This assignment delves into the essential concepts of project management, emphasizing the role of quality control in achieving project success. It examines various quality management practices and tools used to ensure projects meet defined standards and objectives. Students are tasked with understanding the importance of quality planning, implementation, monitoring, and control throughout the project lifecycle. The document also highlights the relationship between effective project management and overall organizational performance.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Project Management: Replacement of Darling Harbour Swing Bridge Project
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Document Name Project Tender Document
Project Name Darling Harbour Swing Bridge Replacement
Project
Part 1: Statement of Work
Introduction
The statement of work is a structured document that gives an insight of the details and
scope of the work that is needed to be completed within the specific project. This formal
document is needed to be agreed upon all the parties involved in the project. An effective
Statement of Work document should contain every minute details of the project so that the
different parties involved have a clear idea of the type of work required, duration of the work and
the project deliverables. The statement of work document generally contains a brief description
of the project and involves a request for proposal as well. This document should be routinely
employees in the implementation of project management as it contains the definition of the
project specific activities, the project deliverables and project timeline along with the project
schedule.
Project Background
The project deals with the work of Darling Harbor Swing Bridge replacement. This
project involves the superstructure replacement of the bridge along with the swing span
replacement, substructure modification. Other works of the project includes a complete
mechanical and electrical overhaul, operator house replacement and fender system replacement.
The project has been designed in order to minimize the impact or effect on public. Therefore, it
is decided that the works related to the superstructure and swing span replacement is to be
completed within the 10-day period during which the bridge will remain closed for the public.
Document Page
2PROJECT MANAGEMENT
The construction work for the project is decided to be start on 11 September 2017 and completed
within 5th December 2017. The budget set for the entire project is AUD 31,474,000. Tenders for
the project have been invited, which is needed to be submitted in person to Samira Alvandi. A
proper project management plan is developed for this project along with the plan for quality
assurance and safety management standards. The contract type chosen for this project is a fixed
type contract with a bid built method of delivery. The project is expected to be completed within
the set schedule and allocated budget.
Scope of Work
The scope of work for renovation of the bridge includes the planning and execution of the
project according to the set plan. A group f architect appointed for the project will be responsible
for designing the structure of the construct ion work and a detailed overview of the part of the
bridge that needs immediate attention. Each part of the planning phase will however require
approval from the project owner before moving on to the subsequent stages. The contractor hired
for the project is responsible for ensuring the presence of adequate resources for redesigning,
building and stress tensing. The implementation phases of the project include the replacement of
the superstructure of the swing bridge, replacement of the swing plan along with the
modifications of the substructure. This requires a planned approach as all the works in the project
should be completed within the 10-day bridge closure period. Other construction works in the
project includes complete mechanical and electrical overhaul, replacement of the operator house
and fender system replacement. The major deliverables associated with the project is the
replacement of superstructure and the swing span. This is a major deliverable because it is set to
be completed within a very constricted time of 10 days. The project should be completed within
the set budget of AUD 31,474,000 with the start date of construction work is scheduled to 11
Document Page
3PROJECT MANAGEMENT
September 2017 and the project completion date is set to 5 December 2017.
Period of Performance
The project of Darling Harbour Swing Bridge Replacement Project is implied for the
development of the effective flow of operations and its significant development of the bridge in
the span of project duration. The operations of the project would be carry on from Monday 11th
September, 2017 to 5th December, 2017.
Work Requirements
The project of Darling Harbour Swing Bridge Replacement Project would consist of using
the waterfall methodology for the development of the construction project. The project of
construction of the activities of bridge redevelopment would involve the use of the effective and
improved operations. The project operations would be divided into four phases namely Project
Planning, Project Initiation, Project Construction, and Project Closure. The planning phase
consists of development of project plan, resource development plan, financial plan development,
quality analysis and strategy, communication plan development, and procurement plan
development. The Project Initiation Phase includes Buisness case development, Feasibility
Analysis and Study, Project Charter Documentation, and Project team is build up. The Project
Construction Phase comprises of "Superstructure Replacement of the “Darling Harbour Swing
Bridge", "Swing Span Replacement of “Darling Harbour Swing Bridge", "Substructure
Modification of “Darling Harbour Swing Bridge", "Mechanical Overhaul is formed for “Darling
Harbour Swing Bridge", "Electrical Overhaul is formed for “Darling Harbour Swing Bridge",
"Operator House replacement for “Darling Harbour Swing Bridge", and "Fender System
Replacement of “Darling Harbour Swing Bridge". The Project Closure Phase includes the
Project Progress is Reviewed, Final Documentation of the project, and Stakeholders Sign off the

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
project final report.
