This paper reflects on the development of a simulation game for the school of nursing within the GU university. It includes project scope, objectives, deliverables, milestones, technical requirements, schedule baseline, work breakdown structure, change management plan, communication management plan, cost baseline human resource plan, procurement management plan, quality baseline and management plan.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Project management: Online simulation game
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
Table of Contents
Overview..........................................................................................................................................2
1. Project scope................................................................................................................................2
1.1 Project objectives...................................................................................................................2
1.2 Project deliverables................................................................................................................3
1.3 Milestones with finishing dates.............................................................................................3
1.4 Technical requirements..........................................................................................................4
2. Schedule baseline and work breakdown structure.......................................................................5
2.1 Gantt chart.............................................................................................................................5
2.2 Work breakdown structure....................................................................................................7
2.3 Network diagram...................................................................................................................9
3. Change management plan..........................................................................................................10
4. Communication management plan............................................................................................11
5. Cost baseline human resource plan............................................................................................12
5.1 Human resource plan...........................................................................................................12
6. Procurement management plan..................................................................................................14
7. Quality baseline and management plan.....................................................................................15
8. Risk management plan including risk register...........................................................................16
9. Project closure...........................................................................................................................18
Bibliography..................................................................................................................................19
Appendices....................................................................................................................................22
Appendix 1: Parametric estimation of budget...........................................................................22
Appendix 2: Three-point estimation method for budget estimation..........................................25
Document Page
2
PROJECT MANAGEMENT
Overview
The paper mainly reflects on the development of a simulation game for the school of
nursing within the GU university. The organization aims to properly develop an online
simulation game that must include proper simulation of nursing where the nurses generally
practices various types of administering related medications, care for development of the
patients, recording patients’ conditions as well as proper communication with the doctors. In
addition to this, the site generally includes proper chat utility with the help of portal of
videoconferencing for proper collaboration. Moreover, this will helps in providing proper related
work for a number of uses in order to give proper online training as one of the important parts of
the project. There are a number of repository requirement for the purpose of game learning for
properly guiding the Iwi/Maori inclusion. It is found that in this paper mixed method of waterfall
as well as scrum is mainly used and it is assumed that the project will get accomplished within 6
months of time within the budget of 120k to 250k.
1. Project scope
1.1 Project objectives
The project objectives are mainly listed below:
ï‚· To develop an online simulation game for the school of nursing in GU university
ï‚· To provide the facility of managing intravenous lines, recording condition of the patient
as well as for the purpose of communication
ï‚· To provide the facility of online training as well as real time utility and
videoconferencing portal for collaboration
Document Page
3
PROJECT MANAGEMENT
1.2 Project deliverables
The deliverables of the online simulation game are mainly divided into tangible as well as
intangible deliverables which are listed below:
ï‚· Tangible deliverables
ï‚· Financial report
ï‚· Feasibility report
ï‚· Project progress report
Intangible deliverables
ï‚· Design of script, layout as well as character
ï‚· Coding and modelling
ï‚· Testing report
ï‚· Technical interpretation
ï‚· Proper collaboration
1.3 Milestones with finishing dates
Milestone Completion date
Milestone 1: Getting approval for the
project
23-10-19
Milestone 2: Completion of the planning
phase
14-11-19
Milestone 3: Completion of pre-
production phase
30-12-20
Milestone 4: Completion of production 21-02-20
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
PROJECT MANAGEMENT
phase
Milestone 5: Completion of alpha version
and beta testing
6-03-20
1.4 Technical requirements
The different types of technical requirements which are needed for properly developing
