This document provides a detailed overview of the Equipment Cleaning Service Project Implementation. It includes a Gantt Project Structure, Outline Budget Template, Importance for Project Closure and Post-Implementation Phase, Summarisation of BSC, and Issues faced when Project Closure is not performed.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
Equipment Cleaning Service Project Implementation
Name of the Student
Name of the University
Author’s note
Equipment Cleaning Service Project Implementation
Name of the Student
Name of the University
Author’s note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
Table of Contents
1. Introduction..................................................................................................................................2
2. Summarising of the Gantt Project Structure................................................................................3
3. Outline Budget Template.............................................................................................................5
4. Importance for Project Closure and Post-Implementation Phase................................................6
5. Summarisation of BSC................................................................................................................8
6. Issues faced when Project Closure is not performed...................................................................8
Bibliography..................................................................................................................................10
Table of Contents
1. Introduction..................................................................................................................................2
2. Summarising of the Gantt Project Structure................................................................................3
3. Outline Budget Template.............................................................................................................5
4. Importance for Project Closure and Post-Implementation Phase................................................6
5. Summarisation of BSC................................................................................................................8
6. Issues faced when Project Closure is not performed...................................................................8
Bibliography..................................................................................................................................10
2EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
1. Introduction
The different tools based on project planning are:
Gantt Chart – The tool of project management would help in providing a graphic form
of schedule based on planning and controlling of the project based on equipment cleaning. This
tool will aid in the planning of activities such as development of a project plan, planning
implementation, actual conduction of cleaning activities and closure of project.
Work Breakdown Structure – This tool would help in defining a formal hierarchical
decomposition of activities. This tool would help in defining the entire scope of the equipment
cleaning project. This tool would also divide each of the project deliverables and work of the
project based on small kind of manageable components.
1. Introduction
The different tools based on project planning are:
Gantt Chart – The tool of project management would help in providing a graphic form
of schedule based on planning and controlling of the project based on equipment cleaning. This
tool will aid in the planning of activities such as development of a project plan, planning
implementation, actual conduction of cleaning activities and closure of project.
Work Breakdown Structure – This tool would help in defining a formal hierarchical
decomposition of activities. This tool would help in defining the entire scope of the equipment
cleaning project. This tool would also divide each of the project deliverables and work of the
project based on small kind of manageable components.
3EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
2. Summarising of the Gantt Project Structure
ID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 Equipment
Cleaning Service
Project
67 days Wed
16-01-19
Thu
18-04-19
1 1 Start 1 day Wed 16-01-19Wed 16-01-19
2 2 Project
Initiation and
de fining
obje ctive s
7 days Thu
17-01-19
Fri
25-01-19
3 2.1 Defining of
project plan
and setting of
objectives
2 days Thu
17-01-19
Fri 18-01-19
4 2.2 Determination
of the project
budget
5 days Mon
21-01-19
Fri 25-01-19
5 3 Planning for
Implementation
of Cle aning
works
17 days Mon
28-01-19
Tue
19-02-19
6 3.1 Outlining the
details of
project
implementation
13 days Mon
28-01-19
Wed
13-02-19
7 3.2 Planning of
deployment of
manual staff
4 days Thu
14-02-19
Tue
19-02-19
8 4 Conduction of
Cleaning
activity
25 days We d
20-02-19
Tue
26-03-19
9 4.1 The cleaning
