Running head: PROJECT MANAGEMENT Assessment 3 Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 PROJECT MANAGEMENT Table of Contents Project overview.........................................................................................................................3 1. Part One..................................................................................................................................3 1.1 MOV- Measurable organizational value..........................................................................3 1.2 Identification of desired area of impact...........................................................................4 1.3 Value of the project..........................................................................................................4 1.4 Appropriate metric...........................................................................................................5 2. Part Two.................................................................................................................................6 2.1 Scope................................................................................................................................6 2.2 Out of scope.....................................................................................................................7 2.3 Scope management plan...................................................................................................7 2.4 Resource plan...................................................................................................................7 3. Part Three...............................................................................................................................9 3.1 Project milestones............................................................................................................9 3.2 Project activities...............................................................................................................9 3.3 Project resources............................................................................................................12 3.4 Time estimation..............................................................................................................13 3.5 Project budget.................................................................................................................14 3.6 Time phase budget.........................................................................................................15 4. Part Four...............................................................................................................................15 4.1 Assumptions...................................................................................................................15 4.2 Project risk and management strategy............................................................................16
2 PROJECT MANAGEMENT 5. Part Five...............................................................................................................................18 6. Part Six.................................................................................................................................19 6.1 Annotated Bibliography.................................................................................................19 6.2 Development of closure checklist..................................................................................19 6.3 Development of project evaluation................................................................................20 Bibliography.............................................................................................................................21 Appendices...............................................................................................................................23 Appendix 1: Annotated Bibliography..................................................................................23
3 PROJECT MANAGEMENT Project overview The paper mainly reflects on the organization “Globlex” whose main aim is to help the farmers in increasing their productivity by minimizing the cost and time by starting a training and Apprenticeship program for high school students. It is found that the program will be helpful in providing a useful work experience and employment opportunities in the field of farming. The organization wants to develop a computer-based system for managing the entire TAHS program. It is found that the new system will be developed within 3 months by utilizing budget of around $94,000. 1. Part One 1.1 MOV- Measurable organizational value MOV is considered as the goal of the project that is mainly utilized for defining the value which will generally bring to the customers. It is identified that for providing proper as well as real value to the organization, it is very much important to properly align the project withthevision,missionaswellasstrategyoftheorganization.Themeasurable organizational value that will be bring to the client are generally elaborated below: FactorDescription CustomerIt is found that the customers will get improved service with the help of the TAHS program. FinancialThe financial income of the organization generallyincreasesby12%duetothe TAHS program. SocialThe TAHS program is linked with the socialmediaforreachingtoagreater
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 PROJECT MANAGEMENT number of students who are interested in helping clients StrategyIt is very much important to use appropriate strategy so that the computer-based system formanagingTAHSprogramcanbe completed on time. OperationalIt is found that the entire program of TAHS willbemanagedproperlyduetothe development of the computer-based system within the organization. 1.2 Identification of desired area of impact The desired area of impact is generally reflected through the table that is generally provided below: FactorRank Customer2nd Financial3rd Social4th Strategy5th Operational1st 1.3 Value of the project The values are generally elaborated below: Better:It is identified that by using the computer-based system, the TAHS program will be managed quite properly. It is found that with the help of new system, the TAHS
5 PROJECT MANAGEMENT program will be able to collect proper information regarding the needs and then train students as per the skills and gives them placement so that they can help the farmers. Faster:The newly developed computer-based system will be able to manage the operations of TAHS program quite faster as compared to the manual system and thus it is found that the new system is quite useful. 1.4 Appropriate metric RankImpactMetricsTimeframe 1stOperationalIt is found that the efficiencyofthe programgenerally improves due to the developmentof computer-based system for managing the TAHS program 3months 2ndCustomerThe benefits that are providedwiththe help of the program isquitebeneficial for farming purpose. 2 months 3rdFinancialThemoneythatis generallyspenton thedevelopmentof the computer system willgenerallyrise 3 months
6 PROJECT MANAGEMENT the financial benefit of the organization. 4thSocialSocialmedia support is generally taken for advertising abouttheTAHS program. 1 month 5thStrategyItisverymuch importantto properlydevelop appropriatestrategy in order to complete thedevelopmentof computer-based system on time. 2 months 2. Part Two 2.1 Scope The project scope generally include: Invite expressions from schools Collecting information from the manufacturers that undertakes farming Facility of placement to the students Detailed reporting system Apprentice tracking facility
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 PROJECT MANAGEMENT 2.2 Out of scope The out-scope of the project mainly include: Appropriate training facility is not given to the team members of the project Detailsrelated with the suppliers are generally not given 2.3 Scope management plan Thestepswhicharegenerallyusedformanagingprojectscopearegenerally elaborated below: It is very much necessary to understand the problem that is associated with the project Secondly, the conflict that exists within the project scope must be embraced quite successfully within the project. It is quite important to communicate successfully with the various customers of the organization It is quite important to identify the sign of scope creep so that scope creep can be properly avoided. 2.4 Resource plan People:The people who are generally related with the development of computer- based system are listed below: Resource NameType Max. Units Std. RateBase Calendar Project plannerWork100%$ 35.00/hrStandard DeveloperWork100%$ 30.00/hrStandard Database administratorWork100%$ 30.00/hrStandard DesignerWork100%$ 35.00/hrStandard
8 PROJECT MANAGEMENT Human resource managerWork100%$ 35.00/hrStandard Financial managerWork100%$ 35.00/hrStandard Quality analystWork100%$ 30.00/hrStandard Risk managerWork100%$ 30.00/hrStandard Project managerWork100%$ 50.00/hrStandard Technical expertWork100%$ 35.00/hrStandard Risk managerWork100%$ 30.00/hrStandard System administratorWork100%$ 30.00/hrStandard System administratorWork100%$ 35.00/hrStandard Software engineerWork100%$ 30.00/hrStandard Project sponsorWork100%$ 0.00/hrStandard Technology:The various type of technologies which are generally required for the project purpose are mainly elaborated below: Hardware:RAM, computer as well as hard disk Software:Designing tool, Development software Facilities:Appropriate facility of training is required for the organization employees who are engaged in the development of the system. Other:The other type of facilities that are provided to the team are generally listed below: Travel requirements:Additional allowances are generally given for travelling to the employees.