the simulation game mainly listed in the table below:
Serial No. Technical needs Additional information
1 Desktop technologies Motif and common desktop environment
2 Mobile technologies React native in order to develop the cross
platform mobile application
Unity for game engine development as
well as for the readiness of virtual reality
3 Mobile platform iOS: 11.0-12.2
Android: 5.1
4 Operating system Ubuntu 16
5 Database MySQL 8.0
6 Security SSL
7 Testing framework Beta testing, Alpha testing, Unit testing as
well as automation testing
8 Infrastructure provider Amazon web services
Document Page
5
PROJECT MANAGEMENT
2. Schedule baseline and work breakdown structure
2.1 Gantt chart
Gantt charts are quite useful for proper scheduling as well as for the purpose of
effectively planning the project and further they also help in assessing the duration that is mainly
required for developing the game for the nursing students. In addition to this, the Gantt chart that
is prepared helps in showcasing the resources that are assigned to (Kerzner 2017). Moreover,
they are also helpful in properly managing the project dependencies between the various project
tasks. It is analyzed that Scrum as well as waterfall methodology is mainly used while preparing
the Gantt chart. It is reflected that before going to the next phase of the project, it is quite
important to finish the earlier phase and therefore each of the project phases are executed
sequentially as per the waterfall methodology (Hornstein 2015). In addition to this, SCRUM
methodology is also utilized while developing the simulation game for the nursing students that
helps in embracing iterative as well as various types of incremental practices which generally
helps in finishing the work effectively such that the online simulation game can be delivered
frequently. The iterations within the project is reflected in the pre-production, production as well
as testing phase such that the online simulation game can be successfully created in sections
(Badewi 2016). Due to the use of SCRUM, proper quality can be maintained during the
development procedure other than the utilization of proper sequential activity and moreover, the
project needs as well as requirements can be managed quite effectively by properly prioritizing
and as a result, the cost which is required for the purpose of online simulation game development
generally reduces. The Gantt chart by utilizing the mixed methodology is mainly reflected
below:
Document Page
6
PROJECT MANAGEMENT
Figure 1: Gantt chart
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
2.2 Work breakdown structure
It helps in offering proper visual representation of the project deliverable including the
milestones (Ong, Wang and Zainon 2016). The key milestones help in simplifying the entire
projects into smaller for managing the project groups. The WBS for the online simulation game
for nursing school is given below:
WBS Task Name
0 Development of online simulation game for school of nursing home
1 Initiation phase
1.1 Analyzing the reason of game development
1.2 Targeting the audience
1.3 Understanding the theme of the game
1.4 Undertaking feasibility study
M1 Milestone 1: Getting approval for the project
2 Planning phase
2.1 Analysis of the various types of requirements
2.1.1 Analysis of pricing
2.1.2 Analyzing different types of technical issue
2.2 Hiring stakeholders
2.3 Allocating budget to the project
M2 Milestone 2: Completion of the planning phase
3 Iteration 1: Pre-production phase
3.1 Designing the script
Document Page
8
PROJECT MANAGEMENT
3.1.1 Layout design
3.1.2 Designing the character
3.2 Design of screen
3.3 Designing the gameplay
3.4 Game engine
3.5 Prototype design
M3 Milestone 3: Completion of pre-production phase
4 Iteration 2: Production phase
4.1 Coding
4.2 Modelling
4.3 Texturing
4.4 Adding sound and images
4.5 Development of feature including chat utility and videoconferencing
M4 Milestone 4: Completion of production phase
5 Iteration 3: Alpha version and beta version
5.1 Alpha version
5.1.1 Alpha testing
5.1.2 Bug fixing
5.2 Beta version
5.2.1 Beta testing
M5 Milestone 5: Completion of alpha version and beta testing
Document Page
9
PROJECT MANAGEMENT
6 Closure phase
6.1 Post project review
6.2 Release of the simulation game
6.3 Stakeholder sign off
6.4 Documentation
M6 Milestone 6: Completion of closure phase
Development of online
simulation game for
school of nursing home
Initiation phase
Analyzing the reason
of game development
Targeting the
audience
Understnding the
theme of the game
Undertaking
feasiability study
Milestone 1: Getting
approval for the
project
Planning phase
Analysis of the various
types of requirements
Analysis of pricing
Analyzing different
types of technical
issue
Hiring stakeholders
Allocating budget to
the project
Milestone 2:
Completion of the
planning phase
Iteration 1:
Pre-production phase
Designing the script
Layout design
Designing the
character
Design of screen
Designing the
gameplay
Game engine
Prototype design
Milestone 3:
Completion of
pre-production
phase
Iteration 2: Production
phase
Coding
Modelling
Texturing
Adding sound and
images
Development of
feature including
chat utility and
videoconferencing
Milestone 4:
Completion of
production phase
Iteration 3: Alpha version
and beta version
Alpha version
Alpha testing
Bug fixing
Beta version
Beta testing
Milestone 5:
Completion of alpha
version and beta
testing
Closure phase
Post project review
Release of the
simulation game
Stakeholder sign off
Documentation
Milestone 6:
Competion of
closure phase
Figure 2: Work breakdown structure
(Source: Created by Author)
2.3 Network diagram
It graphically showcases the tasks, responsibilities as well as the entire flow of the project
work. It is found that the network diagram that is given below helps in proper planning,
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
PROJECT MANAGEMENT
controlling as well as organizing the projects with proper relationship so that the entire project
can be managed effectively (Chen et al. 2016).
