Running head: PROJECT MANAGEMENT Relocation of the family to Perth Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 PROJECT MANAGEMENT Table of Contents 1. Overview of the project scenario...........................................................................................2 2. Assumptions and criteria that is used for preparing the milestone plan and task list of the project.........................................................................................................................................2 3. Milestone plan........................................................................................................................3 4. List of tasks and the responsible person.................................................................................3 5. Gantt chart..............................................................................................................................3 6. Details and reason of adjustment...........................................................................................3 7. Personal reflection of the process..........................................................................................8 References................................................................................................................................10 Appendices...............................................................................................................................12 Appendix 1: Milestone.........................................................................................................12 Appendix 2: List of task and responsible person.................................................................12 Appendix 3: Gantt chart.......................................................................................................13
2 PROJECT MANAGEMENT 1. Overview of the project scenario This reportshowcases the preparation of a schedule for a relocation case scenario. The main aim of the report is to develop a plan including all the project activities for moving the entire family along with their stuffs to a new location in Perth as Jeff has received a new position within an organization in Perth. The entire family of Jeff mainly includes four members including Jeff, his wife Kelly and two children Lexie and Will. In addition to this, the family have two cars and a dog. Presently the family is living in a two-bedroom flat in Queensland and as Jeff has secured a new job, he wants to relocate with his family to a four- bed room flat in Perth. The actual date for emptying the house that is in Queensland will be around 20thJanuary whereas the new house will be generally commenced on January 27th. The cost that is required for moving to the new city will be around $15,000. In addition to this, all the information that are provided are generally compiled for inspecting as well as for making the necessary changes for meeting the requirements of the family within the assumed budget. 2. Assumptions and criteria that is used forthe preparation of the task list and milestone plan of the project The assumptions as well as criteria on which proper focus is made for the preparation of the milestone plan as well as task list for the project is provided in the table below: Budget:The cost that is generally needed for relocating the family to Perth from sunshine coast will be assumed to be around $15,000. All the project activities need to be executed within the budget that is sponsored for avoiding the problems as well as issues that mainly occurs due to the rise in the budget of the project.
3 PROJECT MANAGEMENT Time:Time is considered as one of the important aspects for the effective project completion. The project manager generally makes an assumption according to which the entire project of relocation will be done on time so that the children’s can be able to join their school on 31stJanuary and Jeff can start his office in Perth from 5thFebruary successfully. It is quite necessary to proceed as per the assumption because it is quite important for the children of Jeff to Resource availability:The resources which are mainly required forrelocatingthe family to a new location in Perth and the human resources who are engaged with the project must be present when pre-relocation or post-relocation activities of the project are performed. This criterion of the project is considered to be essential as proper resource availability within the project generally helps in completing the work of the project quite successfully. 3. Milestone plan Refer to appendix 1 4. List of tasks and the responsible person Refer to appendix 2 5. Gantt chart Refer to appendix 3 6. Details and reason of adjustment The project that reflects on relocation helps in showcasing that Jeff needs to vacate his present house by January 20thhowever the provided date for the hew apartment inauguration will be on 27thJanuary and as Jeff do not have family or relatives in the city of Perth, the family needs to focus on the commencement of the new apartment successfully. For this, the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 PROJECT MANAGEMENT project planner needs to make some important adjustment are required within the project schedule. The changes that are mainly done in the entire schedule is mainly reflected below: Adjustmentinthetime:Theprojectplannermainlyaimstofinishthe commencement of the new apartment as soon as possible such that the Jeff’s family can move to the new location in the city of Perth after vacating their old house in Queensland. As the commencement of the project is assumed to be done by 20thJanuary thus the family of Jeff does not have to stay in hotel and they will be able to properly move .to the new city on time. Adjustment in the cost:New house commencement will be done within 20thJanuary 2018 as per the assumption that is made and therefore the family will not spend money on the hotel and therefore the money that is needed for hotel expense will get saved. Moreover, it is found that the budget that is generally required for completing relocation will be less as compared to the budget that is generally required as per the initial plan of the project. The changes that are done in the project schedule will be shown below in the table by using yellow colour. Moreover, the table helps in showcasing the duration as well as cost that is associated with relocation generally reduces as compared to the previous schedule of the project. The changes that are done in the project schedule are mainly reflected below: WBSTask NameDurationStartFinishPredecessors Resource Names Cost 0 New schedule with the adjustments for relocation 28 days Sun 30-12- 18 Sat 26- 01-19 $13,704.00
