered successful only when it is completed within the
boundary line of scope, quality, time and budget.
The finance manager’s responsibility is to conduct feasibility analysis and ensure that the
project will give on-time and quality delivery expected by clients. The resource manager need to
allocate resources for individual activities and the project manager should monitor the activities
and control them according to requirements. If the above mentioned roles are properly played by
human resources then, easily the project will deliver expected outcomes.
NEW BUILDING CONSTRUCTION IN NORTHERN VIRGINIA_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Assignment about What Do You Mean Project Management?
|5
|503
|18

Cost Management in Sunshine Coast Airport Construction Project
|21
|2825
|158

Building Construction by ADCO Constructions - Project Plan and Management
|18
|1859
|339

Business Project Management
|7
|1291
|18

Project Management: Royale Pizza Shop Renovation
|16
|2463
|4

Project Management Techniques
|8
|2107
|64