Figure 3: Network diagram
(Source: Created by Author)
3. Change management plan
Serial number Changes needed Reason Impact on project
Document Page
11
PROJECT MANAGEMENT
1. Extending the project
accomplishment date as
the requirements that are
associated with the project
are not set properly.
This is because if
additional time is
getting by the team
members then can
analyze the needs
properly for
developing the
simulation game
effectively.
This generally have a
positive impact on
the project on the
project outcome but
the chances of
increasing the total
expenditure is quite
high.
2. As the present
stakeholders change their
minds then it is necessary
to incorporate new ideas
within the project and this
is needed to be done quite
impact for avoiding
negative impact on the
project.
If the stakeholders
do not work
effectively the rate
rework will get
incurred that further
increase the cost and
time of the project.
Changes within the
project is important
for developing the
game within the
nursing school
effectively for
providing all the
required facilities.
4. Communication management plan
Type of meeting Participants Purpose
Planning meeting
(Once- before the initiation
phase)
Team members The project manager and the
planner reflect the project
activities and the project aim
Document Page
12
PROJECT MANAGEMENT
so that the team members can
easily understood the main
motive of the project and can
be able to achieve its
effectively.
Daily meeting
(Every morning- 10.am to
10.30 am)
Team members The project manager asks the
issues that the team faces
while progressing with the
project and the team discuss
the current status of the
project. In addition to this, the
complexities which can
hinder the progress of the
project are also discussed so
that they can be mitigated.
Review meeting
After the completion of the
project
Project team Review is mainly done for
making sure that the activities
of design, development as
well as testing phase are
properly undertaken so that
the project work can get
finished on time.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13
PROJECT MANAGEMENT
5. Cost baseline human resource plan
5.1 Human resource plan
Stakeholders Work Cost/hr. Cost
Project manager 104 hrs. $ 13.00/hr. $1,352.00
Developer 96 hrs. $ 10.00/hr. $960.00
Application manager 136 hrs. $ 10.00/hr. $1,360.00
IT manager 168 hrs. $ 10.00/hr. $1,680.00
Designer 256 hrs. $ 9.00/hr. $2,304.00
Project planner 96 hrs. $ 9.00/hr. $864.00
Financial manager 112 hrs. $ 8.00/hr. $896.00
Requirement analysis 72 hrs. $ 8.00/hr. $576.00
Coder 112 hrs. $ 10.00/hr. $1,120.00
Tester 56 hrs. $ 9.00/hr. $504.00
Technical writer 40 hrs. $ 8.00/hr. $1,352.00
Document Page
14
PROJECT MANAGEMENT
September
2019
October 2019 November
2019
December
2019
January 2020 February
2020
March 2020
$ 0.00
$ 2,000.00
$ 4,000.00
$ 6,000.00
$ 8,000.00
$ 10,000.00
$ 12,000.00
$ 14,000.00
$ 16,000.00
Cost-baseline
Cumulative Cost
Figure 4: Cost baseline
(Source: Created by Author)
6. Procurement management plan
It is found that after the effective procurement process helps in ensuring proper process
efficiency within each stage of a procurement cycle within an organization that helps in
shortening the entire sourcing cycle times. The steps that are needed to be followed within the
entire procedure of procurement are as follows:
Requirement identification: This cycle generally gets started when any of the business
units within the entire organization generally requires proper services from the suppliers. In this
step, it is necessary to entail the identification as well as consolidation of the different business
units (Fleming 2019).
