This assignment delves into the project management aspects of Carillion's downfall. It requires a detailed analysis of the company's project management practices, focusing on areas like budget allocation, risk management strategies, and team structure. The analysis should highlight the specific shortcomings that contributed to Carillion's financial troubles and eventual collapse.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT REPORT
Project Management Report
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT REPORT
Table of Contents
Introduction......................................................................................................................................2
1. Background and Scope of Event..................................................................................................2
1.1 Project Background...............................................................................................................2
1.2 Scope of the Project...............................................................................................................2
1.3 Objectives of the project........................................................................................................3
2. Event Objectives..........................................................................................................................3
3. Entertainment Activities..............................................................................................................4
4. Target Audience...........................................................................................................................4
5. Event Deliverables.......................................................................................................................4
6. Project Management Tools and Techniques................................................................................4
6.1 Project Schedule in table format............................................................................................5
6.2 Gantt chart for the project......................................................................................................9
6.3 Critical Path for the project..................................................................................................10
6.4 Planning Chart Diagram for the project...............................................................................12
7. Project Team Management and Structure..................................................................................13
8. Budget for the Project................................................................................................................13
9. Awareness of Potential Risk Factors.........................................................................................15
10. Evaluation and Control of your Project...................................................................................16
Conclusion.....................................................................................................................................16
Bibliography..................................................................................................................................18
Document Page
2PROJECT MANAGEMENT REPORT
Introduction
The project of hosting a music event in London was implied for forming the use of the
project management principles and processes. According to Kerzner (2013), the implication of
the theories of project management would employ the development of the improved operational
processing. The integration has provided scope for the development of the smart and effective
alignment of the operations. The event of musical show was aligned well with the development
of the improved processes. The implication of the project would align to the integration of the
effective processing and development (Coombs 2014). The alignment of the profound
development would help in forming the alignment of the project integration and development.
The following assignment would allow the analysis of the project for developing a report
that would include background of the project, project scope, objectives of the project,
identification of the target audience, tools and project methodology analysis, team management,
project budget, and risk management. The assignment would cover the use of the Ms-Project for
the development of the project schedule. The cost estimation and the budget would be developed
for ensuring that project is completed in the expected time and budget.
1. Background and Scope of Event
1.1 Project Background
The project is developed for planning a schedule and implying it for successful
completion of the event of the music festival. The implementation of the project would be
helpful for ensuring the deployment of the project analysis and development (Cicmil et al. 2017).
The profound development of the project would be helpful in integrating the functions of the
project of music event in London. The music event in London is held for the music lovers and it
consists of a number of artists performing at the event. The event would be held in an open space
where a number of artists and performers would perform and the project would involve the
deployment of the projects.
Document Page
3PROJECT MANAGEMENT REPORT
1.2 Scope of the Project
The project of organizing London Music Festival is an event program that holds an
integral part in terms of entertainment business and development. The project aligns for the
development of the specific and improved functions of the project. The scope of the project can
be divided into two parts namely in-scope and out of scope.
In-scope items: The in-scope items of the project include the project plan that consists of
the development of the schedule and its integration for the alignment of the project. The cost
management, risk management, and event alignment is helpful for the successful completion of
the project.
Out of scope items: The out of scope items of the project of organizing London Music
Festival are the change management plan, communication plan, and the transportation of the
materials. Moreover, the activities of the contractor are another major factor that would not be
considered in this project.
1.3 Objectives of the project
The project objectives for the project of organizing London Music Festival are given below,
To develop a project plan along with schedule for the development of the successful
project completion
To form the analysis of the project integration and alignment of the plan of the project
development
To implement the plan for the successful holding the event of the London Music
Festival for the people
2. Event Objectives
The event of the London Music Festival is helpful for the holding an event where many
musicians get to perform and entertain thousands of people live. The objectives of the event are,

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT REPORT
To entertain people and music lovers by providing them scope for listening to
many talented musicians and singers
To help the musicians and singers for performing live for the audiences and make
a name for them
To relieve the people of their daily stress by providing them 3 day entertainment
from the music performances
3. Entertainment Activities
The music festival event in London is developed for the alignment of the profound
development of the system integration and development. The entertainment activities are aligned
for the formation of entertainment of the project integration and management (Hegazy 2013).
