Running head: COMPANY RELOCATION PROJECT PLAN Project Plan: To manage moving the company to another location Name of the Student: Name of the University:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1COMPANY RELOCATION PROJECT PLAN Table of Contents 1.0 Introduction to the project...........................................................................................2 2.0 Project scope statement.............................................................................................2 2.1 Project objectives...................................................................................................2 2.2 Project deliverables................................................................................................3 2.3 Milestones..............................................................................................................3 2.4 Technical requirements..........................................................................................4 2.5 Limits and exclusions.............................................................................................4 2.6 Review with customer.............................................................................................4 3.0 Establish project priorities..........................................................................................4 4.0 Create Work Breakdown Structure.............................................................................6 5.0 Cost estimation........................................................................................................10 References.....................................................................................................................12
2COMPANY RELOCATION PROJECT PLAN 1.0 Introduction to the project The project plan is based on to manage moving the company to another location. A private healthcare provider in Singapore desires to relocate their healthcare business to another city of Singapore. The relocation decision is taken to improve the healthcare business by expanding the IT infrastructure and better serve the clients and healthcare associates. The entire relocation of the company is dependent in company’s size. The company decides to outgrow the current space due to their expanded workforces, and they also need an efficient and updated facility to relocate their business. The relocation process needs proper planning of the location, finding of the office space, office fit out, technology, visual and furniture. This particular project plan includes of key dates of moving the office, strategies fortheofficemove,ITandtelecominfrastructureneedsandcommunication considerations. Themain benefit of this project plan is to deliver theplan within scheduled time and also budget. This report reflects on project scope statement based onsixitemssuchasobjectives,deliverables,milestones,limitsandexclusions, technical requirements and review with the customer. It also establishes three project priorities criteria for determining the priorities based on factors such as time, scope and cost. It provides a work breakdown structure, estimation of the cost with time phase budget. It also provides a Gantt chart which shows the estimated time with proper end and finish date of entire relocation plan of the healthcare provider business. 2.0 Project scope statement 2.1 Project objectives Following are the objectives of the project plan: To complete the project plan on scheduled time and estimated budget To complete check for the live operations of the relocation plan To approve the construction documents, furniture plans and moving map To expand the IT infrastructure and support of the healthcare provider business
3COMPANY RELOCATION PROJECT PLAN ï‚·To better service and provide healthcare services to the patients, clients and healthcare associates 2.2 Project deliverables In order to successfully complete the project plan, all the project deliverables are required to meet and approve by the project manager (Fisher, 2014). The lists of deliverables for relocation of the business to another location are as follows: ï‚·Survey of new office space before construction phase ï‚·Relocation of the healthcare business with minor modifications to current operational building ï‚·Real time office relocation of the employees and contractors ï‚·ExpansionoftheITinfrastructureaswellassystemalongwith upgradation of the online throughout the move ï‚·Project documentation such as project management plan, construction document, furniture plan and moving map such as interior layout 2.3 Milestones The project milestones are: Task NameExpected Start Completion of Feasibility Analysis Phase12/12/17 Completion of Planning Phase12/26/17 Completion of Relocation phase2/15/18 Completion of Closing phase2/22/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4COMPANY RELOCATION PROJECT PLAN 2.4 Technical requirements Following are the technical requirements to relocate of the business are: 1.The building where the office is relocated should meet with the building code and it should have authorized holder. 2.Provide the new location details into the official website of the company so that thecustomersshouldknowabouttheirrelocation(Huang,Chaiprapat& Waiyagan, 2015). 3.End of the project plan on time such as within 67 days 4.Obtaining of the insurance and permit from the higher authority and government to construct the office building 5.Providing of training to the staffs so as to handle the project relocation plans 2.5 Limits and exclusions The limitations of the project plan are that there is limited budget, therefore the relocation plan requires more fund. There is lot of downtime into the company while moving of their business to another location (Indelicato, 2014). Extra resources are required for the plan so that there is need to add more cost which may extend the project schedule. 2.6 Review with customer The workers those are working into the company should provide their review and feedback using communication processes such as survey and weekly meetings. Based on the feedback of the workers, the relocation work of the company is continued so that in future the workers can get better working environment and they are satisfied to work on it. 3.0 Establish project priorities Beforetheprojectmanagerstartedtoworkontheprojectplan,thereis requirement to develop the project priorities as based on those the work should be done. It enables the project manager to determine which of three criteria’s are most essential (Manning, 2014). The project priority matrix for company relocation plan is:
5COMPANY RELOCATION PROJECT PLAN CriteriaTimeScopeCost Constrain Enhance Accept The responsibility of the project manager is to estimate of the time, cost and provide the scope of the relocation project plan those are considered as the three main principles into the project priority matrix. Into this particular project plan, the priorities are as follows: Time:Time is considered as a constraint, as it is required to start the plan on scheduled time which is 22ndNovember, 2017 and end the plan on estimated plan with duration of 67 days. Proper finish is required on time as the company should start their healthcare business into new location on time. Scope:The project scope may enhance when new requirements are added into the plan. There should also possibility of scope changes into middle of the project phase (Rivinus, 2013). Cost:There is limited cost into the project; therefore project funding is required to meet with the project requirements for relocation of the business. Before start of the project, the project sponsor should estimate the resources properly so that later there are no chances of increasing the budgeted cost. Therefore, it is accepted by the project sponsor for funding requirements. When the three principles are accepted, then the project manager ranks those based on their priorities on the project. Based on the ranking system, time has highest priority, budget has second and scope consists of third priority.