Evaluation of suppliers: In this step, the suppliers are determined and additionally this
specific process generally requires web search. In this step, the various suppliers are generally
Document Page
15
PROJECT MANAGEMENT
evaluated successfully (Schapper, Malta and Gilbert 2017). After the entire assessment gets
finished therefore the supplier’s helps in offering proper maximum value.
Negotiation of contracts: After the suppliers generally fulfill the entire needs within the
organization after the beginning of the contract procedure. It is found that the entire contracting
process is found to be important for the entire procedure of value creation as well as by
stimulating the collaboration.
Purchase of requisition: After the organization generally gets finalized within the entire
contract with the suppliers for raising the purchase requisition effectively. It is found that after
the PR gets approved then the team helps in releasing the entire purchase to the various suppliers
that document information (Kisomi, Solimanpur and Doniavi 2016).
Completion of payment procedure: After the PO is received then it is necessary to send
the invoice for properly mentioning the price. After the organization generally received the PO
then the procurement team matches for ensuring both the quantity as well as quality.
Auditing and receiving requested goods: It is found that based on the contractual as
well as payment terms therefore the supplier generally helps in delivering proper services as well
as goods and thus it is quite necessary for the nursing school to make sure such that the suppliers
met proper quality related expectation (De Araújo et al. 2017).
Maintenance of records and invoices: After the delivery, it is very much important for
effectively storing all the invoices for tracking the spending for managing the expenditure
categories in the organization.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16
PROJECT MANAGEMENT
7. Quality baseline and management plan
As per the plan of quality management, it generally helps in guiding both the program
manager as well as the various project personnel for executing the quality management as well as
different types of assurance activities within the program (Carvalho and Rabechini Junior 2015).
The main purpose of quality management plan helps in describing how the project quality gets
managed within the project lifecycle. It mainly assists in properly determining the various
procedures and policies. It is identified that while developing the online simulation game, the
quality of should be managed properly by utilizing effective strategies which are mainly
illustrated below:
Setting quality standards: It is very much important to determine as well as announce
various types of quality-based standards that are mainly needed to be followed for properly
executing the entire work of the project successfully (Kerzner 2017). Setting appropriate
standards of quality are helpful in managing the quality of the online simulation game.
Discovery quality needs: The quality needs that are discovered must be fulfilled by
checking the quality of the used hardware and software properly for avoiding various types of
quality related challenges in the project.
Using proper tools of quality management: It is necessary to utilize proper tools and
techniques for properly managing the quality of the project effectively. It is identified that in
order to manage the quality of online simulation game, it is quite important to use tools like
flowchart, control charts, histograms as well as finish bone diagram (Mullaly and Thomas 2016).
8. Risk management plan including risk register
Risk Impact Risk Register Probability Mitigation
Document Page
17
PROJECT MANAGEMENT
Methods
Schedule
slippage
Due to slippage
of project
schedule, the
chances of delay
within the entire
project are quite
high which
creates a number
of issues.
Medium Medium The schedule
must be managed
effectively for
avoiding the
issue of slippage
and thus the
problem of delay
can be avoided.
Improper design If testing is not
conducted
properly due to
improper
experience of
the designer then
it will create a
lot of issues in
developing the
online game
simulation.
High High Testing should
be conducted
properly with the
help of
experienced
team members
for properly
developing the
online simulation
game.
Budget
overshoot
If the project
budget gets
High High The problem of
financial
Document Page
18
PROJECT MANAGEMENT
overshoot then a
lot of financial
issues can hinder
the progress of
the project.
overshoot must
be resolved by
properly
managing the
budget of the
project quite
beneficially.