The music concerts and shows would be held for ensuring that the people get relieved of the
work pressure and the music lovers can enjoy the event successfully.
4. Target Audience
The target audience of the project consists of the development of the specifically aligned
people who are interested in project. The deliverance of the project would ensure that most of the
music lovers and people would get time to form the alignment of the project. The audiences of
the project would also involve the sponsors and other potential investors of the event.
5. Event Deliverables
The deliverables of the event of Music Festival in London include,
a) Music Concerts and Shows for entertaining people and relieving them from their stressed
life
b) Gathering sponsors of the project for ensuring that the next event can be done on a larger
scale
c) Formation of the specific deliverance of the successful event completion
6. Project Management Tools and Techniques
Document Page
5PROJECT MANAGEMENT REPORT
The project management for the project of “Music Festival Event in London” can be done
by forming the specific project schedule. The project developed would ensure that all
performances are aligned in a specific timeline without overlapping each other and the
participants must follow them for the successful completion of the Music festival event. The
festival lasted for 3 days and the program had been running successfully. There are various
vendors that have set their food and beverage stalls at the event location. According to Nicholas
and Steyn (2017), the Gantt chart, critical path, and Planning chart has been made by using the
Ms-Project Software for ensuring that the project would be completed successfully.
6.1 Project Schedule in table format
The project schedule for the project of Music Festival Event in London is given in the
table format below,
WBS Task Name Duration Start Finish
0 Music Festival Event in London 57 days Mon 1/15/18 Wed 4/4/18
1 Project Initiation 10 days Mon 1/15/18 Fri 1/26/18
1.1 Analysis of the requirements 2 days Mon 1/15/18 Tue 1/16/18
1.2 Developing initiation Plan 3 days Wed 1/17/18 Fri 1/19/18
1.3 Charter Documents are made 2 days Mon 1/22/18 Tue 1/23/18
1.4 Submitting the documents made 1 day Wed 1/24/18 Wed 1/24/18
1.5 Signing the documents 1 day Thu 1/25/18 Thu 1/25/18
1.6 Project Kick off 1 day Fri 1/26/18 Fri 1/26/18
2 Project Planning 13 days Mon 1/22/18 Wed 2/7/18
2.1 Selecting plan methodology 2 days Mon 1/22/18 Tue 1/23/18
2.2 Developing Plan Outline 3 days Wed 1/24/18 Fri 1/26/18
2.3 Plan is reviewed 2 days Mon 1/29/18 Tue 1/30/18
Document Page
6PROJECT MANAGEMENT REPORT
2.4 Plan is completed 5 days Wed 1/31/18 Tue 2/6/18
2.5 Plan is approved 1 day Wed 2/7/18 Wed 2/7/18
3 Project Execution 31 days Thu 2/8/18 Fri 3/23/18
3.1 Management Activities for Music
Event 20 days Thu 2/8/18 Wed 3/7/18
3.1.1 Scope Development 2 days Thu 2/8/18 Fri 2/9/18
3.1.2 Team Structure is built 3 days Mon 2/12/18 Wed 2/14/18
3.1.3 Activities are assigned to the team
members 3 days Thu 2/15/18 Mon 2/19/18
3.1.4 Communication Plan is developed 5 days Mon 2/12/18 Fri 2/16/18
3.1.5 Risk Management is applied 6 days Mon 2/19/18 Mon 2/26/18
3.1.6 Scope Management is developed 3 days Tue 2/27/18 Thu 3/1/18
3.1.7 Marketing and Promotion 4 days Fri 3/2/18 Wed 3/7/18
3.2 Site Development 20 days Tue 2/20/18 Mon 3/19/18
3.2.1 Selection of event site 1 day Tue 2/20/18 Tue 2/20/18
3.2.2 Getting Site Approval 1 day Wed 2/21/18 Wed 2/21/18
3.2.3 Site Cleaning 3 days Thu 2/22/18 Mon 2/26/18
