Work Breakdown Structure for Project Management Project Management

15 Pages1440 Words421 Views
   

Conventry University

   

Project Management (FBLT155)

   

Added on  2020-03-04

About This Document

In this document, we will discuss the project on the development of an order-taking system utilizing an iPad and create a breakdown structure, produce a work breakdown structure. Also, we cover the project's tasks and their dependencies, as well as human resources.

Work Breakdown Structure for Project Management Project Management

   

Conventry University

   

Project Management (FBLT155)

   Added on 2020-03-04

ShareRelated Documents
Running head: PROJECT MANAGEMENT
Project Management
Development of Order taking system by using Ipad
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Work Breakdown Structure for Project Management Project Management_1
1PROJECT MANAGEMENT
1. Work Breakdown Structure
Development of Order
taking system by using
Ipad
Project Intialization
Making initial
documents for the
project
Developing Project
Charter Document
Submission of the
document
Approval of the
document
Project Planning
Analysis of the
requirements
Selecting plan
methodology
Developing plan
outline
Reviewing the
outline developed
Making Complete
Plan
Approval of the plan
System Development
Designing of the system
Design Requirement
Analysis
IOS Platform Tool is
Selected for design
Design Prototype is
Made
Prototype is Tested
Errrors are rectified
Complete design is
made
Design is Approved
Database Development
Storage platform is
selected
Database Structure
is developed
Data is stored in the
database developd
Compatibility is
checked
Application Development
Application Interface
is developed
Creation of the
module
Coding of the
module
Functions are
endcoded in the
application
Database and
Application is
Integrated
Testing of the application
Testing the usability
of the interface
Testing the
functionality of the
application
Project closure
Project sign off
Figure 1: WBS for the project
(Created by the author in WBS Pro)
Work Breakdown Structure for Project Management Project Management_2
2PROJECT MANAGEMENT
Description of WBS developed: WBS for the project includes the activities of the
making initial documents for the project, developing project charter document, submission of the
document, and approval of the document in the project initialization phase. The project planning
phase consists of analysis of the requirements, selecting plan methodology, developing plan
outline, reviewing the outline developed, making complete plan, and approval of the plan. After
planning the main system development processes are started and it consists of designing of the
system, database development, application development, and testing of the application. The
designing phase includes design requirement analysis, IOS platform tool is selected for design,
design prototype is made, prototype is tested, errors are rectified, complete design is made, and
design is approved. The storage platform is selected, database structure is developed, data is
stored in the database developed, compatibility is checked, and application interface is developed
are the activities of database development phase. The application development comprises of
creation of the module, coding of the module, functions are encoded in the application, and
database and application is integrated. The testing activities of the system developed are testing
the usability of the interface and testing the functionality of the application. The project closure
includes the sign off the project.
Work Breakdown Structure for Project Management Project Management_3