Lack of
resources
If the project
resources are not
properly
available then it
generally causes
delay in the
project.
Medium Medium It is quite
needed to
manage the
resources of the
project
effectively which
avoids delay in
the project.
9. Project closure
Stakeholders Sign off
Project manager <Please fill>
Developer <Please fill>
Application manager <Please fill>
IT manager <Please fill>
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19
PROJECT MANAGEMENT
Designer <Please fill>
Project planner <Please fill>
Financial manager <Please fill>
Requirement analysis <Please fill>
Coder <Please fill>
Tester <Please fill>
Technical writer <Please fill>
Document Page
20
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Carvalho, M.M.D. and Rabechini Junior, R., 2015. Impact of risk management on project
performance: the importance of soft skills. International Journal of Production Research, 53(2),
pp.321-340.
Carvalho, M.M.D. and Rabechini Junior, R., 2015. Impact of risk management on project
performance: the importance of soft skills. International Journal of Production Research, 53(2),
pp.321-340.
Chen, X., Chen, J., Wu, D., Xie, Y. and Li, J., 2016. Mapping the research trends by co-word
analysis based on keywords from funded project. Procedia Computer Science, 91, pp.547-555.
Conforto, E.C., Amaral, D.C., da Silva, S.L., Di Felippo, A. and Kamikawachi, D.S.L., 2016.
The agility construct on project management theory. International Journal of Project
Management, 34(4), pp.660-674.
De Araújo, M.C.B., Alencar, L.H. and de Miranda Mota, C.M., 2017. Project procurement
management: A structured literature review. International Journal of Project
Management, 35(3), pp.353-377.
Fleming, Q.W., 2019, January. Project procurement management: contracting, subcontracting,
teaming. Project Management Institute.
Document Page
21
PROJECT MANAGEMENT
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Huemann, M., Keegan, A. and Turner, R., 2018, September. Human resource management in the
project-oriented organization. Project Management Institute.
Kaiser, M.G., El Arbi, F. and Ahlemann, F., 2015. Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), pp.126-139.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Kisomi, M.S., Solimanpur, M. and Doniavi, A., 2016. An integrated supply chain configuration
model and procurement management under uncertainty: a set-based robust optimization
methodology. Applied Mathematical Modelling, 40(17-18), pp.7928-7947.
Mullaly, M. and Thomas, J., 2016. The Value of Project Management: Rethinking Project
Management Maturity and Fit. In Gower Handbook of Project Management (pp. 79-100).
Routledge.
Mullaly, M. and Thomas, J., 2016. The Value of Project Management: Rethinking Project
Management Maturity and Fit. In Gower Handbook of Project Management (pp. 79-100).
Routledge.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
22
PROJECT MANAGEMENT
Oakland, J.S. and Marosszeky, M., 2017. Total construction management: Lean quality in
construction project delivery. Routledge.
Ong, H.Y., Wang, C. and Zainon, N., 2016. Integrated earned value Gantt chart (EV-Gantt) tool
for project portfolio planning and monitoring optimization. Engineering Management
Journal, 28(1), pp.39-53.
Ramazani, J. and Jergeas, G., 2015. Project managers and the journey from good to great: The
benefits of investment in project management training and education. International Journal of
Project Management, 33(1), pp.41-52.