equipment are
deployed
2 days Wed
20-02-19
Thu
21-02-19
10 4.2 Conduction of
equipment
cleaning
service
23 days Fri 22-02-19Tue
26-03-19
11 5 Final Closure of
the Proje ct
17 days We d
27-03-19
Thu
18-04-19
12 5.1 Placing and
fitting of
cleaned
equipments
10 days Wed
27-03-19
Tue
09-04-19
13 5.2 Gaining
feedbacks
from the
Company
7 days Wed
10-04-19
Thu
18-04-19
14 6 Stop 0 days Thu 18-04-19Thu 18-04-19 18-04
07-01 28-01 18-02 11-03 01-04 22-04 13-05
01 January 21 February 11 April
(Fig 1: Gantt Project Structure of Equipment Cleaning Project)
(Source: Created by author)
2. Summarising of the Gantt Project Structure
ID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 Equipment
Cleaning Service
Project
67 days Wed
16-01-19
Thu
18-04-19
1 1 Start 1 day Wed 16-01-19Wed 16-01-19
2 2 Project
Initiation and
de fining
obje ctive s
7 days Thu
17-01-19
Fri
25-01-19
3 2.1 Defining of
project plan
and setting of
objectives
2 days Thu
17-01-19
Fri 18-01-19
4 2.2 Determination
of the project
budget
5 days Mon
21-01-19
Fri 25-01-19
5 3 Planning for
Implementation
of Cle aning
works
17 days Mon
28-01-19
Tue
19-02-19
6 3.1 Outlining the
details of
project
implementation
13 days Mon
28-01-19
Wed
13-02-19
7 3.2 Planning of
deployment of
manual staff
4 days Thu
14-02-19
Tue
19-02-19
8 4 Conduction of
Cleaning
activity
25 days We d
20-02-19
Tue
26-03-19
9 4.1 The cleaning
equipment are
deployed
2 days Wed
20-02-19
Thu
21-02-19
10 4.2 Conduction of
equipment
cleaning
service
23 days Fri 22-02-19Tue
26-03-19
11 5 Final Closure of
the Proje ct
17 days We d
27-03-19
Thu
18-04-19
12 5.1 Placing and
fitting of
cleaned
equipments
10 days Wed
27-03-19
Tue
09-04-19
13 5.2 Gaining
feedbacks
from the
Company
7 days Wed
10-04-19
Thu
18-04-19
14 6 Stop 0 days Thu 18-04-19Thu 18-04-19 18-04
07-01 28-01 18-02 11-03 01-04 22-04 13-05
01 January 21 February 11 April
(Fig 1: Gantt Project Structure of Equipment Cleaning Project)
(Source: Created by author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
0 - Equipment Cleaning Service Project
1 - Start
2 - Project Initiation and defining objectives
2.1 - Defining of project plan and setting of objectives
2.2 - Determination of the project budget
3 - Planning for Implementation of Cleaning works
3.1 - Outlining the details of project implementation
3.2 - Planning of deployment of manual staff
4 - Conduction of Cleaning activity
4.1 - The cleaning equipment are deployed
4.2 - Conduction of equipment cleaning service
5 - Final Closure of the Project
5.1 - Placing and fitting of cleaned equipments
5.2 - Gaining feedbacks from the Company
6 - Stop
(Fig 2: Work Breakdown Structure of Equipment Cleaning Project)
(Source: Created by author)
0 - Equipment Cleaning Service Project
1 - Start
2 - Project Initiation and defining objectives
2.1 - Defining of project plan and setting of objectives
2.2 - Determination of the project budget
3 - Planning for Implementation of Cleaning works
3.1 - Outlining the details of project implementation
3.2 - Planning of deployment of manual staff
4 - Conduction of Cleaning activity
4.1 - The cleaning equipment are deployed
4.2 - Conduction of equipment cleaning service
5 - Final Closure of the Project
5.1 - Placing and fitting of cleaned equipments
5.2 - Gaining feedbacks from the Company
6 - Stop
(Fig 2: Work Breakdown Structure of Equipment Cleaning Project)
(Source: Created by author)
5EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
The Gantt Structure helps in defining the entire outline of the project. In this outline the
initiation phase of the project is defined. Each objectives are set for the project initiation. After a
proper project planning has been implemented, the outlining of the details of project deployment
have been made. The conduction of cleaning of equipment have been introduced after each of the
previous stages have been completed. After the cleaning procedures have been implemented,
each of the cleaned equipment would be properly put in place and thus feedback would be gained
from the company officials.
3. Outline Budget Template
Total Cost for the project
Planning for implementation of cleaning 3960
Conduction of cleaning activity 6270
Total Cost for the project 10230
(Fig 3: Budget Structure of Equipment Cleaning Project)
(Source: Created by author)
The Gantt Structure helps in defining the entire outline of the project. In this outline the
initiation phase of the project is defined. Each objectives are set for the project initiation. After a
proper project planning has been implemented, the outlining of the details of project deployment
have been made. The conduction of cleaning of equipment have been introduced after each of the
previous stages have been completed. After the cleaning procedures have been implemented,
each of the cleaned equipment would be properly put in place and thus feedback would be gained
from the company officials.