3.2.4 Infrastructure is developed 4 days Tue 2/27/18 Fri 3/2/18
3.2.5 Stage is formed 2 days Mon 3/5/18 Tue 3/6/18
3.2.6 Seats and Lights are aligned 3 days Wed 3/7/18 Fri 3/9/18
3.2.7 Sound system is formed 2 days Mon 3/12/18 Tue 3/13/18
3.2.8 Pyros and Cameras are added 2 days Wed 3/14/18 Thu 3/15/18
3.2.9 Safety and Medical Kit is installed 2 days Fri 3/16/18 Mon 3/19/18
3.3 Invitation and Arrangements 18 days Tue 2/20/18 Thu 3/15/18

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT REPORT
3.3.1 Making guests lists 1 day Tue 2/20/18 Tue 2/20/18
3.3.2 Sending invitation via emails, calls, or
face ot face talk 2 days Wed 2/21/18 Thu 2/22/18
3.3.3 Getting RSVPs of the guests 2 days Fri 2/23/18 Mon 2/26/18
3.3.4 Sorting the performers and Artists
participating in the event 3 days Tue 2/27/18 Thu 3/1/18
3.3.5 Providing them program schedule 1 day Fri 3/2/18 Fri 3/2/18
3.3.6 Making seating arrangements 2 days Mon 3/5/18 Tue 3/6/18
3.3.7 Making arrangements for contestants 2 days Wed 3/7/18 Thu 3/8/18
3.3.8 5 days practice session 5 days Fri 3/9/18 Thu 3/15/18
3.4 Music Event 3 days Tue 3/20/18 Fri 3/23/18
3.4.1 First Day of the Music Festival 1 day Tue 3/20/18 Tue 3/20/18
3.4.1.1 Welcoming all to the event 45 mins Tue 3/20/18 Tue 3/20/18
3.4.1.2 First Half of the Music event 3.25 hrs Tue 3/20/18 Tue 3/20/18
3.4.1.3 Refreshment break 45 mins Tue 3/20/18 Tue 3/20/18
3.4.1.4 Second half of the event 3.25 hrs Tue 3/20/18 Tue 3/20/18
3.4.2 Second Day of the Music event 1 day Wed 3/21/18 Thu 3/22/18
3.4.2.1 First Half of the Music event 3.8 hrs Wed 3/21/18 Wed 3/21/18
3.4.2.2 Refreshment break 25 mins Wed 3/21/18 Wed 3/21/18
3.4.2.3 Second half of the event 3.8 hrs Wed 3/21/18 Thu 3/22/18
3.4.3 Last Day of the Music Event 1 day Thu 3/22/18 Fri 3/23/18
3.4.3.1 First Half of the Music event 3.5 hrs Thu 3/22/18 Thu 3/22/18
3.4.3.2 Refreshment break 30 mins Thu 3/22/18 Thu 3/22/18
3.4.3.3 Second half of the event 3.5 hrs Thu 3/22/18 Thu 3/22/18
Document Page
8PROJECT MANAGEMENT REPORT
3.4.3.4 Thank you 30 mins Thu 3/22/18 Fri 3/23/18
3.4.4 Event Completed 0 days Fri 3/23/18 Fri 3/23/18
4 Final documentation and Closure 8 days Fri 3/23/18 Wed 4/4/18
4.1 Final Documents are made 3 days Fri 3/23/18 Wed 3/28/18
4.2 Checklist is evaluated 2 days Wed 3/28/18 Fri 3/30/18
4.3 Feedbacks of the audience is analyzed 2 days Fri 3/30/18 Tue 4/3/18
4.4 Project is closed 1 day Tue 4/3/18 Wed 4/4/18
Table 1: Project Schedule in Table Format
(Source: Created by the author)
Document Page
9PROJECT MANAGEMENT REPORT
6.2 Gantt chart for the project
The Gantt chart for the project of Music Festival Event in London is shown in the diagram below,
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Music Festival Event in London 57 days Mon 1/15/18 Wed 4/4/18
1 1 Project Initiation 10 days Mon 1/15/18 Fri 1/26/18
2 1.1 Analysis of the requirements 2 days Mon 1/15/18 Tue 1/16/18
3 1.2 Developing initiation Plan 3 days Wed 1/17/18 Fri 1/19/18
4 1.3 Charter Documents are made 2 days Mon 1/22/18 Tue 1/23/18
5 1.4 Submitting the documents made 1 day Wed 1/24/18 Wed 1/24/18
6 1.5 Signing the documents 1 day Thu 1/25/18 Thu 1/25/18
7 1.6 Project Kick off 1 day Fri 1/26/18 Fri 1/26/18
8 2 Project Planning 13 days Mon 1/22/18 Wed 2/7/18
9 2.1 Selecting plan methodology 2 days Mon 1/22/18 Tue 1/23/18
10 2.2 Developing Plan Outline 3 days Wed 1/24/18 Fri 1/26/18
11 2.3 Plan is reviewed 2 days Mon 1/29/18 Tue 1/30/18
12 2.4 Plan is completed 5 days Wed 1/31/18 Tue 2/6/18