Schapper, P.R., Malta, J.N.V. and Gilbert, D.L., 2017. Analytical framework for the
management and reform of public procurement. In International handbook of public
procurement (pp. 119-136). Routledge.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on project
success and on the execution of business strategies. International Journal of Project
Management, 33(1), pp.53-66.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Document Page
23
PROJECT MANAGEMENT
Appendices
Appendix 1: Parametric estimation of budget
WBS Task Name Duration Resource Names Cost
0
Development of online
simulation game for
school of nursing home
6 mons $ 14,136.00
1 Initiation phase 1.15 mons $ 1,720.00
1.1
Analyzing the reason
of game development
5 days Requirement analysis $ 320.00
1.2
Targeting the
audience
5 days Project manager $ 520.00
1.3
Understanding the
theme of the game
6 days Project planner $ 432.00
1.4
Undertaking
feasibility study
7 days Financial manager $ 448.00
M1
Milestone 1: Getting
approval for the project
0 days $ 0.00
2 Planning phase 0.8 mons $ 1,840.00
2.1
Analysis of the
various types of
requirements
0.35 mons $ 704.00
2.1.1 Analysis of pricing 3 days Financial manager, Requirement $ 384.00
Document Page
24
PROJECT MANAGEMENT
analysis
2.1.2
Analyzing different
types of technical issue
4 days IT manager $ 320.00
2.2 Hiring stakeholders 5 days Project manager, Project planner $ 880.00
2.3
Allocating budget to
the project
4 days Financial manager $ 256.00
M2
Milestone 2:
Completion of the
planning phase
0 days $ 0.00
3
Iteration 1: Pre-
production phase
1.6 mons $ 4,264.00
3.1 Designing the script 0.5 mons $ 2,200.00
3.1.1 Layout design 4 days Designer $ 288.00
3.1.2
Designing the
character
6 days
Designer, IT manager, Software
requirements [1]
$ 1,912.00
3.2 Design of screen 5 days Designer $ 360.00
3.3
Designing the
gameplay
6 days Designer, IT manager $ 912.00
3.4 Game engine 4 days Designer $ 288.00
3.5 Prototype design 7 days Designer $ 504.00
M3 Milestone 3:
Completion of pre-
0 days $ 0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
25
PROJECT MANAGEMENT
production phase
4
Iteration 2:
Production phase
1.6 mons $ 5,040.00
4.1 Coding 10 days Coder $ 800.00
4.2 Modelling 7 days Application manager, Developer $ 1,120.00
4.3 Texturing 5 days Developer, IT manager $ 800.00
4.4
Adding sound and
images
4 days
Application manager, Coder,
Hardware requirement including
database server [1]
$ 1,840.00
4.5
Development of
feature including chat
utility and
videoconferencing
6 days Application manager $ 480.00
M4
Milestone 4:
Completion of production
phase
0 days $ 0.00
5
Iteration 3: Alpha
version and beta version
0.35 mons $ 504.00
5.1 Alpha version 0.25 mons $ 360.00
5.1.1 Alpha testing 2 days Tester $ 144.00
5.1.2 Bug fixing 3 days Tester $ 216.00
5.2 Beta version 0.1 mons $ 144.00
Document Page
26
PROJECT MANAGEMENT
5.2.1 Beta testing 2 days Tester $ 144.00
M5
Milestone 5:
Completion of alpha
version and beta testing
0 days $ 0.00
6 Closure phase 0.5 mons $ 768.00
6.1 Post project review 3 days Project manager $ 312.00
6.2
Release of the
simulation game
1 day Project planner $ 72.00
6.3 Stakeholder sign off 1 day Requirement analysis $ 64.00
6.4 Documentation 5 days Technical writer $ 320.00
M6
Milestone 6:
Completion of closure
phase
0 days $ 0.00
Appendix 2: Three-point estimation method for budget estimation
WB
S
Task Name Total cost Optimisti
c cost
