Industrial Services Business Project Presentation
VerifiedAdded on 2023/04/25
|16
|1025
|150
Presentation
AI Summary
This project presentation focuses on the Industrial Services Business and its aim to improve quality, enhance reliability of operational assets and bring down operational costs. It includes stakeholder analysis, management strategies, risk analysis, budget template, key performance indicators, and lessons learned. References are also provided.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Industrial Services Business
Project Presentation
Project Presentation
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Scope
Industrial Services Business
Variety of services to the customers and
business enterprises
Improve the quality
Enhance the reliability of the operational
assets
Bring down the operational costs
Industrial Services Business
Variety of services to the customers and
business enterprises
Improve the quality
Enhance the reliability of the operational
assets
Bring down the operational costs
Project Aims & Objective
Factors that lead to the reduction in
reliability
Factors that lead to the reduction in quality
Evaluation of the measures to enhance
reliability and quality
Recommendation of the strategies for
effective implementation
Adherence to the project costs and time
Factors that lead to the reduction in
reliability
Factors that lead to the reduction in quality
Evaluation of the measures to enhance
reliability and quality
Recommendation of the strategies for
effective implementation
Adherence to the project costs and time
Analysis of Stakeholder Groups
Ten stakeholders in the organization
Joe Bennett: Interim President
Secondary Stakeholders
The United Way of Davidson County
Ncarf
Gray Wilson, Cathy Misenheimer, and Doug
Meredith
Ten stakeholders in the organization
Joe Bennett: Interim President
Secondary Stakeholders
The United Way of Davidson County
Ncarf
Gray Wilson, Cathy Misenheimer, and Doug
Meredith
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Stakeholder Issues
Secondary stakeholders have different
demands
Difference in perspectives and viewpoints
Difficulty in problem-solving and decision-
making activities
Increased number of conflicts
Increased disputes and overall project risks
Collaboration and resolution becomes
difficult
Secondary stakeholders have different
demands
Difference in perspectives and viewpoints
Difficulty in problem-solving and decision-
making activities
Increased number of conflicts
Increased disputes and overall project risks
Collaboration and resolution becomes
difficult
Stakeholder Management Strategies
Belbin’s model for team roles
Action-oriented roles
Complete-Finisher (CF)
Pay attention to minute details
Concerned with deadlines
Push the team
See the project is completed successfully
Stakeholder communication, reporting, and
information sharing
Belbin’s model for team roles
Action-oriented roles
Complete-Finisher (CF)
Pay attention to minute details
Concerned with deadlines
Push the team
See the project is completed successfully
Stakeholder communication, reporting, and
information sharing
Risk Analysis & Risk Mitigation
Primary Risk Driver: Approach of delivery
facilities to the clients
Development of various risks
Cost, quality, and schedule risks
Risk Mitigation Strategies
Risk management using project management
methodologies
Project reviews and audits
Automated tools for risk identification and
analysis
Primary Risk Driver: Approach of delivery
facilities to the clients
Development of various risks
Cost, quality, and schedule risks
Risk Mitigation Strategies
Risk management using project management
methodologies
Project reviews and audits
Automated tools for risk identification and
analysis
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Tasks & Phases
0 - Equipment Cleaning Service Project
1 - Start
2 - Project Initiation and defining objectives
2.1 - Defining of project plan and setting of objectives
2.2 - Determination of the project budget
3 - Planning for Implementation of Cleaning works
3.1 - Outlining the details of project implementation
3.2 - Planning of deployment of manual staff
4 - Conduction of Cleaning activity
4.1 - The cleaning equipment are deployed
4.2 - Conduction of equipment cleaning service
5 - Final Closure of the Project
5.1 - Placing and fitting of cleaned equipments
5.2 - Gaining feedbacks from the Company
6 - Stop
0 - Equipment Cleaning Service Project
1 - Start
2 - Project Initiation and defining objectives
2.1 - Defining of project plan and setting of objectives
2.2 - Determination of the project budget
3 - Planning for Implementation of Cleaning works