The project requirements consist of some resources that would be implied for the development of
the effective processing and analysis.
Resource Name Type
Project manager Human
Project planner Human
Sub-contractor Human
Architect Human
Contractor Human
Supervisor Human
Machines Material
Tools Material
Safety and Health Material
Documents Material
Project Schedule
WBS Task Name Duration Start Finish
0 Darling Harbour Swing Bridge
Replacement Project 62 days Mon 9/11/17 Tue 12/5/17
1 Project Plan Development Phase 16 days Mon 9/11/17 Mon 10/2/17
1.1 Development of Project Plan 3 days Mon 9/11/17 Wed 9/13/17
1.2 Resource Plan Development 2 days Thu 9/14/17 Fri 9/15/17
1.3 Financial Plan is formed 2 days Mon 9/18/17 Tue 9/19/17
1.4 Quality Analysis and Strategy 3 days Wed 9/20/17 Fri 9/22/17
1.5 Risk Mitigation Strategy 2 days Mon 9/25/17 Tue 9/26/17
1.6 Communictaion Plan Development 2 days Wed 9/27/17 Thu 9/28/17
1.7 Procurement plan development 2 days Fri 9/29/17 Mon 10/2/17
1.8 Plan is approved 0 days Mon 10/2/17 Mon 10/2/17
2 Project Initiation Phase 10 days Tue 10/3/17 Mon 10/16/17
2.1 Buisness case development 2 days Tue 10/3/17 Wed 10/4/17
2.2 Feasibility Analysis and Study 3 days Thu 10/5/17 Mon 10/9/17
2.3 Project Charter Documentation 3 days Tue 10/10/17 Thu 10/12/17
2.4 Project team is build up 2 days Fri 10/13/17 Mon 10/16/17
2.5 Project Kick off 0 days Mon 10/16/17 Mon 10/16/17
3 Project Construction Phase 32 days Tue 10/17/17 Wed 11/29/17
3.1 Superstructure Replacement of the
“Darling Harbour Swing Bridge" 4 days Tue 10/17/17 Fri 10/20/17
3.2 Swing Span Replacement of
“Darling Harbour Swing Bridge" 6 days Mon 10/23/17 Mon 10/30/17
Document Page
5PROJECT MANAGEMENT
3.3 Substructure Modification of
“Darling Harbour Swing Bridge" 3 days Tue 10/31/17 Thu 11/2/17
3.4 Mechanical Overhaul is formed for
“Darling Harbour Swing Bridge" 4 days Fri 11/3/17 Wed 11/8/17
3.5 Electrical Overhaul is formed for
“Darling Harbour Swing Bridge" 4 days Thu 11/9/17 Tue 11/14/17
3.6 Operator House replacement for
“Darling Harbour Swing Bridge" 5 days Wed 11/15/17 Tue 11/21/17
3.7 Fender System Replacement of
“Darling Harbour Swing Bridge" 6 days Wed 11/22/17 Wed 11/29/17
3.8 Construction Activities are
completed 0 days Wed 11/29/17 Wed 11/29/17
4 Project Closure Phase 4 days Thu 11/30/17 Tue 12/5/17
4.1 Project Progress is Reviewed 2 days Thu 11/30/17 Fri 12/1/17
4.2 Final Documentation of the project 1 day Mon 12/4/17 Mon 12/4/17
4.3 Stakeholders Sign off the project
final report 1 day Tue 12/5/17 Tue 12/5/17
4.4 Project is Closed 0 days Tue 12/5/17 Tue 12/5/17
Acceptance Criteria
The project of Darling Harbour Swing Bridge Replacement would have to endure the
development of the effective and smart analysis of the project integration management. The
development of the project operations would be helpful for the integration of the profound
knowledge development. The acceptance of the project would be based on the following factors,
Project Initial Requirements and Resources are gathered
Project would be completed in the estimated time schedule
Operations of the project would be completed in the estimated cost budget
