The assignment provides a comprehensive project plan for the construction of a residential complex in Queensland, Australia. The plan includes a budget breakdown with estimated costs for materials, equipment, and labor, as well as a timeline for completion. It also identifies stakeholders, assumptions, constraints, and approval requirements for the project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT CHARTER
Project Charter
Construction of Residential Complex in Queensland, Australia
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Charter
Construction of Residential Complex in Queensland, Australia
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT CHARTER
Table of Contents
Project Name...................................................................................................................................2
Project Justification.........................................................................................................................2
Project Description..........................................................................................................................2
Project Objectives and Success Criteria..........................................................................................2
High Level Risks.............................................................................................................................3
Summary Milestone Schedule.........................................................................................................3
Summary Budget.............................................................................................................................5
Stakeholder List...............................................................................................................................8
Limits and Exclusions......................................................................................................................8
Assumptions and Constraints..........................................................................................................8
Project Approval Requirements.......................................................................................................9
Assigned Project Manager: Sign off................................................................................................9
Bibliography..................................................................................................................................10
Table of Contents
Project Name...................................................................................................................................2
Project Justification.........................................................................................................................2
Project Description..........................................................................................................................2
Project Objectives and Success Criteria..........................................................................................2
High Level Risks.............................................................................................................................3
Summary Milestone Schedule.........................................................................................................3
Summary Budget.............................................................................................................................5
Stakeholder List...............................................................................................................................8
Limits and Exclusions......................................................................................................................8
Assumptions and Constraints..........................................................................................................8
Project Approval Requirements.......................................................................................................9
Assigned Project Manager: Sign off................................................................................................9
Bibliography..................................................................................................................................10
2PROJECT CHARTER
Project Charter Document
Project Name
Construction of Residential Complex in Queensland, Australia
Project Justification
The completion of the project would result in forming the residential complex suitable for
people’s living with all required facility. The construction projects are developed for the
implication of the operations for the deployment of the effective construction activities. The
project completion would help in yielding the effective and improved operations. The
construction project would yield in using the concepts of project management for developing the
final project.
Project Description
The residential complex construction project is aligned with the implication of the
construction project management operations. The implication of the construction activities would
help in easing the project operations development. The tender documentation is followed by a
project schedule and cost report that would provide a detail overview of the project scheduling
and the cost estimation. The project scheduling is developed by listing the activities that would
be carried on within the project. The activities would allow the formation of the dependencies
and the resource alignment. The completion of the activities, sequencing them, and adding
resources to the project would tend to form the final project plan. The report would help in
easing the flow of information and aligning the final project delivery.
Project Objectives and Success Criteria
The project of Construction of Residential Complex in Queensland, Australia would result in
forming the residential complex suitable for people’s living with all required facility.
The following are the objectives of the project,
• To develop the residential building at Queensland, Australia
Project Charter Document
Project Name
Construction of Residential Complex in Queensland, Australia
Project Justification
The completion of the project would result in forming the residential complex suitable for
people’s living with all required facility. The construction projects are developed for the
implication of the operations for the deployment of the effective construction activities. The
project completion would help in yielding the effective and improved operations. The
construction project would yield in using the concepts of project management for developing the
final project.
Project Description
The residential complex construction project is aligned with the implication of the
construction project management operations. The implication of the construction activities would
help in easing the project operations development. The tender documentation is followed by a
project schedule and cost report that would provide a detail overview of the project scheduling
and the cost estimation. The project scheduling is developed by listing the activities that would
be carried on within the project. The activities would allow the formation of the dependencies
and the resource alignment. The completion of the activities, sequencing them, and adding
resources to the project would tend to form the final project plan. The report would help in
easing the flow of information and aligning the final project delivery.
Project Objectives and Success Criteria
The project of Construction of Residential Complex in Queensland, Australia would result in
forming the residential complex suitable for people’s living with all required facility.
The following are the objectives of the project,
• To develop the residential building at Queensland, Australia
3PROJECT CHARTER
• To use project management concepts for developing the plan for construction of
building
• To complete the project in the estimated time and budget requirements
• To ensure that all safety and required functions are aligned to the construction of the
building
High Level Risks
The high level risks of the project of Construction of Residential Complex in Queensland,
Australia are given below,
Quality Issues: The quality issues in the project is the major risk factor as it would result
in degrading the overall quality of the building developed.
Over budget: The problem of cost overrun is a major factor that would form the impact
on the operations of the project. The over budget would tend to form the major issue in project
operations.
Delay: The delay in project activities would result in forming the issues in the
development of the final project deliverable.
