Unit code:BSBPMG522 Unit name:Undertake project work Nameof the Student: <<Please Fill>> Student ID:<<Please Fill>>
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
P a g e|2 Table of Contents INTRODUCTION..............................................................................................................................................................3 PROJECT CHARTER DOCUMENT..............................................................................................................................3 PROJECT SUMMARY.....................................................................................................................................................3 BUSINESS CASE...............................................................................................................................................................3 PROJECT OBJECTIVES AND OUTCOMES...............................................................................................................3 PROJECT SCOPE STATEMENT...................................................................................................................................3 PROJECT DELIVERABLES...........................................................................................................................................4 EXCLUSIONS....................................................................................................................................................................4 PROJECT TEAM STRUCTURE.....................................................................................................................................4 PROJECT GOVERNANCE STRUCTURE....................................................................................................................5 INTERDEPENDENCIES AND INPUTS.........................................................................................................................5 ASSUMPTIONS.................................................................................................................................................................6 CONSTRAINTS.................................................................................................................................................................6 RISKS, INCLUDING WORK HEALTH AND SAFETY..............................................................................................6 SPECIFICATIONS............................................................................................................................................................6 MILESTONE LIST............................................................................................................................................................7 PROJECT BUDGET..........................................................................................................................................................7 COST MANAGEMENT STRATEGY.............................................................................................................................7 PROCUREMENT STRATEGY.......................................................................................................................................7 COMMUNICATIONS STRATEGY................................................................................................................................8 CONTROL AND MONITORING STRATEGY.............................................................................................................8 CHANGE MANAGEMENT STRATEGY......................................................................................................................8 CRITICAL SUCCESS FACTORS...................................................................................................................................8 CLOSURE STRATEGY....................................................................................................................................................8 APPROVALS......................................................................................................................................................................8 CONCLUSION...................................................................................................................................................................9 RECOMMENDATIONS...................................................................................................................................................9 REFERENCES...................................................................................................................................................................9