Government Approval of the construction Activities
WHS health and Safety Policies for construction is implied
Fire Safety Measures are used
Part 2 Work Breakdown Structure
Project WBS
Document Page
6PROJECT MANAGEMENT
0 - Darling Harbour Swing
Bridge Replacement
Project
1 - Project Plan
Development Phase
1.1 - Development of Project
Plan
1.2 - Resource Plan
Development
1.3 - Financial Plan is formed
1.4 - Quality Analysis and
Strategy
1.5 - Risk Mitigation Strategy
1.6 - Communictaion Plan
Development
1.7 - Procurement plan
development
1.8 - Plan is approved
2 - Project Initiation Phase
2.1 - Buisness case
development
2.2 - Feasibility Analysis and
Study
2.3 - Project Charter
Documentation
2.4 - Project team is build up
2.5 - Project Kick off
3 - Project Construction
Phase
3.1 - Superstructure
Replacement of the
“Darling Harbour Swing
Bridge"
3.2 - Swing Span
Replacement of “Darling
Harbour Swing Bridge"
3.3 - Substructure
Modification of “Darling
Harbour Swing Bridge"
3.4 - Mechanical Overhaul is
formed for “Darling
Harbour Swing Bridge"
3.5 - Electrical Overhaul is
formed for “Darling
Harbour Swing Bridge"
3.6 - Operator House
replacement for “Darling
Harbour Swing Bridge"
3.7 - Fender System
Replacement of “Darling
Harbour Swing Bridge"
3.8 - Construction Activities
are completed
4 - Project Closure Phase
4.1 - Project Progress is
Reviewed
4.2 - Final Documentation of
the project
4.3 - Stakeholders Sign off
the project final report
4.4 - Project is Closed
Project Gantt Chart

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 Darling Harbour Swing Bridge
Replacement Project
62 days Mon 9/11/17 Tue 12/5/17 $31,474,00...
1 1 Project Plan Development Phase16 days Mon 9/11/17 Mon 10/2/17 $575,800.00
2 1.1 Development of Project Plan 3 days Mon 9/11/17 Wed 9/13/17 Project manager $60,000.00
3 1.2 Resource Plan Development 2 days Thu 9/14/17 Fri 9/15/17 2 Project planner $25,600.00
4 1.3 Financial Plan is formed 2 days Mon 9/18/17 Tue 9/19/17 3 Project manager,Documents[1]$161,900.00
5 1.4 Quality Analysis and Strategy3 days Wed 9/20/17 Fri 9/22/17 4 Project planner $38,400.00
6 1.5 Risk Mitigation Strategy 2 days Mon 9/25/17 Tue 9/26/17 5 Project manager,Sub-contractor$72,000.00
7 1.6 Communictaion Plan
Development
2 days Wed 9/27/17 Thu 9/28/17 6 Project manager,Architect $70,400.00
8 1.7 Procurement plan development2 days Fri 9/29/17 Mon 10/2/17 7 Project planner,Documents[1]$147,500.00
9 1.8 Plan is approved 0 days Mon 10/2/17 Mon 10/2/17 8 $0.00
10 2 Project Initiation Phase 10 days Tue 10/3/17 Mon 10/16/17 $311,500.00
11 2.1 Buisness case development 2 days Tue 10/3/17 Wed 10/4/17 9 Architect,Contractor $65,600.00
12 2.2 Feasibility Analysis and Study3 days Thu 10/5/17 Mon 10/9/17 11 Project planner $38,400.00
13 2.3 Project Charter Documentation3 days Tue 10/10/17 Thu 10/12/17 12 Project manager,Documents[1]$181,900.00
14 2.4 Project team is build up 2 days Fri 10/13/17 Mon 10/16/17 13 Project planner $25,600.00
15 2.5 Project Kick off 0 days Mon 10/16/17 Mon 10/16/17 14 $0.00
16 3 Project Construction Phase 32 days Tue 10/17/17 Wed 11/29/17 $30,404,80...
