This document provides a project quality management plan for the construction project of a new facility for Beauty Therapy and Complementary Health Classrooms and Offices. It includes project details, project team, quality policy, quality procedure register, audit schedule, procedures and register, and more.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT QUALITY MANAGEMENT PLAN BSBPMG505A: Assessment 2- Project Quality Management Plan Project 4 Blue Mountains TAFE Name of the Student: Student ID:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT QUALITY MANAGEMENT PLAN Table of Contents Introduction..............................................................................................................................3 Project Details............................................................................................................................3 Project Team..............................................................................................................................3 Quality Policy.............................................................................................................................4 Quality Procedure Register........................................................................................................4 Audit Schedule...........................................................................................................................5 Procedures and Register.............................................................................................................6 Cost Control...............................................................................................................................7 Client Variation Register............................................................................................................7 Document Control......................................................................................................................8 Drawing Control.........................................................................................................................8 Request for Information Register...............................................................................................8 Inspection and Test Plans...........................................................................................................8 Internal Procedures.....................................................................................................................9 Conclusion..................................................................................................................................9 Recommendations......................................................................................................................9 Bibliography.............................................................................................................................11
PROJECT QUALITY MANAGEMENT PLAN Introduction The construction project management holds an integral role in the alignment of the developed communication management for enduring the development of innovative and effective information development. The project of aligning the continuous management of construction management. The development of the facilities for integrating the deployment of innovative informationmanagement.Theconstructionmanagementwouldbemanagedwiththe alignment of the innovative information development. The innovative information would be listedwiththecontinuousdevelopmentoftheworks.Theconstructionprojectof Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Officeswouldbetakenforconsideringthealignmentoftheimprovedmanagement development. Thefollowingreportwouldincludethedevelopmentoftheworksforaligningthe management of specific and implied management development. It is very crucial for aligning the continuous management of the specific and implied management of the works. The collection of the works would help enable the compilation of innovative and effective work development. The information alignment would be formed with the evaluation of the works related to the development of the works. The completion of the report would be done for enabling the continuous listing of the specific construction and management. Project Details The project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices would be developed for aligning the integration of the construction project management and the alignment of the innovative information alignment. The project would be formed for constructing the new facility with the required facilities and operations with the integration of the works. The project would be formed with the use of innovative information alignment. The improved development would support the consistent evaluation oftheconstructionprinciplesandformingtheeffectivealignmentoftheimproved construction. Project Team The project team would comprise of the Project Manager, Contractor, Workers, Civil Engineer, Architecture, Documenter, Planner, and Risk Analyst. These are the project team
PROJECT QUALITY MANAGEMENT PLAN members that would be required for enabling the completion of the project completion. The following is the project team member’s role explanation, Team memberRoles and Responsibilities Project Manager Management of the works and ensuring the completion of the works ContractorFollowing the procurement works and completion of the works WorkersWould do all the construction works assigned to them Civil EngineerIn charge of the works related to the construction works for enabling the innovative work completion ArchitectureWould take care of the works for listing the explicit management of the designing of the buildings DocumenterMaking the documents for the enabling of the compilation of the works PlannerDevelopment of the project plan for the enabling of the works Risk AnalystAnalysis of the risk and the development of the mitigation strategies Quality Policy The quality policy would be developed with the management of innovative information management. The policy would be developed for ensuring the compiled management of innovative information. The quality policy for the project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices would be marked with, •Use of sustainable practices for the construction of the new facility •Implementing the works for enabling the 7QC tools for the implied management •Supporting the deployment of the quality management plan Quality Procedure Register IDProductTarget Quality Review DateProducerApproverResults SUB- 000201Sand 8/1019-03-2018JVRGPass SUB- 000202Cement 9/1019-03-2018FGRGPass SUB- 000203Brick 8.5/1019-03-2018UGUYPass SUB- 000204Gravel 7/1019-03-2018ERUYPass SUB- 000205Pillars 7.5/1019-03-2018POTPPass