13 2.5 Plan is approved 1 day Wed 2/7/18 Wed 2/7/18
14 3 Project Execution 31 days Thu 2/8/18 Fri 3/23/18
15 3.1 Management Activities for Music Event 20 days Thu 2/8/18 Wed 3/7/18
16 3.1.1 Scope Development 2 days Thu 2/8/18 Fri 2/9/18
17 3.1.2 Team Structure is built 3 days Mon 2/12/18 Wed 2/14/18
18 3.1.3 Activities are assigned to the team members 3 days Thu 2/15/18 Mon 2/19/18
19 3.1.4 Communication Plan is developed 5 days Mon 2/12/18 Fri 2/16/18
20 3.1.5 Risk Management is applied 6 days Mon 2/19/18 Mon 2/26/18
21 3.1.6 Scope Management is developed 3 days Tue 2/27/18 Thu 3/1/18
22 3.1.7 Marketing and Promotion 4 days Fri 3/2/18 Wed 3/7/18
23 3.2 Site Development 20 days Tue 2/20/18 Mon 3/19/18
24 3.2.1 Selection of event site 1 day Tue 2/20/18 Tue 2/20/18
25 3.2.2 Getting Site Approval 1 day Wed 2/21/18 Wed 2/21/18
26 3.2.3 Site Cleaning 3 days Thu 2/22/18 Mon 2/26/18
27 3.2.4 Infrastructure is developed 4 days Tue 2/27/18 Fri 3/2/18
28 3.2.5 Stage is formed 2 days Mon 3/5/18 Tue 3/6/18
29 3.2.6 Seats and Lights are aligned 3 days Wed 3/7/18 Fri 3/9/18
30 3.2.7 Sound system is formed 2 days Mon 3/12/18 Tue 3/13/18
31 3.2.8 Pyros and Cameras are added 2 days Wed 3/14/18 Thu 3/15/18
32 3.2.9 Safety and Medical Kit is installed 2 days Fri 3/16/18 Mon 3/19/18
33 3.3 Invitation and Arrangements 18 days Tue 2/20/18 Thu 3/15/18
34 3.3.1 Making guests lists 1 day Tue 2/20/18 Tue 2/20/18
35 3.3.2 Sending invitation via emails, calls, or face ot face
talk
2 days Wed 2/21/18 Thu 2/22/18
36 3.3.3 Getting RSVPs of the guests 2 days Fri 2/23/18 Mon 2/26/18
37 3.3.4 Sorting the performers and Artists participating in
the event
3 days Tue 2/27/18 Thu 3/1/18
38 3.3.5 Providing them program schedule 1 day Fri 3/2/18 Fri 3/2/18
39 3.3.6 Making seating arranagements 2 days Mon 3/5/18 Tue 3/6/18
40 3.3.7 Making arrangements for contestants 2 days Wed 3/7/18 Thu 3/8/18
41 3.3.8 5 days practice session 5 days Fri 3/9/18 Thu 3/15/18
42 3.4 Music Event 3 days Tue 3/20/18 Fri 3/23/18
43 3.4.1 First Day of the Music Festival 1 day Tue 3/20/18 Tue 3/20/18
44 3.4.1.1 Welcoming all to the event 45 mins Tue 3/20/18 Tue 3/20/18
45 3.4.1.2 First Half of the Music event 3.25 hrs Tue 3/20/18 Tue 3/20/18
46 3.4.1.3 Refreshment break 45 mins Tue 3/20/18 Tue 3/20/18
47 3.4.1.4 Second half of the event 3.25 hrs Tue 3/20/18 Tue 3/20/18
48 3.4.2 Second Day of the Music event 1 day Wed 3/21/18 Thu 3/22/18
49 3.4.2.1 First Half of the Music event 3.8 hrs Wed 3/21/18 Wed 3/21/18
50 3.4.2.2 Refreshment break 25 mins Wed 3/21/18 Wed 3/21/18
51 3.4.2.3 Second half of the event 3.8 hrs Wed 3/21/18 Thu 3/22/18
52 3.4.3 Last Day of the Music Event 1 day Thu 3/22/18 Fri 3/23/18
53 3.4.3.1 First Half of the Music event 3.5 hrs Thu 3/22/18 Thu 3/22/18
54 3.4.3.2 Refreshment break 30 mins Thu 3/22/18 Thu 3/22/18
55 3.4.3.3 Second half of the event 3.5 hrs Thu 3/22/18 Thu 3/22/18
56 3.4.3.4 Thank you 30 mins Thu 3/22/18 Fri 3/23/18
57 3.4.4 Event Completed 0 days Fri 3/23/18 Fri 3/23/18
58 4 Final documentation and Closure 8 days Fri 3/23/18 Wed 4/4/18
59 4.1 Final Documents are made 3 days Fri 3/23/18 Wed 3/28/18
60 4.2 Checklist is evaluated 2 days Wed 3/28/18 Fri 3/30/18
61 4.3 Feedbacks of the audience is analyzed 2 days Fri 3/30/18 Tue 4/3/18
62 4.4 Project is closed 1 day Tue 4/3/18 Wed 4/4/18
Analyst
Planner
Documenter
Documenter
Project Manager
Project Manager
Planner
Planner
Project Manager
Planner
Project Manager
HR Manager
Project Manager
Project Manager
Planner
HR Manager
HR Manager
HR Manager
Client