17 3.1 Superstructure Replacement
of the “Darling Harbour
Swing Bridge"
4 days Tue 10/17/17 Fri 10/20/17 15 Architect,Sub-contractor,Machines[1],Tools
[1],Safety and Health [1]
$4,304,800...
18 3.2 Swing Span Replacement of
“Darling Harbour Swing
Bridge"
6 days Mon 10/23/17 Mon 10/30/17 17 Architect,Sub-contractor,Machines[1],Tools
[1],Safety and Health [1]
$4,367,200...
19 3.3 Substructure Modification of
“Darling Harbour Swing
Bridge"
3 days Tue 10/31/17 Thu 11/2/17 18 Contractor,Supervisor,Machines[1],Tools
[1],Safety and Health [1]
$4,273,600...
20 3.4 Mechanical Overhaul is
formed for “Darling Harbour
Swing Bridge"
4 days Fri 11/3/17 Wed 11/8/17 19 Contractor,Sub-contractor,Supervisor,Machines[1],Tools
[1],Safety and Health [1]
$4,368,800...
21 3.5 Electrical Overhaul is formed
for “Darling Harbour Swing
Bridge"
4 days Thu 11/9/17 Tue 11/14/17 20 Architect,Contractor,Supervisor,Machines[1],Tools
[1],Safety and Health [1]
$4,365,600...
22 3.6 Operator House replacement
for “Darling Harbour Swing
Bridge"
5 days Wed 11/15/17 Tue 11/21/17 21 Contractor,Sub-contractor,Machines[1],Safety
and Health [1],Tools [1]
$4,348,000...
23 3.7 Fender System Replacement
of “Darling Harbour Swing
Bridge"
6 days Wed 11/22/17 Wed 11/29/17 22 Architect,Contractor,Machines[1],Safety
and Health [1],Tools [1]
$4,376,800...
24 3.8 Construction Activities are
completed
0 days Wed 11/29/17 Wed 11/29/17 23 $0.00
25 4 Project Closure Phase 4 days Thu 11/30/17 Tue 12/5/17 $181,900.00
26 4.1 Project Progress is Reviewed2 days Thu 11/30/17 Fri 12/1/17 24 Supervisor $27,200.00
27 4.2 Final Documentation of the project1 day Mon 12/4/17 Mon 12/4/17 26 Project planner,Documents[1]$134,700.00
28 4.3 Stakeholders Sign off the
project final report
1 day Tue 12/5/17 Tue 12/5/17 27 Project manager $20,000.00
29 4.4 Project is Closed 0 days Tue 12/5/17 Tue 12/5/17 28 $0.00
Project manager
Project planner
Project manager,Documents[1]
Project planner
Project manager,Sub-contractor
Project manager,Architect
Project planner,Documents[1]
10/2
Architect,Contractor
Project planner
Project manager,Documents[1]
Project planner
10/16
Architect,Sub-contractor,Machines[1],Tools [1],Safety and Health [1]
Architect,Sub-contractor,Machines[1],Tools [1],Safety and Health [1]
Contractor,Supervisor,Machines[1],Tools [1],Safety and Health [1]
Contractor,Sub-contractor,Supervisor,Machines[1],Tools [1],Safety and He
Architect,Contractor,Supervisor,Machines[1],Tools [1],Safety and Health
Contractor,Sub-contractor,Machines[1],Safety and Health [1],Tools [1]
Architect,Contractor,Machines[1],Safety and Health [1],Tools [1]
11/29
Supervisor
Project planner,Documents[1]
Project manager
12/5
9/10 10/22 12/3 1/14 2/25
July 1 October 1 January 1 April 1
Gantt Chart in table format
WBS Task Name Duratio
n Start Finish Predecessors Resource Names
0
Darling Harbour
Swing Bridge
Replacement
Project
62 days Mon
9/11/17
Tue
12/5/17
1 Project Plan
Development Phase 16 days Mon
9/11/17
Mon
10/2/17
1.1 Development of
Project Plan 3 days Mon
9/11/17
Wed
9/13/17 Project manager
1.2 Resource Plan
Development 2 days Thu
9/14/17
Fri
9/15/17 2 Project planner
1.3 Financial Plan is
formed 2 days Mon
9/18/17
Tue
9/19/17 3 Project manager,
Documents[1]
1.4 Quality Analysis
and Strategy 3 days Wed
9/20/17
Fri