3.1 - Outlining the details of project implementation
3.2 - Planning of deployment of manual staff
4 - Conduction of Cleaning activity
4.1 - The cleaning equipment are deployed
4.2 - Conduction of equipment cleaning service
5 - Final Closure of the Project
5.1 - Placing and fitting of cleaned equipments
5.2 - Gaining feedbacks from the Company
6 - Stop
Project Gantt ChartID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 Equipment
Cleaning Service
Project
67 days Wed
16-01-19
Thu
18-04-19
1 1 Start 1 day Wed 16-01-19Wed 16-01-19
2 2 Project
Initiation and
defining
objectives
7 days Thu
17-01-19
Fri
25-01-19
3 2.1 Defining of
project plan
and setting of
objectives
2 days Thu
17-01-19
Fri 18-01-19
4 2.2 Determination
of the project
budget
5 days Mon
21-01-19
Fri 25-01-19
5 3 Planning for
Implementation
of Cleaning
works
17 days Mon
28-01-19
Tue
19-02-19
6 3.1 Outlining the
details of
project
implementation
13 days Mon
28-01-19
Wed
13-02-19
7 3.2 Planning of
deployment of
manual staff
4 days Thu
14-02-19
Tue
19-02-19
8 4 Conduction of
Cleaning
activity
25 days Wed
20-02-19
Tue
26-03-19
9 4.1 The cleaning
equipment are
deployed
2 days Wed
20-02-19
Thu
21-02-19
10 4.2 Conduction of
equipment
cleaning
service
23 days Fri 22-02-19Tue
26-03-19
11 5 Final Closure of
the Project
17 days Wed
27-03-19
Thu
18-04-19
12 5.1 Placing and
fitting of
cleaned
equipments
10 days Wed
27-03-19
Tue
09-04-19
13 5.2 Gaining
feedbacks
from the
Company
7 days Wed
10-04-19
Thu
18-04-19
14 6 Stop 0 days Thu 18-04-19Thu 18-04-19 18-04
07-01 28-01 18-02 11-03 01-04 22-04 13-05 03-06 24-06 15-07 05-08
01 January 21 February 11 April 01 June 21 July
Number
Task
Mode
Task Name Duration Start Finish
0 0 Equipment
Cleaning Service
Project
67 days Wed
16-01-19
Thu
18-04-19
1 1 Start 1 day Wed 16-01-19Wed 16-01-19
2 2 Project
Initiation and
defining
objectives
7 days Thu
17-01-19
Fri
25-01-19
3 2.1 Defining of
project plan
and setting of
objectives
2 days Thu
17-01-19
Fri 18-01-19
4 2.2 Determination
of the project
budget
5 days Mon
21-01-19
Fri 25-01-19
5 3 Planning for
Implementation
of Cleaning
works
17 days Mon
28-01-19
Tue
19-02-19
6 3.1 Outlining the
details of
project
implementation
13 days Mon
28-01-19
Wed
13-02-19
7 3.2 Planning of
deployment of
manual staff
4 days Thu
14-02-19
Tue
19-02-19
8 4 Conduction of
Cleaning
activity
25 days Wed
20-02-19
Tue
26-03-19
9 4.1 The cleaning
equipment are
deployed
2 days Wed
20-02-19
Thu
21-02-19
10 4.2 Conduction of
equipment
cleaning
service
23 days Fri 22-02-19Tue
26-03-19
11 5 Final Closure of
the Project
17 days Wed
27-03-19
Thu
18-04-19
12 5.1 Placing and
fitting of
cleaned
equipments
10 days Wed
27-03-19
Tue
09-04-19
13 5.2 Gaining
feedbacks
from the
Company
7 days Wed
10-04-19
Thu
18-04-19
14 6 Stop 0 days Thu 18-04-19Thu 18-04-19 18-04
07-01 28-01 18-02 11-03 01-04 22-04 13-05 03-06 24-06 15-07 05-08
01 January 21 February 11 April 01 June 21 July
Budget Template
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Budget Template
Key Performance Indicators
Fiscal Metric
Actual Values and Planned Values
Calculation of
Schedule Variance
Cost Variance
Net Present Value (NPV) & Internal Rate of
Return (IRR)
Fiscal Metric
Actual Values and Planned Values
Calculation of
Schedule Variance
Cost Variance
Net Present Value (NPV) & Internal Rate of
Return (IRR)
Key Performance Indicators
Defect Rate & Open Defects
Customer Satisfaction Rate
Appearance Matrix
Sanitizing Metric
Acceptance of Deliverables
Risk(s) Status
Defect Rate & Open Defects
Customer Satisfaction Rate
Appearance Matrix
Sanitizing Metric
Acceptance of Deliverables
Risk(s) Status
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Lessons Learned & Conclusion
Significance of each of the project stages
Project initiation
Project planning
Project execution
Project control
Project closure
Need of a project management methodology
Stakeholder analysis, management, and
communication
Significance of each of the project stages
Project initiation
Project planning
Project execution
Project control
Project closure
Need of a project management methodology
Stakeholder analysis, management, and
communication
Lessons Learned & Conclusion
Necessary to define project scope
SMART project objectives and aims
Schedule management in project
Budget management in project
Cost benefit analysis and forecasting
Risk analysis and management
Necessary to define project scope
SMART project objectives and aims
Schedule management in project
Budget management in project
Cost benefit analysis and forecasting
Risk analysis and management
References
Belbin, R. (2010). Design Innovation and the TEAM. Design Management Journal (Former Series),
2(3), pp.38-42.