Ben Russel CEO/Client Quality Officer End User CFO Project Manager P a g e|3 Executive Summary The project is developed for the listing of the probable management of the project of effective alignment of the case study of AX with the tools of project management. The completion of the project had helped in listing down the tools of Gantt chart, WBS, scope statement, reports, and final documentation. The use of these tools would help in conveying effective information transfer for the stakeholders. Question 1: Option 2 - Simulated Workplace Project Purpose The project has been developed for the execution of the work and developing effective alignment of the activities. The relocation of the AX office from Brisbane to Eagle Farms is the primary purpose of the project. Project Scope The scope of the project involves the development of the project plan, removal of the old office at Brisbane, new office development at Eagle farms, and completion of the project in estimated time and budget. List of relevant documents The relevant documents required for the project of relocation of the AX Queensland branch in Brisbane to Eagle farm are, a)Project Charter b)Project Scope Statement c)Project Communication Management d)Project Cost Estimation e)Project Activity Schedule f)Risk Management Plan Project team structure Team MembersRoleResponsibilities <<name of the student>>Project ManagerManagement of the project works Jack BrookeContractorGetting the work completed as per the contract Keli MirinHR ManagerManagement of the human resources for the project Austin, Ben, John, etc.Transport Workers Shifting of the materials from one location to other Lisa HudsonBudgeterMaking project budget Amanda JonesPlannerDeveloping the project plan Project Stakeholders
P a g e|4 Project Objectives ď‚·To relocate the AX office from one location (Brisbane) to other (Eagle Farms) ď‚·To form the project plan that is feasible in nature ď‚·To complete the project in estimated time and budget ď‚·To innovate the shifting using project management processes Resource Requirements 1.Documentation like project charter, PID, and others 2.Human resources for executing the works 3.Contract Procurement 4.Transport Medium 5.Communication Plan 6.Furniture and Fixtures 7.Construction materials 8.Equipment and devices 9.Operational plan 10.Integration works List of Key people in project planning The key people required for the project planning are Project Manager, Contractor, HR Manager, Transport Workers, Budgeter, and Planner. Question 2: Option 2 - Simulated Workplace Introduction The following assignment helps in developing the project management tools required for the completion of the project of relocation of the office from the Queensland state branch to Eagle farm. The documentation has been developed by considering the requirement for the information transfer and the integration of the effective work alignment. The relocation of the office from the Queensland state branch to Eagle farm for improving their art of production facilities and it would also be implied with the significance of the recently developed. Project Charter Document Project summary The project is developed for the relocation of the AX Queensland branch in Brisbane to Eagle farm. The owner of AX, Ben Russel had decided to buy the Tight Fit Doors in Brisbane and he wants to move his Queensland state branch in Brisbane to Eagle farm. The project would involve the deploying of the project management principles for ensuring that the effective work alignment would be executed. The analysis would be successful with the formation of the innovative and effective work alignment for AX organization. Business case The relocation of the office from the Queensland state branch to Eagle farm for improving their art of production facilities and it would also be implied with the significance of the recently developed. The analysis would be implied with the formation of the relocation of the office from one location to other. The deployment ofthebusinesscaseanalysiswouldbesupportedfortheutilizationoftheimprovedanalysisand development.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
P a g e|5 Project objectives and outcomes The objectives of the project of Office Relocation for AX to Eagle Farm were, To relocate the office premise from Brisbane to Eagle Farm for AX organization To complete the project in the estimated time and budget duration To comply project management works for developingthe project plan and execute them for the project To increase the probability of the mitigation of the risk factors for the relocation of the office The outcomes of the project of Office Relocation for AX to Eagle Farm were, Initial Outcomes: Project Plan documents, Resources required for relocation, and risk management plan. Intermediate Outcomes: Office refurbished at Eagle Farm and dismantle of office at Brisbane. Final Outcomes: The final outcomes of the project include the final reports for the project and the relocated office ready at Eagle Farm for use by AX. Project scope statement The project scope statement is dependent on the in scope items of the project for defining the work of relocation of the office and the formation of the successful integration of the works. The allocation of the work would be specifically implied with the use of the project management operations. The scope statement would include, “The use of the project management tools and processes for relocation of the office from one place to other would be effectively done with the consideration for the implication of the smart and innovative work alignment.” Project deliverables The deliverables for the project include project plan documents, resources required for relocation, risk management plan, office refurbished at Eagle Farm, dismantle of office at Brisbane, final reports for the project and the relocated office ready at Eagle Farm for use by AX. Exclusions The change management and the communication plan is excluded from the project operations for Office Relocation for AX to Eagle Farm. Project team structure The project team structure is given below,