Project Manager
Contractor
Contractor
Workers
Workers
Workers
Workers
Workers
Event Coordinator
Event Coordinator
Event Coordinator
Event Coordinator
Event Coordinator
Contractor
Contractor
Participants
Speaker
Participants
Audience
Participants
Participants
Audience
Participants
Participants
Audience
Participants
Speaker
3/23
Documenter
Event Coordinator
Event Coordinator
Project Manager
F S S M T W T
Dec 10, '17 Jan 28, '18 Mar 18, '18 May 6, '18
Figure 1: Gantt chart for the project

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT REPORT
(Source: Created by the author)
6.3 Critical Path for the project
The critical path (highlighted in yellow colour) for the project of Music Festival Event in London is shown in the diagram below,
Music Festival Event in
London
Project Initiation
Analysis of the
requirements
Developing initiation
Plan
Charter Documents
are made
Submitting the
documents made
Signing the
documents
Project Kick off
Project Planning
Selecting plan
methodology
Developing Plan
Outline
Plan is reviewed Plan is completed Plan is approved
Project Execution
Management Activities for
Music Event Scope Development
Team Structure is
built
Activities are
assigned to the team
members
Communication Plan
is developed
Risk Management is
applied
Scope Management is
developed
Marketing and
Promotion
Site Development
Selection of event
site
Getting Site
Approval Site Cleaning
Infrastructure is
developed
Stage is formed Seats and Lights are
aligned
Sound system is
formed
Pyros and Cameras
are added
Safety and Medical
Kit is installed
Invitation and
Arrangements Making guests lists
Sending invitation
via emails, calls, or
face ot face talk
Getting RSVPs of
the guests
Sorting the
performers and
Artists participating
in the event
Providing them
program schedule
Making seating
arranagements
Making
arrangements for
contestants
5 days practice
session
Music Event
First Day of the Music
Festival
Welcoming all to the
event
First Half of the
Music event
Refreshment break Second half of the
event
Second Day of the Music
event
First Half of the
Music event
Refreshment break Second half of the
event
Last Day of the Music
Event
First Half of the
Music event Refreshment break
Second half of the
event
Thank you
Event Completed
Final documentation and
Closure
Final Documents are
made
Checklist is
evaluated
Feedbacks of the
audience is analyzed
Project is closed
Figure 2: Critical Path Diagram of the Project
(Source: Created by the author)
Document Page
11PROJECT MANAGEMENT REPORT
The Gantt chart highlighting the critical path (in yellow colour in table and red bars in the timeline of the Gantt chart) for the project of Music Festival Event in London is shown in the diagram below,
ID Task
Mode
WBS Task Name
0 0 Music Festival Event in London
1 1 Project Initiation
2 1.1 Analysis of the requirements
3 1.2 Developing initiation Plan
4 1.3 Charter Documents are made
5 1.4 Submitting the documents made
6 1.5 Signing the documents
7 1.6 Project Kick off
8 2 Project Planning
9 2.1 Selecting plan methodology
10 2.2 Developing Plan Outline
11 2.3 Plan is reviewed
12 2.4 Plan is completed
13 2.5 Plan is approved
14 3 Project Execution
15 3.1 Management Activities for Music Event
16 3.1.1 Scope Development
17 3.1.2 Team Structure is built
18 3.1.3 Activities are assigned to the team members
19 3.1.4 Communication Plan is developed
20 3.1.5 Risk Management is applied
21 3.1.6 Scope Management is developed
22 3.1.7 Marketing and Promotion
23 3.2 Site Development
24 3.2.1 Selection of event site