9/22/17 4 Project planner
1.5 Risk Mitigation
Strategy 2 days Mon
9/25/17
Tue
9/26/17 5 Project manager, Sub-
contractor
Document Page
8PROJECT MANAGEMENT
1.6 Communication
Plan Development 2 days Wed
9/27/17
Thu
9/28/17 6 Project manager,
Architect
1.7 Procurement plan
development 2 days Fri
9/29/17
Mon
10/2/17 7 Project planner,
Documents[1]
M1 Plan is approved 0 days Mon
10/2/17
Mon
10/2/17 8
2 Project Initiation
Phase 10 days Tue
10/3/17
Mon
10/16/17
2.1 Business case
development 2 days Tue
10/3/17
Wed
10/4/17 9 Architect, Contractor
2.2 Feasibility
Analysis and Study 3 days Thu
10/5/17
Mon
10/9/17 11 Project planner
2.3 Project Charter
Documentation 3 days Tue
10/10/17
Thu
10/12/17 12 Project manager,
Documents[1]
2.4 Project team is
build up 2 days Fri
10/13/17
Mon
10/16/17 13 Project planner
M2 Project Kick off 0 days Mon
10/16/17
Mon
10/16/17 14
3 Project
Construction Phase 32 days Tue
10/17/17
Wed
11/29/17
3.1
Superstructure
Replacement of the
“Darling Harbour
Swing Bridge"
4 days Tue
10/17/17
Fri
10/20/17 15
Architect, Sub-contractor,
Machines[1], Tools [1],
Safety and Health [1]
3.2
Swing Span
Replacement of
“Darling Harbour
Swing Bridge"
6 days Mon
10/23/17
Mon
10/30/17 17
Architect, Sub-contractor,
Machines[1], Tools [1],
Safety and Health [1]
3.3
Substructure
Modification of
“Darling Harbour
Swing Bridge"
3 days Tue
10/31/17
Thu
11/2/17 18
Contractor, Supervisor,
Machines[1], Tools [1],
Safety and Health [1]
3.4
Mechanical
Overhaul is formed
for “Darling Harbour
Swing Bridge"
4 days Fri
11/3/17
Wed
11/8/17 19
Contractor, Sub-
contractor, Supervisor,
Machines[1],Tools
[1],Safety and Health [1]
3.5
Electrical
Overhaul is formed
for “Darling Harbour
Swing Bridge"
4 days Thu
11/9/17
Tue
11/14/17 20
Architect, Contractor,
Supervisor, Machines[1],
Tools [1], Safety and
Health [1]
3.6
Operator House
replacement for
“Darling Harbour
Swing Bridge"
5 days Wed
11/15/17
Tue
11/21/17 21
Contractor, Sub-
contractor,
Machines[1],Safety and
Health [1],Tools [1]
Document Page
9PROJECT MANAGEMENT
3.7
Fender System
Replacement of
“Darling Harbour
Swing Bridge"
6 days Wed
11/22/17
Wed
11/29/17 22
Architect, Contractor,
Machines[1], Safety and
Health [1], Tools [1]
M3
Construction
Activities are
completed
0 days Wed
11/29/17
Wed
11/29/17 23
4 Project Closure
Phase 4 days Thu
11/30/17
Tue
12/5/17
4.1 Project Progress
is Reviewed 2 days Thu
11/30/17
Fri
12/1/17 24 Supervisor
4.2
Final
Documentation of the
project
1 day Mon
12/4/17
Mon
12/4/17 26 Project planner,
Documents[1]
4.3
Stakeholders Sign
off the project final
report
1 day Tue
12/5/17
Tue
12/5/17 27 Project manager
M4 Project is Closed 0 days Tue
12/5/17
Tue
12/5/17 28
Part 3: Milestone schedule
From the project schedule, the milestone for the project of is,
WBS Task Name Duration Start Finish
M1 Plan is approved 0 days Mon 10/2/17 Mon 10/2/17
M2 Project Kick off 0 days Mon 10/16/17 Mon 10/16/17
M3 Construction Activities are completed 0 days Wed 11/29/17 Wed 11/29/17
M4 Project is Closed 0 days Tue 12/5/17 Tue 12/5/17
Part 4: Cost Estimates
The project budget is shown in the table below,
WBS Task Name Cost
0 Darling Harbour Swing Bridge Replacement Project $31,474,000.00
1 Project Plan Development Phase $575,800.00
1.1 Development of Project Plan $60,000.00
1.2 Resource Plan Development $25,600.00