3PROJECT MANAGEMENT
2. Gantt chart of the project
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors
0 0 Development of Order taking system by using Ipad51 days Wed 11/1/17 Wed 1/10/18
1 1 ProjectIntialization 7days Wed11/1/17 Thu11/9/17
2 1.1 Makinginitial documentsfor the project 3days Wed11/1/17 Fri 11/3/17
3 1.2 DevelopingProject Charter Document 2days Mon 11/6/17 Tue 11/7/17 2
4 1.3 Submissionof the document 1day Wed11/8/17 Wed11/8/17 3
5 1.4 Approval of the document 1day Thu11/9/17 Thu 11/9/17 4
6 2 ProjectPlanning 11days Fri 11/10/17 Fri 11/24/17
7 2.1 Analysisof the requirements 5days Fri 11/10/17 Thu 11/16/17 5
8 2.2 Selectingplan methodology 1day Fri 11/10/17 Fri 11/10/17 5
9 2.3 Developingplanoutline 3days Mon 11/13/17 Wed11/15/17 8
10 2.4 Reviewingthe outline developed 2days Thu11/16/17 Fri 11/17/17 9,8
11 2.5 MakingComplete Plan 5days Mon 11/20/17 Fri 11/24/17 10
12 2.6 Approval of the plan 1day Mon 11/20/17 Mon 11/20/17 10
13 3 SystemDevelopment 36days Tue11/21/17 Tue1/9/18
14 3.1 Designingofthesystem 18days Tue11/21/17 Thu12/14/17
15 3.1.1 Design Requirement Analysis 3days Tue 11/21/17 Thu 11/23/17 12
16 3.1.2 IOSPlatformTool isSelectedfor design 1day Fri 11/24/17 Fri 11/24/17 15
17 3.1.3 Design Prototype isMade 4days Mon 11/27/17 Thu 11/30/17 16
18 3.1.4 Prototype isTested 2days Mon 11/27/17 Tue 11/28/17 16
19 3.1.5 Errrorsare rectified 2days Fri 12/1/17 Mon 12/4/17 17
20 3.1.6 Complete design ismade 7days Tue 12/5/17 Wed12/13/17 19
21 3.1.7 Design isApproved 1day Thu12/14/17 Thu 12/14/17 20
22 3.2 DatabaseDevelopment 9days Fri 12/15/17 Wed12/27/17
23 3.2.1 Storage platformisselected 1day Fri 12/15/17 Fri 12/15/17 21
24 3.2.2 Database Structure isdeveloped 5days Mon 12/18/17 Fri 12/22/17 23
25 3.2.3 Dataisstored in the database developd 2days Mon 12/25/17 Tue 12/26/17 24
26 3.2.4 Compatibilityischecked 1day Wed12/27/17 Wed12/27/17 25
27 3.3 ApplicationDevelopment 15days Thu12/14/17 Wed1/3/18
28 3.3.1 ApplicationInterface isdeveloped 5days Thu12/14/17 Wed12/20/17 20
29 3.3.2 Creationof the module 3days Thu12/21/17 Mon 12/25/17 28
30 3.3.3 Codingof the module 4days Tue 12/26/17 Fri 12/29/17 29
31 3.3.4 Functionsare endcodedinthe application2days Mon 1/1/18 Tue 1/2/18 30
32 3.3.5 Database andApplication isIntegrated 1day Wed1/3/18 Wed1/3/18 31,26
33 3.4 Testingoftheapplication 4days Thu1/4/18 Tue1/9/18
34 3.4.1 Testingthe usabilityof the interface 2days Thu1/4/18 Fri 1/5/18 32
35 3.4.2 Testingthe functionalityof the application2days Mon 1/8/18 Tue 1/9/18 34,20
36 4 Projectclosure 1day Wed1/10/18 Wed1/10/18
37 4.1 Project sign off 1day Wed1/10/18 Wed1/10/18 35
Documentor
Documentor
Documentor
Project Manager
Analyst
Planner
Planner
Project Manager
Planner
Project Manager
Designer
Designer
Designer
Tester
Designer
Designer
Project Manager
DatabaseEngineer
DatabaseEngineer
DatabaseEngineer
DatabaseEngineer
ITEngineer
ITEngineer
ITEngineer
ITEngineer
ITEngineer
Tester
Tester
Project Manager
T F S S M T W T F
Sep 24, '17 Oct 29, '17 Dec 3, '17 Jan 7, '18 Feb 11, '18
Figure 2: Gantt chart for the project
(Created by the author in Ms-Project)
Work Breakdown Structure for Project Management Project Management_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Installation of Computerized E-Ticketing System for RALS : Project
|11
|2282
|53

High Level Work Breakdown Structure for Desklib Project
|8
|5016
|457

Installation of Computerized E-Ticketing System for RALS
|12
|2349
|173

Designing of Pharmacy Application and Installation of database servers and hardware
|4
|633
|346

SIT773 SOFTWARE REQUIREMENTS AND ANALYSIS.
|4
|384
|11

Riverina Agriculture and Lifestyle Show
|11
|2242
|32