25 3.2.2 Getting Site Approval
26 3.2.3 Site Cleaning
27 3.2.4 Infrastructure is developed
28 3.2.5 Stage is formed
29 3.2.6 Seats and Lights are aligned
30 3.2.7 Sound system is formed
31 3.2.8 Pyros and Cameras are added
32 3.2.9 Safety and Medical Kit is installed
33 3.3 Invitation and Arrangements
34 3.3.1 Making guests lists
35 3.3.2 Sending invitation via emails, calls, or face ot face
talk
36 3.3.3 Getting RSVPs of the guests
37 3.3.4 Sorting the performers and Artists participating in
the event
38 3.3.5 Providing them program schedule
39 3.3.6 Making seating arranagements
40 3.3.7 Making arrangements for contestants
41 3.3.8 5 days practice session
42 3.4 Music Event
43 3.4.1 First Day of the Music Festival
44 3.4.1.1 Welcoming all to the event
45 3.4.1.2 First Half of the Music event
46 3.4.1.3 Refreshment break
47 3.4.1.4 Second half of the event
48 3.4.2 Second Day of the Music event
49 3.4.2.1 First Half of the Music event
50 3.4.2.2 Refreshment break
51 3.4.2.3 Second half of the event
52 3.4.3 Last Day of the Music Event
53 3.4.3.1 First Half of the Music event
54 3.4.3.2 Refreshment break
55 3.4.3.3 Second half of the event
56 3.4.3.4 Thank you
57 3.4.4 Event Completed
58 4 Final documentation and Closure
59 4.1 Final Documents are made
60 4.2 Checklist is evaluated
61 4.3 Feedbacks of the audience is analyzed
62 4.4 Project is closed
Analyst
Planner
Documenter
Documenter
Project Manager
Project Manager
Planner
Planner
Project Manager
Planner
Project Manager
HR Manager
Project Manager
Project Manager
Planner
HR Manager
HR Manager
HR Manager
Client
Project Manager
Contractor
Contractor
Workers
Workers
Workers
Workers
Workers
Event Coordinator
Event Coordinator
Event Coordinator
Event Coordinator
Event Coordinator
Contractor
Contractor
Participants
Speaker
Participants
Audience
Participants
Participants
Audience
Participants
Participants
Audience
Participants
Speaker
3/23
Documenter
Event Coordinator
Event Coordinator
Project Manager
S T M F T S W S T M F T S W S T M F T S W S T M
Jan 14, '18 Jan 28, '18 Feb 11, '18 Feb 25, '18 Mar 11, '18 Mar 25, '18 Apr 8, '18
Figure 2: Gantt chart showing Critical path of the project
(Source: Created by the author)
Document Page
12PROJECT MANAGEMENT REPORT
6.4 Planning Chart Diagram for the project
The planning chart diagram for the project of Music Festival Event in London is shown in the diagram below,
Music Festival Event in
London
Project Initiation
Analysis of the
requirements
Developing initiation
PlanCharter Documents are
made
Submitting the documents
made
Signing the documents
Project Kick off
Project Planning
Selecting plan
methodology
Developing Plan
OutlinePlan is reviewed
Plan is completed
Plan is approved
Project Execution
Management Activities for
Music Event
Scope Development
Team Structure is built
Activities are assigned to
the team members
Communication Plan is
developed
Risk Management is
applied
Scope Management is
developed
Marketing and Promotion
Site Development
Selection of event site
Getting Site
ApprovalSite Cleaning
Infrastructure is
developed
Stage is formed
Seats and Lights are
aligned
Sound system is formed
Pyros and Cameras are
added
Safety and Medical Kit is
installed
Invitation and
Arrangements
Making guests lists
Sending invitation via
emails, calls, or face ot
face talk
Getting RSVPs of the
guests
Sorting the performers
and Artists participating in
the event
Providing them program
schedule
Making seating
arranagements
Making arrangements for
contestants