1.3 Financial Plan is formed $161,900.00
1.4 Quality Analysis and Strategy $38,400.00
1.5 Risk Mitigation Strategy $72,000.00
1.6 Communication Plan Development $70,400.00
1.7 Procurement plan development $147,500.00
M1 Plan is approved $0.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
2 Project Initiation Phase $311,500.00
2.1 Business case development $65,600.00
2.2 Feasibility Analysis and Study $38,400.00
2.3 Project Charter Documentation $181,900.00
2.4 Project team is build up $25,600.00
M2 Project Kick off $0.00
3 Project Construction Phase $30,404,800.00
3.1 Superstructure Replacement of the “Darling Harbour Swing Bridge" $4,304,800.00
3.2 Swing Span Replacement of “Darling Harbour Swing Bridge" $4,367,200.00
3.3 Substructure Modification of “Darling Harbour Swing Bridge" $4,273,600.00
3.4 Mechanical Overhaul is formed for “Darling Harbour Swing Bridge" $4,368,800.00
3.5 Electrical Overhaul is formed for “Darling Harbour Swing Bridge" $4,365,600.00
3.6 Operator House replacement for “Darling Harbour Swing Bridge" $4,348,000.00
3.7 Fender System Replacement of “Darling Harbour Swing Bridge" $4,376,800.00
M3 Construction Activities are completed $0.00
4 Project Closure Phase $181,900.00
4.1 Project Progress is Reviewed $27,200.00
4.2 Final Documentation of the project $134,700.00
4.3 Stakeholders Sign off the project final report $20,000.00
M4 Project is Closed $0.00
Part 5: Quality Assurance/Safety Standards
Quality assurance for any project is necessary for maintaining a desirable quality of a
product. This requires through attention to every stage and processes from the project initiation
phase to the project completion phase. The construction work related to the repair an renovation
of the Darling Harbor Swing bridge is a highly optimized process involving different disciplines
and different participants as well. The quality assurance standards thus undertaken in this project
eliminates the cause of unsatisfying performance in the project implementation. A contract
document is developed as a guideline of quality control. This document indicates that any
construction work in the bridge will be considered acceptable under the applicable regulatory
codes and standards of professional practice, only if it is reliable enough and the ease with which
the maintenance works can be managed. The different tools and technology involved with the
maintenance of the quality standard includes regular inspection of the works, control charts and
Document Page
11PROJECT MANAGEMENT
statistical sampling. These tools help in improvement of the quality of the works and in decision
acceptance as well. Evaluation of the project performance in regular basis helps in providing the
confidence that the project will satisfy the relevant quality standards and therefore this is one of
the major requirements in maintaining a standard quality of the project. Furthermore, monitoring
of the quality assurance program is necessary for ensuring a proper result. This further requires a
development of quality management plan that should be followed throughout the project
implementation phase. Quality audit is another major criteria required for safeguarding the
assured quality of the project is scheduled to be completed in a constricted time of 10 days.