Machine Failure: The failure of the machine and equipments would result in forming
the major issues in the development of the project activities.
Summary Milestone Schedule
The summary milestone schedule of the project of Construction of Residential Complex
in Queensland, Australia is given below,
WBS Task Name Duratio
n Start Finish
1.5 Securing foundation permit, electrical permit, and
plumbing permit 3 days Wed 5/9/18 Fri 5/11/18
• To use project management concepts for developing the plan for construction of
building
• To complete the project in the estimated time and budget requirements
• To ensure that all safety and required functions are aligned to the construction of the
building
High Level Risks
The high level risks of the project of Construction of Residential Complex in Queensland,
Australia are given below,
Quality Issues: The quality issues in the project is the major risk factor as it would result
in degrading the overall quality of the building developed.
Over budget: The problem of cost overrun is a major factor that would form the impact
on the operations of the project. The over budget would tend to form the major issue in project
operations.
Delay: The delay in project activities would result in forming the issues in the
development of the final project deliverable.
Machine Failure: The failure of the machine and equipments would result in forming
the major issues in the development of the project activities.
Summary Milestone Schedule
The summary milestone schedule of the project of Construction of Residential Complex
in Queensland, Australia is given below,
WBS Task Name Duratio
n Start Finish
1.5 Securing foundation permit, electrical permit, and
plumbing permit 3 days Wed 5/9/18 Fri 5/11/18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT CHARTER
2.4 Assigning resources to the activities 2 days Tue
5/22/18
Wed
5/23/18
3.6 Approval of the design 1 day Wed
6/13/18
Wed
6/13/18
4.1.6 Backfilling the foundation 2 days Fri 6/8/18 Mon
6/11/18
4.2.6 Complete Roof Framing and decking 6 days Tue
7/10/18
Tue
7/17/18
4.2.11 Main Electric lining is done 10 days Fri 6/22/18 Thu 7/5/18
4.3.5 Cabinet works in kitchen, bedroom, hall, bathroom,
and balcony 4 days Tue
7/24/18 Fri 7/27/18
4.4.1 Main gate is made 2 days Thu
7/26/18 Fri 7/27/18
4.4.3 Fencing the building 2 days Mon
7/30/18
Tue
7/31/18
4.4.7 Security Cameras are installed 2 days Fri 7/20/18 Mon
7/23/18
4.5.1 Bathroom Equipments are added 2 days Thu 7/5/18 Fri 7/6/18
4.5.2 Kitchen Appliances are added 2 days Thu
7/26/18 Fri 7/27/18
4.5.3 Beds, Chairs, Dining table, Sofa, and side tables are
added 2 days Thu 8/2/18 Fri 8/3/18
4.5.4 Fans, Lights, Air conditioners, and Room heaters are 2 days Mon Tue
2.4 Assigning resources to the activities 2 days Tue
5/22/18
Wed
5/23/18
3.6 Approval of the design 1 day Wed
6/13/18
Wed
6/13/18
4.1.6 Backfilling the foundation 2 days Fri 6/8/18 Mon
6/11/18
4.2.6 Complete Roof Framing and decking 6 days Tue
7/10/18
Tue
7/17/18
4.2.11 Main Electric lining is done 10 days Fri 6/22/18 Thu 7/5/18
4.3.5 Cabinet works in kitchen, bedroom, hall, bathroom,
and balcony 4 days Tue
7/24/18 Fri 7/27/18
4.4.1 Main gate is made 2 days Thu
7/26/18 Fri 7/27/18
4.4.3 Fencing the building 2 days Mon
7/30/18
Tue
7/31/18
4.4.7 Security Cameras are installed 2 days Fri 7/20/18 Mon
7/23/18
4.5.1 Bathroom Equipments are added 2 days Thu 7/5/18 Fri 7/6/18
4.5.2 Kitchen Appliances are added 2 days Thu
7/26/18 Fri 7/27/18
4.5.3 Beds, Chairs, Dining table, Sofa, and side tables are
added 2 days Thu 8/2/18 Fri 8/3/18
4.5.4 Fans, Lights, Air conditioners, and Room heaters are 2 days Mon Tue
5PROJECT CHARTER
added 7/30/18 7/31/18
5.3 Electrical Line Inspection 1 day Fri 7/6/18 Fri 7/6/18
5.6 Final walk-through Inspection 1 day Wed 8/1/18 Wed 8/1/18
6.3 Final Report is made 4 days Mon 8/6/18 Thu 8/9/18
6.5 Project is Closed 0 days Fri 8/10/18 Fri 8/10/18
Summary Budget
The summary budget of the project of Construction of Residential Complex in
Queensland, Australia is given below,
