Running Head: PROJECT MANAGEMENT Bungalow Project: Cost and Quality Management Planning Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT Table of Contents Part A...............................................................................................................................................2 Part B...............................................................................................................................................3 Cost Planning...............................................................................................................................3 Quality Management Planning....................................................................................................7 References........................................................................................................................................9
2PROJECT MANAGEMENT Part A Quality on a project is defined as the measure of the outcomes that are generated from the project. Generally, the quality of the project is determined through the quality of the outcome generated but it also depends on the three main variables of the project – time, scope and cost (Mir & Pinnington, 2014). In other words, the quality of the project depends significantly on the time, scope and cost of the project and change in any one of these variables can affect the quality of the project significantly. For instance, if the cost of the project is increased, the quality of the project can also increase whereas if the scope is increased keeping cost and time same, the quality of the project will decrease. There are several tools and techniques that can be used for quality planning of a project. Some of these tools and techniques are listed as follows. Cause and Effect Diagram (Fishbone / Ishikawa Diagram) Pareto Charts Histograms Flowcharts Gantt Chart Control Charts Project cost has significant relationship with the quality of a project. With greater quality requirement, the cost increases whereas in case of low cost, the quality of the project decreases significantly (Kerzner & Kerzner, 2017). Again, poor quality of a project may also increase the cost of a project. For instance, in a project in spite of investing the project amount, the quality of
3PROJECT MANAGEMENT the project is poor and hence, the project has to be redone / modified that will further increase the cost of the project. Part B Cost Planning In the given project, there are two different types of costs involved – material and plant costs and human labour costs (Schwalbe, 2015). The human labour costs are determined using the work breakdown structure and bottom up estimation technique as shown in the following table. WBSTask NameDurationResource NamesCost 0Bungalow Project60 wks$251,460.00 1Preliminary51 wks$193,950.00 1.1Design Structure2 wksTradesman$3,600.00 1.2Appoint Project Manager48 wksTradesman [50%]$43,200.00 1.3Modify Changes1 wkTradesman [25%]$450.00 1.4Conduct Soil Test2 wks$0.00 1.5Receive Client Design Approval1 wkTradesman [50%]$900.00 1.6Draw Plans and Schedules2 wksTradesman$3,600.00 1.7Attain Engineer Certification2 wks$0.00 1.8Submit Plans to Local Council6 wks$0.00 1.9Prepare and Submit Application to QBCC1 wkTradesman$1,800.00 1.10Select Insurance Package2 wksTradesman$3,600.00 1.11Engage the Project Management Team38 wksTradesman [200%]$136,800.00 2Site49 wks$4,200.00 2.1Erect Temporary Fencing1 wk$0.00 2.2Install Portaloo to Site48 wks$0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT 2.3Install Temporary Power Pole1 wk$0.00 2.4Install Water Point1 wk$0.00 2.5Power and Water Construction Costs1 wkLabourers[50%],Tradesman [50%]$1,500.00 2.6Clear Ground1 wkTradesman [20%]$360.00 2.7Set Out the Dwelling1 wkLabourers[50%],Tradesman [50%]$1,500.00 2.8Dig Foundations3 wks$0.00 2.9Foundation Inspection1 wkLabourers [20%]$240.00 2.10Install Trench Mesh1 wkLabourers[20%],Tradesman [20%]$600.00 2.11Pour Footings1 wk$0.00 3Building (To Lock Up)13.5 wks$33,630.00 3.1Erect Double Brick External Wall System3 wksLabourers, Tradesman$9,000.00 3.2Door and Window Frames1 wkLabourers[50%],Tradesman [50%]$1,500.00 3.3Glazing1 wk$0.00 3.4Install Floor Joists1 wkTradesman [50%]$900.00 3.5Erect internal timber frame, floors and walls3 wksLabourers[50%],Tradesman [50%]$4,500.00 3.6Install roof trusses and battens3 wksTradesman [80%]$4,320.00 3.7Install Roof Rail2.5 wksLabourers[20%],Tradesman [20%]$1,500.00 3.8Ceiling Joists1 wkLabourers[50%],Tradesman [50%]$1,500.00 3.9Fit T & G Strip Flooring1 wkLabourers[75%],Tradesman [75%]$2,250.00 3.10Install Guttering1 wkTradesman [20%]$360.00 3.11Fit Roof Tiles2 wksLabourers, Tradesman$6,000.00 3.12Rough in Electrical1 wkTradesman [50%]$900.00 3.13Rough in Plumbing1 wkTradesman [50%]$900.00 4Building (Handover)10 wks$19,680.00 4.1Install Insulation1 wkLabourers [50%]$600.00 4.2Plaster Ceiling1 wk$0.00 4.3Plaster Walls1 wk$0.00