9 PROJECT MANAGEMENT 3. Part Three 3.1 Project milestones MilestoneCompletion date Milestone 1: Completion of initiation phaseMon 07-01-19 Milestone 2: Project planning completionThu 17-01-19 Milestone 3: Design phase completionThu 31-01-19 Milestone 4: Development completionFri 12-04-19 Milestone 5: Completion of testing phaseFri 26-04-19 Milestone 6: Completion of closure phaseFri 03-05-19 3.2 Project activities The activities that are generally executed for developing the computer-based system in order to manage the TAHS program are mainly given in the table: WBSTask Name 0Development of computer-based system for managing TAHS 1Project initiation phase 1.1Identification of requirement 1.2Project plan development 1.3Cost benefit analysis 1.4Milestone 1: Completion of initiation phase 2Project planning phase 2.1Identification of resources 2.2Project activities scheduling 2.3Work allocation
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 PROJECT MANAGEMENT 2.4Communication plan development 2.5Assigning project resources 2.6Milestone 2: Project planning completion 3Project design phase 3.1Designing prototype 3.2Incorporation of features 3.3Identifying functional and non-functional needs 3.4Milestone 3: Design phase completion 4Development phase 4.1Invitation of expressions of interest from school 4.2Collection of detail including farming equipment’s 4.3Providing the facility of placement 4.4Providing training facility to the students 4.5Providing proper facility of farming 4.6Development of reporting system 4.7Adding details of the student 4.8Apprentice tracking 4.9Skills requirements 4.10Developing database for marketing 4.11Milestone 4: Development completion 5Testing phase 5.1Performance testing 5.2Black box testing 5.3User acceptance testing
11 PROJECT MANAGEMENT 5.4White box testing 5.5User-acceptability testing 5.6Milestone 5: Completion of testing phase 6Closing Phase 6.1Post project review 6.2Stakeholder sign off 6.3Milestone 6: Completion of closure phase
12 PROJECT MANAGEMENT 3.3 Project resources Figure 1: Project resource (Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13 PROJECT MANAGEMENT 3.4 Time estimation Figure 2: Time estimation (Source: Created by Author)
14 PROJECT MANAGEMENT 3.5 Project budget Figure 3: Project budget (Source: Created by Author)
15 PROJECT MANAGEMENT 3.6 Time phase budget December 2018 January 2019 February 2019 March 2019April 2019May 2019 $ 0.00 $ 5,000.00 $ 10,000.00 $ 15,000.00 $ 20,000.00 $ 25,000.00 $ 30,000.00 $ 35,000.00 $ 40,000.00 Time-phase budget Cost Figure 4: Time-phase budget (Source: Created by Author) 4. Part Four 4.1 Assumptions The assumptions which are given in the project mainly include: It is assumed that proper computer-based systemdevelopment will be completed within 90 days It is expected that it is quite important to design the architecture of the computer- based system
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16 PROJECT MANAGEMENT 4.2 Project risk and management strategy Ris k ID DescriptionProbabilit y Impac t Rat e Assigne d To Response Strategy Threator Opportunit y R1It is found thatmore amountof moneyis neededin orderto trainthe peoplewho aremainly involved withthe developmen tof computer based system 703210TrainerItis considered asan opportunity asitwill generally bring positive impact on e project. Opportunity R2Thedesign thatis developed forthe entire 905450Project designer It is found thatthe risksas wellas challenges Threat
17 PROJECT MANAGEMENT systemis not appropriate canbe resolved by successfull y developing thedesign ofthe system. R3Ifthe resources of theproject arenot appropriate thenitwill bedifficult to finish the projecton time. 704280Human resource manager The problem canbe resolved by properly estimating thevarious typesof resources whichare generally required. Threat R4Ifthe scheduleof theproject isnot managed 805400TesterIt is quite necessary tomanage theproject schedule Threat
18 PROJECT MANAGEMENT properly thenthe chancesof schedule slippageis quite high. properly so thatthe entire projectcan be completed on time. R5Dueto improper testing,the entire systemwill not function properly. 905450TesterIt is very much necessary tocheck the operation ofthe system properly for preventing the challenges. Threat 5. Part Five Statement on project quality
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19 PROJECT MANAGEMENT It is quite important for the team of the project for maintaining the project quality. The strategies that are generally followed by the team in order to maintain the project quality are generally listed below: It is quite important to define the project quality properly Use of appropriate strategies as well as rules in order to mitigate the issues Use of appropriate tools that are quite helpful in checking the project quality. Set of verification activities Verification activityWhen? Quality testingProject quality testing is generally done in the project testing phase. Undertaking surveyThe survey is conducted by the project team before the project work started. Set of validation activities Validation activityWhen? Requirement testingIn the closure of the project Simulation testingAfter the project testing is completed ROI analysisAfter proper estimation of project budget 6. Part Six 6.1 Annotated Bibliography Refer to appendices. 6.2 Development of closure checklist ActivitiesStatus Does the training session related with theYes