Project Manager ContractorHR Manager Transport WorkersBudgeter Planner Ben Russel CEO/Client Quality Officer End User CFO Project Manager P a g e|6 Project governance structure Interdependencies and Inputs WBSTask NamePredecessor sSuccessors 1.1Set Up Tender Process3 1.2Hiring Vendor24 1.3Complete Lease Negotiation with Hamilton office agent35 1.4Close lease contract with existing Brisbane46
P a g e|7 office agent 1.5Completion of the phase58 2.1Develop Communication Plan69 2.2Update Clients and other stakeholders of relocation plan810 2.3Draft new floor plan for new office911 2.4Purchase of new office furniture1012 2.5Completion of the phase1114 3.1Removal of the existing Offices1215 3.2Disposal of the existing furniture1416 3.3Cleaning Existing Brisbane Office1517 3.4Construction of the new office1618 3.5Relocation of I.T. and communications equipment to the new office premises1719 3.6I.T. and communications equipment relocation and installations1820 3.7Setting Up accounts for utilities – Gas, Telephone, Electricity1921 3.8Create and implement a new work health and safety induction program2022 3.9Office Relocated2124 4.1Test and service fire/ emergency, heating and cooling and hot water systems2225 4.2Organise mail redirection with Australia Post2426 4.3Update AX website with new address and contact details2527 4.4Arrange insurance for new premises2628 4.5Project Closed27 Assumptions The assumptions of the project include successful accumulation of the resources, completion of the project in time, team members working cohesively, and improved management of the operations. Constraints The time, budget, and quality would act as the constraints of the project of Office Relocation for AX to Eagle Farm. Risks, including work health and safety The probable risk factors for the project of Office Relocation for AX to Eagle Farm were delay in completion, over budget, material shortage, accidents, and information management. Specifications WBSTask Name 1.1Set Up Tender Process 1.2Hiring Vendor 1.3Complete Lease Negotiation with Hamilton office agent 1.4Close lease contract with existing Brisbane office agent 1.5Completion of the phase 2.1Develop Communication Plan 2.2Update Clients and other stakeholders of
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
P a g e|8 relocation plan 2.3Draft new floor plan for new office 2.4Purchase of new office furniture 2.5Completion of the phase 3.1Removal of the existing Offices 3.2Disposal of the existing furniture 3.3Cleaning Existing Brisbane Office 3.4Construction of the new office 3.5Relocation of I.T. and communications equipment to the new office premises 3.6I.T. and communications equipment relocation and installations 3.7Setting Up accounts for utilities – Gas, Telephone, Electricity 3.8Create and implement a new work health and safety induction program 3.9Office Relocated 4.1Test and service fire/ emergency, heating and cooling and hot water systems 4.2Organize mail redirection with Australia Post 4.3Update AX website with new address and contact details 4.4Arrange insurance for new premises 4.5Project Closed Milestone list WBSTask NameDurationStartFinish 1.5Completion of the phase0 daysThu 1/10/19Thu 1/10/19 2.5Completion of the phase0 daysMon 1/28/19 Mon 1/28/19 3.9Office Relocated0 daysFri 3/22/19Fri 3/22/19 4.5Project Closed0 daysMon 4/15/19 Mon 4/15/19 Project budget Cost Budget for the Project ParticularsHumanMaterialSum Draft for new floor plan$2,200.00$8,800.00$11,000.00 Office Decoration and Fit out$25,000.0 0 $125,000.00$150,000.00 Removal and Disposal$2,500.00$12,500.00$15,000.00 New Office Furniture$60,000.00$60,000.00 Emergency,coolingand heating system $2,000.00$2,000.00 Relocation$1,500.00$7,500.00$9,000.00 Cleaning$2,000.00$1,000.00$3,000.00 Total Budget$250,000.00
P a g e|9 Cost management strategy The cost management strategy for the project of Office Relocation for AX to Eagle Farm includes the following points, Step 1: Identification of the resources Step 2: Resource Usage Plan Step 3: Resource Management Step 4: Calculation of the resource expenses Step 5: Documenting the plan strategy Procurement strategy The procurement strategy for the project of Office Relocation for AX to Eagle Farm includes the following points, Step 1: Identification of the contract requirements Step 2: Conflict Negotiation Plan Step 3: Contract terms and value analysis Step 4: Documenting the terms and norms Step 5: Sign off the documents Communications strategy The communication strategy for the project of Office Relocation for AX to Eagle Farm includes the following points, Step 1: Identification of the communication media Step 2: Information Transfer Plan Step 3: Communication Management Step 4: Identification of the sender Step 5: Documenting the process Control and monitoring strategy The control and monitoring strategy for the project of Office Relocation for AX to Eagle Farm includes the following points, Step 1: Identification of the processes for evaluation Step 2: Monitoring the processes for any issues Step 3: Development of control strategies Step 4: Implementation of the control strategies Step 5: Development of final documents Change management strategy The change management strategy for the project of Office Relocation for AX to Eagle Farm includes the following points, Step 1: Analysis of the change requirements Step 2: Development of change management strategy Step 3: Implementation of the change implication Step 4: Evaluation of the change processes Step 5: Development of final documents Critical success factors The critical success factors for the project would be implied with the implication of the effective work alignment and development. The utilization of the successful project factors would be implied with the formation of the effective new strategy for developing successive work alignment. The completion of the project in the estimated time and budget duration would be the major factors for success for the project. Closure strategy The closure strategy for the project of Office Relocation for AX to Eagle Farm includes the following points,