Furthermore, in order to assure a good quality project, determining and inspecting the quality of
the building materials such as cement, sand, steel and aggregate concrete is essential. The
moisture content in the specific part of the bridge is to be measured and dealt accordingly. The
tensile strength of the steel and compressive strength of the bricks is needed to be inspected in
order to deliver a good quality product and project. The different steps involved in quality
assurance are listed below-
1) The materials testing are to be done prior to the beginning of the construction
2) The contractor is responsible for obtaining the samples of the materials designated as
the proposed source of the materials
3) Contractor is responsible for sending the test samples in the testing laboratory for
determining the acceptance criteria of the material under testing
4) The CQAO is responsible for inspecting the materials being used periodically
5) The project manager is responsible for supervision of the entire project work and
should make sure that the project undergoes every phases of the project management.
Safety Standards are designed in order to ensure the safety of the products activities and
Document Page
12PROJECT MANAGEMENT
the processes involved in the project management life cycle. Every worker and employees
associated with this project should abide by the safety standards of the project. The safety policy
is designed to comply with the occupational safety and health administration, with an aim of
maintaining a safe workplace. Workers are requires to familiarize themselves with all the
potential hazards in the construction site and should not work in the areas where the protection
system have not been installed. The project owner should also ensure fall protection systems to
protect the workers working in the site and prevent them from walking on unprotected edges.
Hard hats are mandatory to be worn while working on site. Furthermore, it is mandatory for the
workers to wear sturdy and non-skid work boots while working on the bridge. For this, workers
should be trained enough to recognize the hazards of falling and should know the procedure of
minimizing the hazards and preventing the falls. The workers should be further provided with an
eye and face protection to the workers and the safety standard designed should meet the
standards of ANSI Z87.1-2010. Workers should be trained to operate the aerial lift in the
workspace.
Part 6: Procurement Strategy
Procurement strategy is a planned approach of delivering a successful product. It deals
with the acquisition of materials, supplies and services that a company need to operate
successfully. The type of contract chosen for a project depends on many factors, which includes
type of the building project and goals and objective of the project. The contract type chosen for
this renovation project is a fixed price contract. This contract type is chosen for this project
because the total budget of the project is already fixed to AUD 31, 474,000 with a a fixed
schedule. Furthermore, the superstructure and swing span replacement of the bridge is needed to
be completed within the 10-day bridge closure period to minimize the impact of construction on

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
public. Therefore, it is beneficial to consider a fixed project contract for this construction work.
In a fixed type contract, the owner and the contractor before the initiation of the construction or
project work agree a single price for all work. This assures the completion of the project within
athe ste time as this type of contract includes incentives fir early completion of the project and in
similar ways, the liquidated damages or penalties for the late completion. Therefore, it becomes
responsibility of the contractor to complete the work within the set time. Since the amount is
already paid at the beginning of the project initiation, it becomes the responsibility of the
contractor to complete the work within the set schedule. There is however, certain risk associated
with the builder or the contractor if he fails to bid an appropriate cost of the project. This risk can
however be mitigated in this case as the budget of the project is already set for this project as
well as the project schedule. Fixed contract is ideal for the projects, which have a clear project
scope and defined construction schedule. There is limited flexibility in modifying and designing
the project works once the project has been initiated. Since the scope, schedule and budget of
the project is clear, it is beneficial for the project owner to consider a fixed type contract. The
major drawback related to the fixed type contract is that there is less transparency in the
breakdown of costs and the profit margin of the builder. The major advantage of a fixed type
contract is that it is normally not subjected to any sort of adjustments unless the provision for the
same is included in the agreement. It provides the assurance of a task or project completion
within a set budget and therefore fixed contract is set for this renovation project. Furthermore, it
places a minimum administrative burden on the different contracting parties but is subjected to
maximum risk in case of cost escalation.
The method of delivery chosen for this project is design bid build method. This includes
designing of the project by a team of architects hired for this project. The contractor appointed
Document Page
14PROJECT MANAGEMENT
for the project along with the project manager is responsible for completion of the project. In this
mode of delivery, the designing and construction phases of a project are clear and distinct and
the entire planning of the project is generally completed before the initiation of the project. The
major advantage of the project is that, the project scope is well understood and there are less
chance of the misunderstandings in the project. The delivery method associated with a fixed time
contract is design bid build delivery and therefore, this method of delivery is recommended for
the project.