3. Outline Budget Template
Total Cost for the project
Planning for implementation of cleaning 3960
Conduction of cleaning activity 6270
Total Cost for the project 10230
(Fig 3: Budget Structure of Equipment Cleaning Project)
(Source: Created by author)
6EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
Year of Project
year 0 year1 year 2 year 3 year 4 year 5 TOTALS
Net economic benefit $0.00 $7,500.00 $7,500.00 $7,500.00 $7,500.00 $7,500.00
Discount Rate 8% 1 0.9259 0.8573 0.7938 0.7350 0.6806
PV Of Benefits $0.00 $6,944.44 $6,430.04 $5,953.74 $5,512.72 $5,104.37
NPV of all BENEFITS $0.00 $6,944.44 $13,374.49 $19,328.23 $24,840.95 $29,945.33 $94,433.43
One Time Costs $10,230.00
Recurring Costs $0.00 $400.00 $400.00 $400.00 $400.00 $400.00
Discount Rate 8% 1.0000 0.9259 0.8573 0.7938 0.7350 0.6806
PV Of Recurring Costs $0.00 $370.37 $342.94 $317.53 $294.01 $272.23
NPV Of All Costs $10,230.00 $10,600.37 $10,943.31 $11,260.84 $11,554.85 $11,827.08 $66,416.45
Overall NPV $28,016.98
(Fig 4: Budget Structure of Equipment Cleaning Project)
(Source: Created by author)
Overall ROI = (Overall NPV / NPV Of All Costs 0.42
Break-Even Analysis
Yearly NPV Cash Flow $0.00 $6,574.07 $6,087.11 $5,636.21 $5,218.71 $4,832.14
Overall NPV Cash Flow $10,230.00 ($3,655.93) $2,431.18 $8,067.39 $13,286.10 $18,118.24
Project break-even occurs between years 2 and 3
Use 1st year of positive cash flow to calculate break-even fraction 2.4314 years
(Fig 5: Budget Structure of Equipment Cleaning Project)
(Source: Created by author)
4. Importance for Project Closure and Post-Implementation Phase
The planning for the closure of the project would be important as it would be helpful for
the final detailing of the entire project. It would also ensure that the entire project has been
completed as per the initial deliverables and set objectives.
Year of Project
year 0 year1 year 2 year 3 year 4 year 5 TOTALS
Net economic benefit $0.00 $7,500.00 $7,500.00 $7,500.00 $7,500.00 $7,500.00
Discount Rate 8% 1 0.9259 0.8573 0.7938 0.7350 0.6806
PV Of Benefits $0.00 $6,944.44 $6,430.04 $5,953.74 $5,512.72 $5,104.37
NPV of all BENEFITS $0.00 $6,944.44 $13,374.49 $19,328.23 $24,840.95 $29,945.33 $94,433.43
One Time Costs $10,230.00
Recurring Costs $0.00 $400.00 $400.00 $400.00 $400.00 $400.00
Discount Rate 8% 1.0000 0.9259 0.8573 0.7938 0.7350 0.6806
PV Of Recurring Costs $0.00 $370.37 $342.94 $317.53 $294.01 $272.23
NPV Of All Costs $10,230.00 $10,600.37 $10,943.31 $11,260.84 $11,554.85 $11,827.08 $66,416.45
Overall NPV $28,016.98
(Fig 4: Budget Structure of Equipment Cleaning Project)
(Source: Created by author)
Overall ROI = (Overall NPV / NPV Of All Costs 0.42
Break-Even Analysis
Yearly NPV Cash Flow $0.00 $6,574.07 $6,087.11 $5,636.21 $5,218.71 $4,832.14
Overall NPV Cash Flow $10,230.00 ($3,655.93) $2,431.18 $8,067.39 $13,286.10 $18,118.24
Project break-even occurs between years 2 and 3
Use 1st year of positive cash flow to calculate break-even fraction 2.4314 years
(Fig 5: Budget Structure of Equipment Cleaning Project)
(Source: Created by author)
4. Importance for Project Closure and Post-Implementation Phase
The planning for the closure of the project would be important as it would be helpful for
the final detailing of the entire project. It would also ensure that the entire project has been
completed as per the initial deliverables and set objectives.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
The Post Implementation Review (PIR) would be conducted based on the completion of
the project. This would ensure that there would not be any kind of improvements and that the
project is successfully completed.
The two ways in which post-implementation review could enable project managers for
improving future projects are:
With the conduction of a thorough and timely PIR, it would help in learning of lessons
and thus help in identification of shortfalls.
The PIR would also help in making of final improvements within the systems.
The Post Implementation Review (PIR) would be conducted based on the completion of
the project. This would ensure that there would not be any kind of improvements and that the
project is successfully completed.