5PROJECT MANAGEMENT 4.4Crane Lift Shell into Place0.2 wks$0.00 4.5Install and Connect Swimming Pool Shell / Pump3 wks$0.00 4.6Conduct Second Fix2 wksLabourers, Tradesman$6,000.00 4.7Tiles4 wksTradesman$7,200.00 4.8Paint Walls and Ceilings2 wks$0.00 4.9Fit Off Electrical Points and Appliances2 wks$0.00 4.10Fit Off Plumbing Points2 wks$0.00 4.11Install Downpipes and Connect to Storm Water2 wksTradesman [10%]$360.00 4.12Landscape the Site3 wksLabourers[50%],Tradesman [50%]$4,500.00 4.13Connection to Sewer1 wkTradesman [10%]$180.00 4.14Connection to Water Supply1 wkTradesman [10%]$180.00 4.15Connection to Power Supply1 wkTradesman [20%]$360.00 4.16Clean Site1 wkLabourers [25%]$300.00 4.17Client Handover1 wk$0.00 4.18Mortgage Holder Inspection1 wk$0.00 Hence, the total labour cost based on the most likely durations for the project is found to be$251,460. Again, for the material and plant costs, using three point estimation technique, the detailed data is shown in the following table. Activity# Units UnitPlantMaterial/ FC Total CostOptimistic CostPessimistic CostMost likely CostMean 1 1.12$ 2,250.00 --$ 4,500.00 $3,600.00$ 6,750.00 $ 4,500.00 $ 4,950.00 1.248$ 1,350.00 --$ 64,800.00 $ 51,840.00 $ 97,200.00 $ 64,800.00 $ 71,280.00 1.30.25$ 2,250.00 --$562.50$450.00$ 843.75 $562.50$618.75 1.41$ 450.00 -$ 450.00 $900.00$720.00$ 1,350.00 $900.00$990.00 1.50.25$ 2,250.00 --$562.50$450.00$ 843.75 $562.50$618.75 1.60.5$ 2,250.00 --$ 1,125.00 $900.00$ 1,687.50 $ 1,125.00 $ 1,237.50 1.71$ - $ 650.00 -$650.00$520.00$ 975.00 $650.00$715.00 1.86$ 700.00 -$ 700.00 $ 4,900.00 $3,920.00$ 7,350.00 $ 4,900.00 $ 5,390.00
7PROJECT MANAGEMENT 4.121$ 1,875.00 -$ 1,800.00 $ 3,675.00 $2,940.00$ 5,512.50 $ 3,675.00 $ 4,042.50 4.130.1$ 2,250.00 -$ 400.00 $625.00$500.00$ 937.50 $625.00$687.50 4.140.1$ - --$-$-$-$-$- 4.150.2$ 2,250.00 --$450.00$360.00$ 675.00 $450.00$495.00 4.160.25$ 1,500.00 --$375.00$300.00$ 562.50 $375.00$412.50 4.171$ - --$-$-$-$-$- 4.181$ - --$-$-$-$- TOTA L $ 276,514.38$221,211.50$414,771.56$276,514.38$ 304,165.81 Considering the most likely outcome for the project, the total project material cost is estimated to be$304,165. Hence, the total estimated cost for the project considering the most likely situation is $ (251,460 + 304,165) =$555,625. Quality Management Planning This project is based on the construction of a bungalow based on the requirements as set by the client. While there are structural and design specifications already provided for the bungalow along with the delivery, the client has requested quote for cost of the project that will also ensure sufficient quality of the outcome (Chen & Luo, 2014). In order to deliver suitable quality of the bungalow, a quality management planning is required. The objectives of the quality management plan are as follows. To identify appropriate construction elements that will ensure high quality of the bungalow To identify the costs of materials and labour required for delivery of high quality project within the deadline To identify the roles of project team members in quality management of the project To develop quality standards for the project
8PROJECT MANAGEMENT In order to ensure the quality for the project outcomes, it is first required to set specific quality standards including quality of construction, design and final delivery of the bungalow. Again, after development of the quality standards, it is required to ensure these standards are applied to the project (Hornstein, 2015). For this, quality monitoring plan needs to be developed in which, specific stakeholders are assigned to monitor the quality of the project and compliance with the quality standards set for the project. Finally, at the end of the project, detailed quality testing is required for reviewing the quality of outcome of the project. If it is found that the expected quality standard is not met, the project manager can order to reopen the project and work on improving the project quality. However, that will require additional costs and hence, it is not desired to deliver poor quality outcome in the project.
9PROJECT MANAGEMENT References Chen, L., & Luo, H. (2014). A BIM-based construction quality management model and its applications.Automation in construction,46, 64-73. Crawford, J. K. (2014).Project management maturity model. Auerbach Publications. Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute. Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017).Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press. Harrison, F., &Lock,D.(2017).Advancedprojectmanagement:astructuredapproach. Routledge. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Ingason, H. T. (2015). Best project management practices in the implementation of an ISO 9001 quality management system.Procedia-Social and Behavioral Sciences,194, 192-200. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Lock, D. (2017).The essentials of project management. Routledge.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217. Schwalbe, K. (2015).Information technology project management. Cengage Learning. Smith,P.(2014).BIM&the5Dprojectcostmanager.Procedia-SocialandBehavioral Sciences,119, 475-484.