For each activity, based on the allocated resources a bar chart that is created elaborated below: Activity People Required Duration Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 A1-2 3 21 3 3 A1-3 2 4 2 2 2 2 A2-4 6 3 4 4 A2-5 5 3 5 5 A3-4 3 4 3 3 3 A4-5 2 16 2 2 2 2 Pessimistic time (PT) = 0.66