P a g e|10 Step 1: Identification of the closure requirements Step 2: Strategy development for the project closure Step 3: Handover report documentation Step 4: Final documentation of the reports Step 5: Post Success review Approvals Approved by: Ben Russell CEO AX Client <<Name of the student>> Project Manager Conclusion The use of the project management tools and processes for relocation of the office from one place to other had been effectively done with the consideration for the implication of the smart and innovative work alignment The deliverables for the project include project plan documents, resources required for relocation, risk management plan, office refurbished at Eagle Farm, dismantle of office at Brisbane, final reports for the project and the relocated office ready at Eagle Farm for use by AX. This project charter document had helped in conveying information to the necessary stakeholders. The information storage for the later phases of the project would be supported by this documentation. Recommendations Some recommendations for the execution of the project is shown below, 1.Utilization of the SDLC process 2.Integration work with formation of the works 3.Change management implication References DybĂĄ,Tore,TorgeirDingsøyr,andNilsBredeMoe."Agileprojectmanagement."InSoftwareproject management in a changing world, pp. 277-300. Springer, Berlin, Heidelberg, 2014. Falcone, D., G. Di Bona, A. Silvestri, A. Forcina, G. Belfiore, and A. Petrillo. "An integrated model for an advanced production process-Agile Re-engineering Project Management."IFAC-PapersOnLine. Vol.51, no. 11 (2018): pp. 1630-1635. Franková, PatrĂcia, Martina Drahošová, and Peter Balco. "Agile project management approach and its use in big data management."Procedia Computer Science. Vol.83 (2016): pp. 576-583. Galli, Brian J., and Paola Andrea Hernandez Lopez. "Risks Management in Agile New Product Development Project Environments: A Review of Literature."International Journal of Risk and Contingency Management (IJRCM). Vol.7, no. 4 (2018): pp. 37-67. Gonzalez,Winston."Applyingagileprojectmanagementtopredevelopmentstagesof innovation."InternationalJournalofInnovationandTechnologyManagement.Vol.11,no.04(2014): 1450020. Hansen, Lars Kristian, and Per Svejvig. "Agile project portfolio management, new solutions and new challenges: preliminary findings from a case study of an agile organization." InIRIS/SCIS Conference 2018. 2018. Hoda,Rashina,andLathaK.Murugesan."Multi-levelagileprojectmanagementchallenges:Aself- organizing team perspective."Journal of Systems and Software. Vol. 117 (2016): pp. 245-257. Hornstein, Henry A. "The integration of project management and organizational change management is now a necessity."International Journal of Project Management. Vol. 33, no. 2 (2015): pp. 291-298. Kerzner, Harold, and Harold R. Kerzner.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2017.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
P a g e|11 Layton, Mark C., and Steven J. Ostermiller.Agile project management for dummies. John Wiley & Sons, 2017. Lehnen, Jens, Tobias Sebastian Schmidt, and Cornelius Herstatt. "Bringing agile project management into lead user projects."International Journal of Product Development. Vol. 21, no. 2-3 (2016): pp. 212-232. Lin, Jun, Han Yu, Zhiqi Shen, and Chunyan Miao. "Studying task allocation decisions of novice agile teams withdatafromagileprojectmanagementtools."InProceedingsofthe29thACM/IEEEinternational conference on Automated software engineering, pp. 689-694. ACM, 2014. Nicholls,GillianM.,Neal A. Lewis, andTedEschenbach."Determiningwhensimplified agile project management is right for small teams."Engineering Management Journal. Vol. 27, no. 1 (2015): pp.3-10. Pope-Ruark,Rebecca."Introducingagileprojectmanagementstrategies intechnical and professional communication courses."Journal of Business and Technical Communication. Vol. 29, no. 1 (2015): pp.112- 133. Serrador,Pedro,andJeffreyK.Pinto."DoesAgilework?—Aquantitativeanalysisofagileproject success."International Journal of Project Management. Vol. 33, no. 5 (2015): pp.1040-1051. Sohi, Afshin Jalali, Marcel Hertogh, Marian Bosch-Rekveldt, and Rianne Blom. "Does lean & agile project management help coping with project complexity?."Procedia-Social and Behavioral Sciences. Vol. 226 (2016): pp. 252-259. Špundak, Mario. "Mixed agile/traditional project management methodology–reality or illusion?."Procedia- Social and Behavioral Sciences. Vol. 119 (2014): pp. 939-948. Stettina, Christoph Johann, and Jeannette Hörz. "Agile portfolio management: An empirical perspective on the practice in use."International Journal of Project Management. Vol. 33, no. 1 (2015): pp. 140-152.