Resource Name Type Work/Unit Standard
Rate Cost
Analyst Human 56 hrs $80.00/hr $4,480.00
Documenter Human 120 hrs $90.00/hr $10,800.00
Project Manager Human 72 hrs $200.00/hr $14,400.00
Budgeter Human 32 hrs $100.00/hr $3,200.00
Planner Human 32 hrs $110.00/hr $3,520.00
Architect Human 96 hrs $175.00/hr $16,800.00
Contractor Human 176 hrs $160.00/hr $28,160.00
Workers Human 312 hrs $150.00/hr $46,800.00
Plumber Contractor Human 56 hrs $140.00/hr $7,840.00
Electrical Contractor Human 80 hrs $155.00/hr $12,400.00
added 7/30/18 7/31/18
5.3 Electrical Line Inspection 1 day Fri 7/6/18 Fri 7/6/18
5.6 Final walk-through Inspection 1 day Wed 8/1/18 Wed 8/1/18
6.3 Final Report is made 4 days Mon 8/6/18 Thu 8/9/18
6.5 Project is Closed 0 days Fri 8/10/18 Fri 8/10/18
Summary Budget
The summary budget of the project of Construction of Residential Complex in
Queensland, Australia is given below,
Resource Name Type Work/Unit Standard
Rate Cost
Analyst Human 56 hrs $80.00/hr $4,480.00
Documenter Human 120 hrs $90.00/hr $10,800.00
Project Manager Human 72 hrs $200.00/hr $14,400.00
Budgeter Human 32 hrs $100.00/hr $3,200.00
Planner Human 32 hrs $110.00/hr $3,520.00
Architect Human 96 hrs $175.00/hr $16,800.00
Contractor Human 176 hrs $160.00/hr $28,160.00
Workers Human 312 hrs $150.00/hr $46,800.00
Plumber Contractor Human 56 hrs $140.00/hr $7,840.00
Electrical Contractor Human 80 hrs $155.00/hr $12,400.00
6PROJECT CHARTER
Telecom Contractor Human 24 hrs $120.00/hr $2,880.00
Civil Engineer Human 96 hrs $170.00/hr $16,320.00
House Painter Human 64 hrs $130.00/hr $8,320.00
Carpenter Human 72 hrs $110.00/hr $7,920.00
Gardener Human 16 hrs $100.00/hr $1,600.00
Technician Human 64 hrs $125.00/hr $8,000.00
External Inspection Officer Human 64 hrs $130.00/hr $8,320.00
Construction Raw Materials Materia
l 1 $25,000.00 $25,000.00
Construction Equipments Rent Materia
l 1 $5,000.00 $5,000.00
Temporary Power Cost Materia
l 1 $1,600.00 $1,600.00
Doors and Windows Materia
l 1 $1,300.00 $1,300.00
Plumbing Equipments and Pipes Materia
l 1 $4,000.00 $4,000.00
Electric Wires and Equipments Materia
l 1 $6,000.00 $6,000.00
Telecom Cost Materia
l 1 $3,000.00 $3,000.00
Telecom Contractor Human 24 hrs $120.00/hr $2,880.00
Civil Engineer Human 96 hrs $170.00/hr $16,320.00
House Painter Human 64 hrs $130.00/hr $8,320.00
Carpenter Human 72 hrs $110.00/hr $7,920.00
Gardener Human 16 hrs $100.00/hr $1,600.00
Technician Human 64 hrs $125.00/hr $8,000.00
External Inspection Officer Human 64 hrs $130.00/hr $8,320.00
Construction Raw Materials Materia
l 1 $25,000.00 $25,000.00
Construction Equipments Rent Materia
l 1 $5,000.00 $5,000.00
Temporary Power Cost Materia
l 1 $1,600.00 $1,600.00
Doors and Windows Materia
l 1 $1,300.00 $1,300.00
Plumbing Equipments and Pipes Materia
l 1 $4,000.00 $4,000.00
Electric Wires and Equipments Materia
l 1 $6,000.00 $6,000.00
Telecom Cost Materia
l 1 $3,000.00 $3,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT CHARTER
Carpentry Equipments Materia
l 1 $2,200.00 $2,200.00
Tiles and Carpet Materia
l 1 $1,800.00 $1,800.00
Main gate Materia
l 1 $1,145.00 $1,145.00
Fences Materia
l 1 $945.00 $945.00
Gardening tools Materia
l 1 $650.00 $650.00
Mailboxes Materia
l 1 $1,000.00 $1,000.00
Cameras Materia
l 1 $1,600.00 $1,600.00
Fire Extinguishers Materia
l 1 $2,000.00 $2,000.00
Bathroom Equipments Materia
l 1 $12,000.00 $12,000.00
Kitchen Appliances Materia
l 1 $16,500.00 $16,500.00
Furniture and Fixtures Materia
l 1 $17,000.00 $17,000.00
Fans and Lights Materia
l 1 $3,500.00 $3,500.00
Carpentry Equipments Materia
l 1 $2,200.00 $2,200.00
Tiles and Carpet Materia
l 1 $1,800.00 $1,800.00
Main gate Materia
l 1 $1,145.00 $1,145.00
Fences Materia
l 1 $945.00 $945.00
Gardening tools Materia
l 1 $650.00 $650.00
Mailboxes Materia
l 1 $1,000.00 $1,000.00
Cameras Materia
l 1 $1,600.00 $1,600.00
Fire Extinguishers Materia
l 1 $2,000.00 $2,000.00
Bathroom Equipments Materia
l 1 $12,000.00 $12,000.00
Kitchen Appliances Materia
l 1 $16,500.00 $16,500.00
Furniture and Fixtures Materia