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PROJECT QUALITY MANAGEMENT PLAN SUB- 000201Bars 8.5/1019-03-2018UGUYPass SUB- 000201Iron Rods 7/1019-03-2018ERUYPass Table 1: Quality Procedure Register (Source:(Zheng, Le, Chan, Hu & Li, 2016) Audit Schedule The following is the project schedule developed for the project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices, WBSTask NameDurationStartFinish 0 Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices 104 daysMon 08-04-19Thu 29-08-19 1Phase 1: Initiation10 daysMon 08-04-19Fri 19-04-19 1.1Analysis of Requirements2 daysMon 08-04-19Tue 09-04-19 1.2Resource Accumulation4 daysWed 10-04-19Mon 15-04-19 1.3Tender Documentation3 daysTue 16-04-19Thu 18-04-19 1.4Submission and review1 dayFri 19-04-19Fri 19-04-19 1.5Approved0 daysFri 19-04-19Fri 19-04-19 2Phase 2: Planning15 daysWed 10-04-19Tue 30-04-19 2.1Collection of information3 daysWed 10-04-19Fri 12-04-19 2.2Listing Activities required2 daysMon 15-04-19Tue 16-04-19 2.3Development of the architectural plan2 daysWed 17-04-19Thu 18-04-19 2.4Scheduling the activities3 daysFri 19-04-19Tue 23-04-19 2.5Complete Plan Development5 daysWed 24-04-19Tue 30-04-19 2.6Approved0 daysTue 30-04-19Tue 30-04-19 3Phase 3: Execution75 daysFri 19-04-19Thu 01-08-19 3.1Layout Development3 daysFri 19-04-19Tue 23-04-19 3.2Blueprint is accessed3 daysWed 24-04-19Fri 26-04-19 3.3I. Demolish car parking12 daysWed 01-05-19Thu 16-05-19 3.3.1Calculate the area and according to area calculate the labour2 daysWed 01-05-19Thu 02-05-19 3.3.2Disconnection of the parking area from other service parts2 daysFri 03-05-19Mon 06-05-19 3.3.3200 mm thick, excavator, crusher, shears are used2 daysTue 07-05-19Wed 08-05-19 3.3.4Less than 200 mm thick, the hammer is adequate2 daysThu 09-05-19Fri 10-05-19 3.3.5Disposing of the demolished particles2 daysMon 13-05-19Tue 14-05-19 3.3.6Ram the earth and use the 3rd class brick and other filler materials2 daysWed 15-05-19Thu 16-05-19
PROJECT QUALITY MANAGEMENT PLAN 3.4II. New car parking26 daysThu 09-05-19Thu 13-06-19 3.4.1excavate the earth3 daysThu 09-05-19Mon 13-05-19 3.4.2ramming of earth2 daysTue 14-05-19Wed 15-05-19 3.4.3flat brick soling2 daysFri 17-05-19Mon 20-05-19 3.4.4use plain cement concrete (PCC) which 1:5:104 daysTue 21-05-19Fri 24-05-19 3.4.5live loads and dead loads applied on the parking floor4 daysMon 27-05-19Thu 30-05-19 3.4.6apply the floor finish 40 mm thick 1.32 daysFri 31-05-19Mon 03-06-19 3.4.7divide the areas into equal parts5 daysTue 04-06-19Mon 10-06-19 3.4.8stag water on it for curing of the floor3 daysTue 11-06-19Thu 13-06-19 3.5III. Interior works23 daysTue 04-06-19Thu 04-07-19 3.5.1floors, slabs, and internal walls are constructed4 daysTue 04-06-19Fri 07-06-19 3.5.2lintel is also casted3 daysMon 10-06-19Wed 12-06-19 3.5.3door and window frames are installed5 daysFri 14-06-19Thu 20-06-19 3.5.4brickwork3 daysFri 21-06-19Tue 25-06-19 3.5.5finishing work is done applying the wall plaster4 daysWed 26-06-19Mon 01-07-19 3.5.6Painting and Other works3 daysTue 02-07-19Thu 04-07-19 3.6IV. Pavement14 daysThu 13-06-19Tue 02-07-19 3.6.1Laying of concrete3 daysThu 13-06-19Mon 17-06-19 3.6.2Levelling of land2 daysTue 18-06-19Wed 19-06-19 3.6.3Cementing the floor4 daysThu 20-06-19Tue 25-06-19 3.6.4Crafting the pavement3 daysWed 26-06-19Fri 28-06-19 3.6.5Drying the cements2 daysMon 01-07-19Tue 02-07-19 3.7V. Electrical Works20 daysFri 05-07-19Thu 01-08-19 3.7.1Laying of wires3 daysFri 05-07-19Tue 09-07-19 3.7.2Electrical sockets and joints are made4 daysWed 10-07-19Mon 15-07-19 3.7.3Equipment are installed6 daysTue 16-07-19Tue 23-07-19 3.7.4Safety measures are installed5 daysWed 24-07-19Tue 30-07-19 3.7.5Power Connection is done2 daysWed 31-07-19Thu 01-08-19 4Closing20 daysFri 02-08-19Thu 29-08-19 4.1Final Documentation3 daysFri 02-08-19Tue 06-08-19 4.2Monitoring and evaluation10 daysWed 07-08-19Tue 20-08-19 4.3Change Implication5 daysWed 21-08-19Tue 27-08-19 4.4Submission and review2 daysWed 28-08-19Thu 29-08-19 4.5Sign off0 daysThu 29-08-19Thu 29-08-19 Procedures and Register
PROJECT QUALITY MANAGEMENT PLAN The procedures for the completion of the project works would be marked with the use of the phase-wise work division. The existing phases of the project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices include Phase 1: Initiation of the initiation phase would be marked with the continuation of the effective and smart alignment of the works. The initiation phase would be marked with the identification of the requirements and collection of the information. Phase 2: Planning the planning phase would involve the management of the facilities and developing an action plan for the completion of the works. The plan development would be marked with the scheduling of the activities. Phase 3: Execution the execution of the works would be formed for listing the management of the innovative information management. The construction works would be implied for enabling the successful completion of the works. Phase 4: Closing the closing of the works would be implied for listing the completion of the project by the development of the documentation. Cost Control The cost budget for the project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices is given below, ResourceTypeStandard rateUnitsCost Project ManagerHuman$8,000.001$8,000.00 ContractorHuman$4,500.003$13,500.00 WorkersHuman$750.0050$37,500.00 Civil EngineerHuman$5,500.001$5,500.00 ArchitectureHuman$4,750.002$9,500.00 DocumenterHuman$3,000.001$3,000.00 PlannerHuman$3,500.001$3,500.00 Risk AnalystHuman$3,500.001$3,500.00 Sub Total$84,000.00 SandMaterial$25.00500$12,500.00 CementMaterial$30.00500$15,000.00 BrickMaterial$15.00700$10,500.00 GravelMaterial$10.00300$3,000.00 PillarsMaterial$50.00150$7,500.00 BarsMaterial$60.00200$12,000.00 Iron RodsMaterial$55.00100$5,500.00 Sub Total$66,000.