20 PROJECT MANAGEMENT project is completed? Does the project is handed to the client?Yes Does all the project requirements are met?Yes 6.3 Development of project evaluation Evaluation activitiesOption Does proper project quality is maintained?YesNo Does the project work gets completed?YesNo Does the project have appropriate designYesNo
21 PROJECT MANAGEMENT Bibliography Bilgihan, A., & Bujisic, M. (2015). The effect of website features in online relationship marketing: A case of online hotel booking.Electronic Commerce Research and Applications,14(4), 222-232. Bilgihan, A., Nusair, K., Okumus, F., & Cobanoglu, C. (2015). Applying flow theory to booking experiences: An integrated model in an online service context.Information & Management,52(6), 668-678. Binder,J.(2016).Globalprojectmanagement:communication,collaborationand management across borders. Routledge. Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014).Peer learning in higher education: Learning from and with each other. Routledge. Eskerod, P., Huemann, M., & Savage, G. (2015). Project stakeholder management—past and present.Project Management Journal,46(6), 6-14. Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute. Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute. Harrison, F., & Lock, D. (2017).Advanced project management: a structured approach. Routledge. Heagney, J. (2016).Fundamentals of project management. AMACOM Div American Mgmt Assn.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
22 PROJECT MANAGEMENT Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Martens, M. L., & Carvalho,M. M. (2017). Key factorsof sustainabilityin project management context: A survey exploring the project managers' perspective.International Journal of Project Management,35(6), 1084-1102. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217. Zwikael, O. (2016). International journal of project management special issue on “project benefit management.
23 PROJECT MANAGEMENT Appendices Appendix 1: Annotated Bibliography Article 1:Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management:linkingprojectmanagementperformanceandproject success.International journal of project management,32(2), 202-217. The article mainly reflects on the PM based literatures and it is found that though the advancement within the process of PM and project-based techniques and tools, it is generally found that the success or achievement of the project has not been improved. This problem that generally persists generally raise lot of questions that are related with the effectiveness and value of PM as well as different types of PM based systems. The paper generally helps in reporting a research study that helps in testing the relation that is mainly present between the performance as well as success of the project. Furthermore, it is analyzed that relationship generally helps in drawing empirical data on the various project management professionals. The article further helps in suggesting that validated framework is mainly used for measuring the performance as well as success of the project. For this, it is found that around 54 questionnaires are generally analyzed. It is identified that Bi-variate correlation as well as number of different types of regression tests are generally conducted that further helps in developing a positive influence on the performance of PM. In addition to this, it is identified that there are number of variable relationships that have not been identified as well as elaborated between the various individual variables of PM performance as well as on the project success. Article 2:Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world.International Journal of Project Management,33(2), 278-290.
24 PROJECT MANAGEMENT The paper generally presents the entire results of the structured review of the project management which is generally dependent on the classification as well as analysis of the various types of contributions It is found that additionally it takes a proper critical look. Moreover, it is found that as the analysis was mainly conducted on six different types of overreaching categories that has generally emerged which mainly includes conceptualization, political aspects as well as rethinking practice and more. It is found that all this type of categories that are generally identified over a range of various contributions have generally drivers. It is found that a proper look on the new world generally helps in exhibiting the entire challenge of RPM for becoming one of the more diffused as well as accepted. Article3:Hornstein,H.A.(2015).Theintegrationofprojectmanagementand organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. This article mainly focuses on the integration of entire PM with the organizational change management which is considered as a necessity. It is identified that the managers as well as the training is provided to the new project managers are generally considered as one off the impact of the entire organizational change as well as due to the failure of the entire project implementation. It is analyzed that this particular case generally needsthe project managers inorder to become very much conversant with the change with the organization that is generally made by the author faster reviewinglot of various types of supportive literature. In addition to this, it is found that project management generally helps in certifying the various types of agencies including PMI and IPMA.