6COMPANY RELOCATION PROJECT PLAN 4.0 Create Work Breakdown Structure The following tables show the works which are taken place into the project plan: WB SProject Activities 0Project Plan: To manage moving the company to another location 1Feasibility Analysis Phase 1.1Project charter 1.2Preliminary project scope 1.3Needs analysis 1.3.1Needs of the business 1.3.2Needs of the customers 2Planning Phase 2.1Selection of the contractor 2.1.1Building materials specifications 2.2IT specification plan 2.3Furniture vendor selection 3Relocation phase 3.1Legal, IT and project management 3.2Checklist for furniture delivery 3.3New IT system delivery checklist
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7COMPANY RELOCATION PROJECT PLAN 3.4Server deployment report 3.5Move map and schedule report 4Closing phase 4.1Sign off report of project manager 4.2Final IT system testing report The work packages are the related tasks within the project plan. It is considered as the smallest unit of the work in which the project is being broken down to create the work breakdown structure. At the time of preparing of the work break down structure, the deliverables are broken down into managerial pieces of the work. The process of deconstruction is continued until the deliverables are small, then it is considered as the work packages (Wells & Kloppenborg, 2015). The works packages are the lowest activity of the work breakdown structure for each the activities. In this project relocation plan, the work packages are considered as: Preliminary project scope, Needs of the customers,Furniture vendor selection, Move map and schedule report and Final IT system testing report.Each of the work packages should be small so that the project manager can estimate both the duration as well as cost (Indelicato, 2014). Those identified work packages are scheduled, cost estimation and controlled properly. The work packages are important as it permits to work on various components of the project plan.
8COMPANY RELOCATION PROJECT PLAN Figure 1: Gantt chart (Source: Created by author)
9COMPANY RELOCATION PROJECT PLAN TomanagmovingthecompanytoanotherlocationFeasibilityanalysisphaseProjectcharterPreliminatyprojectscopeNeedsanalysisNeedsofthebusinessNeedsofthecustomersPlanningphaseSelectionofthecontractorBuildingmaterialsspecificationsITspecificationplanFurniturevendorselectionFinalphaseSignoffreportFinalITtestingreportRelocationphaseLegal,ITandprojectmanagementChecklistforfurnituredeliveryServerdeploymentreportNewITsystemdeliverychecklistMovemapandschedulereport
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10COMPANY RELOCATION PROJECT PLAN Figure 2: Work breakdown structure (Source: Created by author) 5.0 Cost estimation Project activitiesDurationBudget Cost of office space occupancyWeek 1$ 1500 Insurance costWeek 2$ 300 Cost of the transactionWeek 3$ 840 Permits fees for the office buildingWeek 4$ 2000 Design and office fitting out costWeek 5$ 2000 Furniture costWeek 6$ 1000 Delivery and installation cost of the furniture Week 7$ 800 IT cablingWeek 8$ 1700 Cost for the disposalWeek 9-10$ 200 Printing costWeek 11$ 300 Marketing and operational costWeek 12$ 500 Other costsWeek 13$ 4700 Total cost for the project:$ 15,840 Within this particular cost estimation, the project manager uses the bottom up estimation technique which shows the expected cost of the work which is taken place. The estimated and total project cost should require being equal ((Huang, Chaiprapat & Waiyagan, 2015).As the cost estimation is accurate, therefore it is the best process. Usingthiscostestimationmethod,theactualcostofalltheworkpackagesare calculated properly.
11COMPANY RELOCATION PROJECT PLAN Time phase budget: Chart 1: Time phase budget (Source: Created by author) $0 $500 $1,000 $1,500 $2,000 $2,500 $3,000 $3,500 $4,000 $4,500 $5,000 $1,500 $300 $840 $2,000$2,000 $1,000$800 $1,700 $200$300$500 $4,700
12COMPANY RELOCATION PROJECT PLAN References Fisher, C. (2014). New Techniques in Project Management.AJIBM,04(12), 739-750. Huang, G., Chaiprapat, S., & Waiyagan, K. (2015). Automated process planning and cost estimation under material quality uncertainty.The International Journal Of Advanced Manufacturing Technology. Indelicato,G.(2014).ACompendiumofPMOCaseStudies:ReflectingProject Business Management Concepts.Project Management Journal,45(2), e4-e4. Manning, S. (2014). Mitigate, tolerate or relocate? Offshoring challenges, strategic imperatives and resource constraints.Journal Of World Business,49(4), 522- 535. Rivinus,C.(2013).ITprojectprioritization:Apracticalapplicationofknowledge management principles.Business Information Review,30(4), 196-203. Wells, K., & Kloppenborg, T. (2015).Project management essentials. New York, NY: Business Expert Press.