5 days practice session
Music Event
First Day of the Music
Festival
Welcoming all to the
eventFirst Half of the Music
event
Refreshment break
Second half of the
event
Second Day of the Music
event
First Half of the Music
event
Refreshment break
Second half of the
event
Last Day of the Music
Event
First Half of the Music
event
Refreshment break
Second half of the
eventThank you
Event
Completed
Final documentation and
Closure
Final Documents are
made
Checklist is evaluated
Feedbacks of the
audience is analyzed
Project is closed
Figure 3: Planning chart diagram for the project
(Source: Created by the author)

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Event
Coordinator
Project Management
Level
Project Governance
Level
Project Operational
Level
Analyst Planner
Documenter
Contractor
Workers
Participants
Audience
Speaker
HR
Manager
Project
Manager
Client
13PROJECT MANAGEMENT REPORT
7. Project Team Management and Structure
The project team structure for the project of Music Festival Event in London consists of
Analyst, Planner, Documenter, Project Manager, HR Manager, Client, Contractor, Workers,
Event Coordinator, Participants, Speaker, and Audience. These project team members are
responsible for the activities of the project and its successful completion (Sears et al. 2015). The
structure of the project team management is given in the diagram below,
8. Budget for the Project
The overall budget for the project of Music Festival Event in London is £70,000.00.
Resource Name Use Cost
Analyst 16 hrs £1,040.00
Planner 144 hrs £10,080.00
Document Page
14PROJECT MANAGEMENT REPORT
Documenter 48 hrs £3,120.00
Project Manager 104 hrs £10,400.00
HR Manager 120 hrs £11,400.00
Contractor 88 hrs £7,920.00
Workers 88 hrs £7,040.00
Event Coordinator 104 hrs £8,840.00
Speaker 1.25 hrs £75.00
Site 1 £5,800.00
Stage & Decorations 1 £1,200.00
Seats 1 £500.00
Lights 1 £500.00
Sound 1 £500.00
Equipments 1 £300.00
First Aid Box 1 £150.00
Fire Extinguisher 1 £120.00
Food & Beverages 3 £990.00
Total £69,975.00
Table 2: Project Budget Estimation
Document Page
15PROJECT MANAGEMENT REPORT
(Source: Created by the author)
9. Awareness of Potential Risk Factors
The project of Organizing the Music Festival at London would be helpful for ensuring the
alignment of the project integration. The risk analysis is formed for ensuring that the project is
formed by eliminating and mitigating the crucial factors that can impact the project in a negative
way (Larson and Gray 2013). The potential risk factors for the project are Delay in Operations,
Cost overrun, technical issues in equipments, lack of transportation of the materials, and medical
emergencies. These risk factors have been explained below,
Delay in Operations: The delay in operations is a primary factor that would tend to be
formed due to the issues in the project (Fleming and Koppelman 2016). The operations of the
project would comprise of developing the specific function to the project team member.
However, due to any reason like the lack of materials, already occupied member, or flaw in the
plan would tend to delay the operation completion.
Cost overrun: The cost overrun is one of the most significant issues in the development
of the music festival event in London. The overall budget of the project has been set to imply for
the project. However, due to the issues of the project there is a probability that the overall cost of
the project would also tend to increase. It would result in the issue of the cost overrun for the
project.
