Project management
ContentsContents...........................................................................................................................................2INTRODUCTION...........................................................................................................................1TASK 1............................................................................................................................................2Network diagram.........................................................................................................................4Construction of Network diagram:..................................................................................................7TASK 2............................................................................................................................................1Importance of Communications Management with respect to the project selected....................1TASK 3............................................................................................................................................3a. Different options for accelerating project completion.............................................................3b. Implementation of project when resources and constrained and not constrained...................4TASK 4............................................................................................................................................5Discussion on managing project with virtual meetings...............................................................5Project 2...........................................................................................................................................6Part 1: initiation...............................................................................................................................6Task 1: Critical evaluation of advantages and disadvantages of outsourcing of project.............6Part 2: Planning................................................................................................................................7Task 2: Work Breakdown Structure (WBS) with all the major tasks..........................................7Part 3: Execution..............................................................................................................................9Task 3: Preparation of milestone report.......................................................................................9Part 4: Controlling.........................................................................................................................10Task 4: Critical functionalities that can be compromised compared to hire additional staff....10Part 5: Closing...............................................................................................................................11Task 5: Lessons-learned report for the entire project................................................................11CONCLUSION..............................................................................................................................12REFERENCES..............................................................................................................................13
INTRODUCTIONChanges with the organization or any other type of institution take place frequently andthese are done so that the quality of services that are delivered can be improved (Kadolph andMarcketti, 2016). Main focus of this project is made is to deliver proper services in relation withbuilding a management software for London Campus. In order to make such type of activities, itrequired to make interpretation of the activities that will be included in this process. Apart fromthis, there are many risk that are involved in the process of project development and it is essentialthat make sure that all the operations that are covered can be completed in effective manner. Inthis context, below given are the aim and objectives that will be covered in this project:Aim:To conduct building a management software for London Campus.Objectives:To develop and design a building that can be used as laboratories by teachers.To form healthy and comfortable environment for students and teachers.To determine the monitoring functions like energy management, power consumption, etc.To complete the project within determined budget that is $10,000.TASK 1Task NameDurationStartFinishPredecessorsBuilding ManagementSystem112 daysThu 2/1/18Fri 7/6/18Initiation phase15 daysTue 1/2/18Mon 1/22/18Setting the target goals ofBMS implementation5 daysTue 1/2/18Mon 1/8/18Setting stakeholdersexpectations10 daysTue 1/9/18Mon 1/22/183Proper and adequatedocumentations, contractsand agreements8 daysTue 1/9/18Thu 1/18/183Planning phase21 daysFri 1/19/18Fri 2/16/18Setting out operationalplans and policies6 daysFri 1/19/18Fri 1/26/185Identifying resourcerequirement i.e. humansource, funds andequipment’s9 daysMon 1/29/18Thu 2/8/187Plan for managing risk6 daysFri 2/9/18Fri 2/16/1881
Execution phase21 daysMon 2/19/18Mon 3/19/18Collection of funds5 daysMon 2/19/18Fri 2/23/189,4Hiring project team i.e.technical expert, websitedeveloper and others4 daysMon 2/26/18Thu 3/1/1811Purchase hardware andsoftware license and others12 daysFri 3/2/18Mon 3/19/1811,12Testing systemfunctioning5 daysFri 3/2/18Thu 3/8/1812Monitoring and controllingphase91 daysTue 1/2/18Tue 5/8/18Continue monitoring ofthe system functioning andwork execution33 daysTue 3/20/18Thu 5/3/1813Regular reporting91 daysFri 3/2/18Fri 7/6/1812Conducting meetings5 daysFri 3/9/18Thu 3/15/1814Analysing the risks4 daysFri 5/4/18Wed 5/9/1816,14Examining the progress bycomparing the performancewith the targets5 daysMon 7/9/18Fri 7/13/1817Altering the plan8 daysMon 7/9/18Wed 7/18/1817,16Closure phase1 dayTue 1/2/18Tue 1/2/18Contract closure1 dayThu 5/10/18Thu 5/10/1819Post-project appraisal andreview1 dayMon 7/16/18Mon 7/16/1820Submitting the final reportto the project manager1 dayThu 7/19/18Thu 7/19/1821Above given are the activities that are included in this project. In this context, all theseactivities need to be considered in appropriate manner. When these are done, then to the aim andobjectives attained will be achieved (Batselier and Vanhoucke, 2015).2
Network diagram3
10+8+6+9+6+5+4+91+8+1= 148 daysIn accordance with the above network diagram show, it can be stated that all the redmarked numbers are the critical pat that are highly important to be followed. All the otheractivities are not that important. Those are the activities that can be completed whenever theproject manager is willing to complete. In total there are 8 of the activities that are required to becompleted within the speculated time period. When this is not completed within the time that isdecided by the project manager, then the project will be a failure (Calvo-Mora, Navarro-Garcíaand Periañez-Cristobal, 2015). The project will have negative impact, when all the peopleinvolved are not able to complete them. Other than time, even cost is included and it is importantthat with the budget thatis determined all the activities are completed. When this is not done andthe balance that is set exceeds, then it a type of risk.IDDurationESEFLSLFSlackSetting the target goals of BMS implementation500555Setting stakeholders expectations1055151510Proper and adequate documentations, contracts andagreements8151523238Setting out operational plans and policies6232329296Identifying resource requirement i.e. humansource, funds and equipment’s9292938387Plan for managing risk6383844446Collection of funds5444449495Hiring project team i.e. technical expert, websitedeveloper and others4384542494Purchase hardware and software license and others124949616112Testing system functioning5616166665Continue monitoring of the system functioning andwork execution106671768110Regular reporting156666818115Conducting meetings56666818115Analyzing the risks4868790914Examining the progress by comparing theperformance with the targets5868691915Altering the plan8919199998Contract closure1919199998Post-project appraisal and review199991001001Submitting the final report to the project manager110010010110114