The two ways in which post-implementation review could enable project managers for
improving future projects are:
With the conduction of a thorough and timely PIR, it would help in learning of lessons
and thus help in identification of shortfalls.
The PIR would also help in making of final improvements within the systems.
8EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
5. Summarisation of BSC
A Balanced Scorecard (BCS) that would include Key Performance Indicators (KPIs)
within the four categories within the project scenario are:
Financial: The financial perspective would view the financial performance of the
organisation and also consider the use of financial resources for the project. The impact
of Fiscal Metric as a part of KPI would be helpful for the evaluation of the entire cleaning
costs and preservation of assets.
Stakeholder or Customer: From this perspective, the organisational performance would
be viewed from the perspective of stakeholders or customers. The customer satisfaction
metric would be used for ensuring the satisfaction of customers based on a scale of 1 to
10.
Internal Processes: The internal processes based on the cleaning project would be
helpful for maintaining the efficiency and quality of the cleaning services. The
appearance matrix would be able to scale the services based on a scale of 1 to 10. This
would depend upon satisfaction and approval from the company officials.
Organizational Capacity: This perspective would be able to view the performance of
the organisation based on human capital, culture and other capacities. The sanitizing
metric could be used for the creation of an average score within the perspective of
healthiness.
5. Summarisation of BSC
A Balanced Scorecard (BCS) that would include Key Performance Indicators (KPIs)
within the four categories within the project scenario are:
Financial: The financial perspective would view the financial performance of the
organisation and also consider the use of financial resources for the project. The impact
of Fiscal Metric as a part of KPI would be helpful for the evaluation of the entire cleaning
costs and preservation of assets.
Stakeholder or Customer: From this perspective, the organisational performance would
be viewed from the perspective of stakeholders or customers. The customer satisfaction
metric would be used for ensuring the satisfaction of customers based on a scale of 1 to
10.
Internal Processes: The internal processes based on the cleaning project would be
helpful for maintaining the efficiency and quality of the cleaning services. The
appearance matrix would be able to scale the services based on a scale of 1 to 10. This
would depend upon satisfaction and approval from the company officials.
Organizational Capacity: This perspective would be able to view the performance of
the organisation based on human capital, culture and other capacities. The sanitizing
metric could be used for the creation of an average score within the perspective of
healthiness.
9EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
6. Issues faced when Project Closure is not performed
When the closure of project is not performed, there might be some issues that
could be faced. These include:
Payment Issues – There might be some kind of payment issues in relation to the
equipment cleaning project.
Feedback Analysis – Without a proper closure of project, feedback from the
company officials cannot be gained.
6. Issues faced when Project Closure is not performed
When the closure of project is not performed, there might be some issues that
could be faced. These include:
Payment Issues – There might be some kind of payment issues in relation to the
equipment cleaning project.
Feedback Analysis – Without a proper closure of project, feedback from the
company officials cannot be gained.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
Bibliography
Chou, H.W., Lin, Y.H., Lu, H.S., Chang, H.H. and Chou, S.B., 2014. Knowledge sharing and
ERP system usage in post-implementation stage. Computers in Human Behavior, 33, pp.16-22.
Kunz, R.E., Siebert, J. and Mütterlein, J., 2016. Structuring objectives of media companies: a
case study based on value-focused thinking and the balanced scorecard. Journal of Media
Business Studies, 13(4), pp.257-275.
Lombardi, R., Caputo, A., Russo, G. and Formisano, V., 2015. Management control of
contractual networks: the business network scorecard. International Journal of Applied
Management Science, 7(4), pp.269-286.
Remington, K., & Pollack, J. (2016). Tools for complex projects. Routledge.
Bibliography
Chou, H.W., Lin, Y.H., Lu, H.S., Chang, H.H. and Chou, S.B., 2014. Knowledge sharing and
ERP system usage in post-implementation stage. Computers in Human Behavior, 33, pp.16-22.
Kunz, R.E., Siebert, J. and Mütterlein, J., 2016. Structuring objectives of media companies: a
case study based on value-focused thinking and the balanced scorecard. Journal of Media
Business Studies, 13(4), pp.257-275.
Lombardi, R., Caputo, A., Russo, G. and Formisano, V., 2015. Management control of
contractual networks: the business network scorecard. International Journal of Applied
Management Science, 7(4), pp.269-286.
Remington, K., & Pollack, J. (2016). Tools for complex projects. Routledge.
11EQUIPMENT CLEANING SERVICE PROJECT IMPLEMENTATION
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.