l 1 $17,000.00 $17,000.00
Fans and Lights Materia
l 1 $3,500.00 $3,500.00
8PROJECT CHARTER
Air Conditioners Materia
l 1 $11,000.00 $11,000.00
Room Heaters Materia
l 1 $10,000.00 $10,000.00
The time phase budget of the project of Construction of Residential Complex in
Queensland, Australia is given below,
May 2018 June 2018 July 2018 August 2018
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
$300,000.00
$350,000.00
$66,660.00 $71,100.00
$154,510.00
$36,730.00
$66,660.00
$137,760.00
$292,270.00
$329,000.00
Cost Cumulative Cost
Stakeholder List
The stakeholders of the project of Construction of Residential Complex in Queensland,
Australia can be divided into three levels,
Steering Committee Investors, Clients
Managerial Level Contractor, Project Manager
Operational Level Project team members including planner, budgeter, workers, designer,
and architect.
Air Conditioners Materia
l 1 $11,000.00 $11,000.00
Room Heaters Materia
l 1 $10,000.00 $10,000.00
The time phase budget of the project of Construction of Residential Complex in
Queensland, Australia is given below,
May 2018 June 2018 July 2018 August 2018
$0.00
$50,000.00
$100,000.00
$150,000.00
$200,000.00
$250,000.00
$300,000.00
$350,000.00
$66,660.00 $71,100.00
$154,510.00
$36,730.00
$66,660.00
$137,760.00
$292,270.00
$329,000.00
Cost Cumulative Cost
Stakeholder List
The stakeholders of the project of Construction of Residential Complex in Queensland,
Australia can be divided into three levels,
Steering Committee Investors, Clients
Managerial Level Contractor, Project Manager
Operational Level Project team members including planner, budgeter, workers, designer,
and architect.
9PROJECT CHARTER
Limits and Exclusions
Limits: The project is limited to the implication of the construction project management
operations.
Exclusions: The communication management plan, risk plan, and change management
plan are excluded from the project.
Assumptions and Constraints
Assumptions:
• All required resources (human and material) would be available for the completion of the
project.
• The project team would work in harmony with each other for the project completion.
Constraints:
• The time, budget, weather conditions, and quality of the raw materials are the constraints
on which the success of the project would depend.
• Government approval is based on the standards set for building construction by WHS.
Project Approval Requirements
The project approval requirements for the project of Construction of Residential Complex in
Queensland, Australia include,
Government approval is based on the standards set for building construction by WHS
Completion of the Project in the estimated time, budget, and quality
Assigned Project Manager: Sign off
<<name of the student>>
Limits and Exclusions
Limits: The project is limited to the implication of the construction project management
operations.
Exclusions: The communication management plan, risk plan, and change management
plan are excluded from the project.
Assumptions and Constraints
Assumptions:
• All required resources (human and material) would be available for the completion of the
project.
• The project team would work in harmony with each other for the project completion.
Constraints:
• The time, budget, weather conditions, and quality of the raw materials are the constraints
on which the success of the project would depend.
• Government approval is based on the standards set for building construction by WHS.
Project Approval Requirements
The project approval requirements for the project of Construction of Residential Complex in
Queensland, Australia include,
Government approval is based on the standards set for building construction by WHS
Completion of the Project in the estimated time, budget, and quality
Assigned Project Manager: Sign off
<<name of the student>>
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT CHARTER
<<name of the student>>
Project Manager
<<name of the student>>
Project Manager
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.