Chou, H.W., Lin, Y.H., Lu, H.S., Chang, H.H. and Chou, S.B., 2014. Knowledge sharing and ERP
system usage in post-implementation stage. Computers in Human Behavior, 33, pp.16-22.
Crawford, J.K., 2014. Project management maturity model. Auerbach Publications.
Gareth Bell, I. (2013). Teamwork makes the team work. Human Resource Management
International Digest, 21(2), pp.45-47.
Jayawardhena, C. (2010). The impact of service encounter quality in service evaluation: evidence
from a business‐to‐business context. Journal of Business & Industrial Marketing, 25(5), pp.338-
348.
Kunz, R.E., Siebert, J. and Mütterlein, J., 2016. Structuring objectives of media companies: a case
study based on value-focused thinking and the balanced scorecard. Journal of Media Business
Studies, 13(4), pp.257-275.
Lombardi, R., Caputo, A., Russo, G. and Formisano, V., 2015. Management control of contractual
networks: the business network scorecard. International Journal of Applied Management
Science, 7(4), pp.269-286.
Patanakul, P. and Shenhar, A.J., 2012. What project strategy really is: The fundamental building
block in strategic project management. Project Management Journal, 43(1), pp.4-20.
Remington, K., & Pollack, J. (2016). Tools for complex projects. Routledge
Tailby, S. (2012). Public service restructuring in the UK: the case of the English National Health
Service. Industrial Relations Journal, 43(5), pp.448-464.
Belbin, R. (2010). Design Innovation and the TEAM. Design Management Journal (Former Series),
2(3), pp.38-42.
Chou, H.W., Lin, Y.H., Lu, H.S., Chang, H.H. and Chou, S.B., 2014. Knowledge sharing and ERP
system usage in post-implementation stage. Computers in Human Behavior, 33, pp.16-22.
Crawford, J.K., 2014. Project management maturity model. Auerbach Publications.
Gareth Bell, I. (2013). Teamwork makes the team work. Human Resource Management
International Digest, 21(2), pp.45-47.
Jayawardhena, C. (2010). The impact of service encounter quality in service evaluation: evidence
from a business‐to‐business context. Journal of Business & Industrial Marketing, 25(5), pp.338-
348.
Kunz, R.E., Siebert, J. and Mütterlein, J., 2016. Structuring objectives of media companies: a case
study based on value-focused thinking and the balanced scorecard. Journal of Media Business
Studies, 13(4), pp.257-275.
Lombardi, R., Caputo, A., Russo, G. and Formisano, V., 2015. Management control of contractual
networks: the business network scorecard. International Journal of Applied Management
Science, 7(4), pp.269-286.
Patanakul, P. and Shenhar, A.J., 2012. What project strategy really is: The fundamental building
block in strategic project management. Project Management Journal, 43(1), pp.4-20.
Remington, K., & Pollack, J. (2016). Tools for complex projects. Routledge
Tailby, S. (2012). Public service restructuring in the UK: the case of the English National Health
Service. Industrial Relations Journal, 43(5), pp.448-464.
1 out of 16
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.