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT QUALITY MANAGEMENT PLAN Total$ 1,50,000.00 Client Variation Register The client variation register would be developed for enabling the smart development of the works. The client variation register for the project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices given below, StakeholderPowerInterest ClientHighHigh InvestorHighHigh Quality headLowHigh Steering CommitteeLowHigh Document Control The document control would be developed for listing the aligned management of the works for listing the continuation of the innovative work continuation. The documentation would be listed for aligning the management of the improved management. The document control would be listed with the innovative and improved development of the works. The document control would be eased with the alignment of the works. Drawing Control The drawing control would be developed for listing the aligned management of the works for listing the continuation of the innovative work continuation. The drawing would be listed for aligning the management of the improved management. The drawing control would be listed with the innovative and improved development of the works. The drawing control would be eased with the alignment of the works. Request for Information Register The information register would be asked for enabling the alignment of the analysis for the listing of the works. The register would be formed with the continued alignment of the information listing specific work development. Inspection and Test Plans
PROJECT QUALITY MANAGEMENT PLAN The inspection and testing policy would be developed with the management of innovative informationmanagement.Thepolicywouldbedevelopedforensuringthecompiled management of innovative information. The inspection and testing policy for the project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices would be marked with the alignment of the successful development management (Banihashemi, Hosseini, Golizadeh & Sankaran, 2017). Internal Procedures The initiation phase would be marked with the continuation of the effective and smart alignment of the works. The initiation phase would be marked with the identification of the requirements and collection of the information. The planning phase would involve the management of the facilities and developing an action plan for the completion of the works. The plan development would be marked with the scheduling of the activities. The execution of the works would be formed for listing the management of innovative information management.Theconstructionworkswouldbeimpliedforenablingthesuccessful completion of the works. The closing of the works would be implied for listing the completion of the project by the development of the documentation. Conclusion The provided report had included the development of the works for aligning the management of specific and implied management development. The construction project of Construction of New facility for Beauty Therapy and Complementary Health Classrooms and Offices had been taken for considering the alignment of the improved management development. It was very crucial for aligning the continuous management of the specific and implied management of the works. The collection of the works had been helpful for enabling the compilation of innovative and effective work development. The information alignment had been formed with the evaluation of the works related to the development of the works. The completion of the report had been done for enabling the continuous listing of the specific construction and management. The construction project management holds an integral role in the alignment of the developed communication management for enduring the development of innovative and effective information development. The project of aligning the continuous management of construction management. The development of the facilities for integrating the deployment of innovative information management. The construction management had been managed with
PROJECT QUALITY MANAGEMENT PLAN the alignment of the innovative information development. The innovative information had been listed with the continuous development of the works. Recommendations Some recommendations had been used for the implication of the works for the construction of the New facility for Beauty Therapy and Complementary Health Classrooms and Offices has been given below, Use of the Designing Principles: The designing principles would be used for aligning the collection of the elements for designing the building structure. The design principles would support the contribution of the effective alignment of the works. Sustainable Construction Principles: The sustainable principles of design would be developed with the continued listing of the works. The principles of aligning the effective strategy alignment can be deployed for forming successful information alignment. The principles of constructionusingsustainablepracticeswouldbedone withtheconsiderationofthe innovative information.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PROJECT QUALITY MANAGEMENT PLAN Bibliography Banihashemi, S., Hosseini, M. R., Golizadeh, H., &Sankaran, S. (2017). Critical success factors(CSFs)fortheintegrationofsustainabilityintoconstructionproject management practicesin developing countries.International Journal of Project Management,35(6), 1103-1119. Zheng, X., Le, Y., Chan, A. P., Hu, Y., & Li, Y. (2016). Review of the application of social network analysis (SNA) in construction project management research.International journal of project management,34(7), 1214-1225.