Technical issues in equipments: Music Festival Event in London would consist of a
number of equipments such as cameras, lights, sound system, and other equipments. Any flaw in
any one of the equipment would also result in hindering the successful completion of the event.
It is one of the factors of the risk hazard in terms of operation in the project.
Lack of transportation of the materials: The lack of the transportation medium would
tend to cause the failure of the project. The site development and equipments are a crucial part
for the project of Organizing Music Festival Event in London and the deployment of the event
successfully.
Medical emergencies: The medical emergency is a risk factor that has least possibility of
occurrence. However, its severity is very high and hence it cannot be neglected or ruled out. The

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT REPORT
medical emergencies can be caused when any participant or audience member becomes sick or
injured during the event of the music festival.
10. Evaluation and Control of your Project
The project evaluation and control for the project of organizing the music festival in
London can be done by following the four steps mentioned below,
Step 1 Establishment of the standards: The establishment of the specific standards
would help in forming the development of the expectations from the project (Martin 2017). The
standards set would comprise of the alignment of the project standards. The deployment of the
projects would help the formation of the project alignment.
Step 2 Observation of Performance: The observation of the project would be helpful
for forming the development of the specific project operations (Martinelli and Milosevic 2016).
The observation would also support the implication of the profound development and
integration.
Step 3 Comparison of the actual outcomes: The comparison of the actual
components would be helpful for aligning the systematic activities and ensure that the qualities
of the operations are successfully aligned.
Step 4 Implementing Right action plan: The implementation of the right action plan
is formed for developing the accurate action plan for the project of the organizing the music
festival event in London.
Conclusion
It can be concluded from the assignment that the project management is very essential for
ensuring the development of the project and alignment of the effective management process. The
development of the project integration would allow the users for developing an understanding of
the implication and development requirements of the project. The project of Music Festival
Event in London has been implied for forming the accurate development of the operations and
alignment of the operations of the project. It is highly crucial for the formation of the improved
operation development. The operations of the project are highly imperative for classifying the
Document Page
17PROJECT MANAGEMENT REPORT
development of the effective project report. The summary of the music event had shown that the
project would be aligned for developing the analysis of the effective development of operations.
The management of the operations was helpful for forming the tools and methods for integrating
the project schedules and cost analysis. The project had consisted of the formation of the
effective implementation method. The summarization of the project had been formed with
analysis of the implication and alignment of the project integration. The analysis had been
formed for developing the project team structure and development of the sufficient project
deliverables. The budget allocation and the risk management evaluation had been formed for
inferring that the project would require 57 working days (almost 3 months in total) and an overall
cost of £69,975.00 (approx £70,000.00).
Document Page
18PROJECT MANAGEMENT REPORT
Bibliography
Bury, R. (2017). Carillion under pressure to inject funds amid growing pension concerns.
[online] The Telegraph. Available at: http://www.telegraph.co.uk/business/2017/07/15/carillion-
pressure-inject-funds-amid-growing-pension-concerns/ [Accessed 20 Nov. 2017].
Cicmil, S., Cooke-Davies, T., Crawford, L. and Richardson, K., 2017, April. Exploring the
complexity of projects: Implications of complexity theory for project management practice.
Project Management Institute.
Coombs, W.T., 2014. Ongoing crisis communication: Planning, managing, and responding.
Sage Publications.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Flyvbjerg, B., 2013. From Nobel prize to project management: getting risks right. arXiv preprint
arXiv:1302.3642.
Hegazy, T., 2013. Computer-Based Construction Project Management: Pearson New
International Edition. Pearson Higher Ed.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated
for the 2015 Exam. John Wiley & Sons.
Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS
Project. McGraw-Hill.
Martin, B., 2017. The politics of electricity planning in South Africa: A review of dominant
advocacy coalitions seeking to influence the Integrated Resource Plan of 2010 (IRP2010), and
its update in 2013 (Doctoral dissertation, University of Cape Town).
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19PROJECT MANAGEMENT REPORT
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Pritchard, C.L. and PMP, P.R., 2014. Risk management: concepts and guidance. CRC Press.
Sallis, E., 2014. Total quality management in education. Routledge.
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015. Construction
project management. John Wiley & Sons.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Walker, A., 2015. Project management in construction. John Wiley & Sons.