5 PROJECT MANAGEMENT 1 Project initiation phase 6 days Sun 30-12- 18 Fri 04- 01-19 $0.00 1.1 Making plan for relocation 1 day Sun 30-12- 18 Sun 30- 12-18 Jeff and Kelly$0.00 1.2 Determining the date on which shift will be done 1 day Mon 31-12- 18 Mon 31-12- 18 2Jeff and Kelly$0.00 1.3 Consulting with the planner 3 days Tue 01-01- 19 Thu 03-01- 19 3Jeff and Kelly$0.00 1.4 Confirming the date for shifting 1 day Fri 04- 01-19 Fri 04- 01-19 4Jeff and Kelly$0.00 M1 Milestone1: Initiation phase completion 0 days Fri 04- 01-19 Fri 04- 01-19 5$0.00 2 Project planning phase 7 days Sat 05- 01-19 Fri 11- 01-19 $4,480.00 2.1 Determining the activities of the project 1 day Sat 05- 01-19 Sat 05- 01-19 6 Project planner $640.00 2.2Developing schedule for the 2 daysSun 06-01- Mon 07-01- 8Project$1,280.00
6 PROJECT MANAGEMENT purpose of relocation 1919planner 2.3 Contingency planning 3 days Tue 08-01- 19 Thu 10-01- 19 9 Project planner $1,920.00 2.4 Allocating the resources which are needed 1 day Fri 11- 01-19 Fri 11- 01-19 10 Project planner $640.00 M2 Milestone 2: Getting approval 0 days Fri 11- 01-19 Fri 11- 01-19 11$0.00 3 Relocation activities 9 days Sat 12- 01-19 Sun 20-01- 19 $5,496.00 3.1 Movers and packers are identified 1 day Sat 12- 01-19 Sat 12- 01-19 12Jeff and Kelly$0.00 3.2 Needed belongings must be identified 2 days Sun 13-01- 19 Mon 14-01- 19 14 Packers, Packaging Cost [1] $2,176.00 3.3 Items selling which are not needed 3 days Sun 13-01- 19 Tue 15- 01-19 14 Project planner $1,920.00 3.4Getting pre- mortgage 2 daysWed 16-01- Thu 17-01- 16Jeff and Kelly, Mortgage Cost $900.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 PROJECT MANAGEMENT 1919[1] 3.5 Applying for the school 2 days Fri 18- 01-19 Sat 19- 01-19 17Jeff and Kelly$0.00 3.6 Relocation to the old department 1 day Sun 20-01- 19 Sun 20- 01-19 18 Transportation Cost [1] $500.00 M3 Milestone 3: Vacating the old house 0 days Sun 20-01- 19 Sun 20- 01-19 19$0.00 4Post-relocation6 days Sun 20-01- 19 Sat 26- 01-19 $3,728.00 4.1 Moving to hotel 0 days Sun 20-01- 19 Sun 20- 01-19 20Hotel cost [0]$0.00 4.2 Moving to new house 1 day Mon 21-01- 19 Mon 21-01- 19 22Jeff and Kelly$0.00 4.3 Shifting commodities and unpacking items 2 days Tue 22-01- 19 Wed 23-01- 19 23Packers$1,376.00 4.4 Aligning the day to day project activities 3 days Thu 24-01- 19 Sat 26- 01-19 24Movers$2,352.00
8 PROJECT MANAGEMENT M4 Milestone 4: Project closure 0 days Wed 23-01- 19 Wed 23-01- 19 24$0.00 7. Personal reflection of the process After engaging within the project, I have analyzed that the relocation of the family from Queensland to Perth is done successfully so that the family can easily move to the new house after vacating their old house. The adjustments as well as changes which are needed to be include in the project schedule for meeting the goals and objectives of the project helps in reflecting that the various changes that are mainly needed within the project schedule must be handled effectively. It is found that the project team needs to use proper tools as well as process for handling the changes by finishing the project on schedule. Moreover, the information about team management that I have gained will help me in my future projects. The experience that I have gained through the help of this project will be used my me in handling similar types of project accurately. Moreover, it is found that proper assumptions are generally made before the initiation of the project and as a result the team needs to complete the project as per the assumption which is considered as one of the crucial points for the project planners. It is very much necessary for the project team to get involved within the project and uses proper assumptions that are needed for successfully completing the project. Thus, I have analyzed that the entire skills and information that I have gained through the help of this particular project will be helpful for me in the upcoming future such that I can be able to handle the project quite effectively and will be able to execute the project within the assumed deadline of the project.
9 PROJECT MANAGEMENT References Chen, H.L., Chen, W.T. and Lin, Y.L., 2016. Earned value project management: Improving the predictive power of planned value.International Journal of Project Management,34(1), pp.22-29. De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effectson project success: Cross-country and cross-industry comparisons.International Journal of Project Management,33(7), pp.1509-1522. Ekrot, B., Kock, A. and Gemünden, H.G., 2016. Retaining project management competence —Antecedentsandconsequences.InternationalJournalofProjectManagement,34(2), pp.145-157. Hoda, R. and Murugesan, L.K., 2016. Multi-level agile project management challenges: A self-organizing team perspective.Journal of Systems and Software,117, pp.245-257. Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts.International Journal of Project Management,33(6), pp.1377-1392. Kerzner,H.,2017.Projectmanagementmetrics,KPIs,anddashboards:aguideto measuring and monitoring project performance. John Wiley & Sons. Kivilä, J., Martinsuo, M. and Vuorinen, L., 2017. Sustainable project management through projectcontrolininfrastructureprojects.InternationalJournalofProject Management,35(6), pp.1167-1183. Martens,M.L.andCarvalho,M.M.,2017.Keyfactorsofsustainabilityinproject management context: A survey exploring the project managers' perspective.International Journal of Project Management,35(6), pp.1084-1102.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 PROJECT MANAGEMENT Sánchez, M.A., 2015. Integrating sustainability issues into project management.Journal of Cleaner Production,96, pp.319-330. Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature reviewwitha criticallookatthebravenewworld.InternationalJournalofProject Management,33(2), pp.278-290. Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015. Projectsuccessanalysisframework:Aknowledge-basedapproachinproject management.International Journal of Project Management,33(4), pp.772-783. Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research.International journal of project management,34(7), pp.1214-1225.
11 PROJECT MANAGEMENT Appendices Appendix 1: Milestone MilestoneCompletion date Milestone1: Initiation phase completionFri 04-01-19 Milestone 2: Getting approvalFri 11-01-19 Milestone 3: Vacating the old houseSun 20-01-19 Milestone 4: Project closureTue 29-01-19 Appendix 2: List of task and responsible person Figure 1: List of task and responsible person (Source: Created by Author)
12 PROJECT MANAGEMENT Appendix 3: Gantt chart Figure 2: Gantt chart (Source: Created by Author)