Pessimistic
cost
Most likely
cost
Mean
0 Development of
online simulation
game for school
of nursing home
$14,136.0
0
$11,308.8
0
$21,204.00 $14,136.00 $15,549.6
0
1.1 Analyzing the
reason of game
$320.00 $256.00 $480.00 $320.00 $352.00
Document Page
27
PROJECT MANAGEMENT
development
1.2 Targeting the
audience
$520.00 $416.00 $780.00 $520.00 $572.00
1.3
Understanding the
theme of the
game
$432.00 $345.60 $648.00 $432.00 $475.20
1.4 Undertaking
feasibility study
$448.00 $358.40 $672.00 $448.00 $492.80
M1 Milestone 1:
Getting approval
for the project
$0.00 $0.00 $0.00 $0.00 $0.00
2 Planning phase $1,840.00 $1,472.00 $2,760.00 $1,840.00 $2,024.00
2.1 Analysis of
the various types
of requirements
$704.00 $563.20 $1,056.00 $704.00 $774.40
2.1.1 Analysis of
pricing
$384.00 $307.20 $576.00 $384.00 $422.40
2.1.2 Analyzing
different types of
technical issue
$320.00 $256.00 $480.00 $320.00 $352.00
2.2 Hiring
stakeholders
$880.00 $704.00 $1,320.00 $880.00 $968.00
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
28
PROJECT MANAGEMENT
2.3 Allocating
budget to the
project
$256.00 $204.80 $384.00 $256.00 $281.60
M2 Milestone 2:
Completion of the
planning phase
$0.00 $0.00 $0.00 $0.00 $0.00
3 Iteration 1:
Pre-production
phase
$4,264.00 $3,411.20 $6,396.00 $4,264.00 $4,690.40
3.1 Designing the
script
$2,200.00 $1,760.00 $3,300.00 $2,200.00 $2,420.00
3.1.1 Layout
design
$288.00 $230.40 $432.00 $288.00 $316.80
3.1.2 Designing
the character
$1,912.00 $1,529.60 $2,868.00 $1,912.00 $2,103.20
3.2 Design of
screen
$360.00 $288.00 $540.00 $360.00 $396.00
3.3 Designing the
gameplay
$912.00 $729.60 $1,368.00 $912.00 $1,003.20
3.4 Game engine $288.00 $230.40 $432.00 $288.00 $316.80
3.5 Prototype
design
$504.00 $403.20 $756.00 $504.00 $554.40
Document Page
29
PROJECT MANAGEMENT
M3 Milestone 3:
Completion of
pre-production
phase
$0.00 $0.00 $0.00 $0.00 $0.00
4 Iteration 2:
Production
phase
$5,040.00 $4,032.00 $7,560.00 $5,040.00 $5,544.00
4.1 Coding $800.00 $640.00 $1,200.00 $800.00 $880.00
4.2 Modelling $1,120.00 $896.00 $1,680.00 $1,120.00 $1,232.00
4.3 Texturing $800.00 $640.00 $1,200.00 $800.00 $880.00
4.4 Adding sound
and images
$1,840.00 $1,472.00 $2,760.00 $1,840.00 $2,024.00
4.5 Development
of feature
including chat
utility and
videoconferencin
g
$480.00 $384.00 $720.00 $480.00 $528.00
M4 Milestone 4:
Completion of
production phase
$0.00 $0.00 $0.00 $0.00 $0.00
5 Iteration 3:
Alpha version
$504.00 $403.20 $756.00 $504.00 $554.40
Document Page
30
PROJECT MANAGEMENT
and beta version
5.1 Alpha
version
$360.00 $288.00 $540.00 $360.00 $396.00
5.1.1 Alpha
testing
$144.00 $115.20 $216.00 $144.00 $158.40
5.1.2 Bug fixing $216.00 $172.80 $324.00 $216.00 $237.60
5.2 Beta version $144.00 $115.20 $216.00 $144.00 $158.40
5.2.1 Beta testing $144.00 $115.20 $216.00 $144.00 $158.40
M5 Milestone 5:
Completion of
alpha version and
beta testing
$0.00 $0.00 $0.00 $0.00 $0.00
6 Closure phase $768.00 $614.40 $1,152.00 $768.00 $844.80
6.1 Post project
review
$312.00 $249.60 $468.00 $312.00 $343.20
6.2 Release of the
simulation game
$72.00 $57.60 $108.00 $72.00 $79.20
6.3 Stakeholder
sign off
$64.00 $51.20 $96.00 $64.00 $70.40
6.4
Documentation
$320.00 $256.00 $480.00 $320.00 $352.00
M6 Milestone 6:
Completion of
$0.00 $0.00 $0.00 $0.00 $0.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
31
PROJECT MANAGEMENT
closure phase
chevron_up_icon
1 out of 32
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]