1. The Gantt chart............................................................................................................................2
2. The High Level Work Breakdown Structure..............................................................................3
1.1 Milestones..............................................................................................................................0
1.2 Activities or Tasks.................................................................................................................1
1.3 Resource Assignments...........................................................................................................3
1.4 Estimates for each activity or task.........................................................................................5
1.5 Project Budget.......................................................................................................................6
Bibliography....................................................................................................................................8

2DEVELOPING THE MBFSA APPLICATION BY GLOBEX
1. The Gantt chart
ID Task
Mode
Task Name Duration Start Finish
0 Developing the MBFSA
Project by Globex
133 days Wed
01-05-19
Fri 01-11-19
1 Phase 1: Requirem e nt Gathe ring Phase29 days Wed 01-05-19 Mon 10-06-19
2 Preparing of Business Case 2 days Wed 01-05-19 Thu 02-05-19
3 Requirement Gathering 4 days Fri 03-05-19 Wed 08-05-19
4 Develop Scope Management Plan 6 days Thu 09-05-19 Thu 16-05-19
5 Develop Project Management Plan 10 days Fri 17-05-19 Thu 30-05-19
6 Perform Initial Risk Assessment 2 days Fri 31-05-19 Mon 03-06-19
7 Initial Application Test Planning 3 days Tue 04-06-19 Thu 06-06-19
8 Develop Quality Plan 2 days Fri 07-06-19 Mon 10-06-19
9 M1: Requirement Complete 0 days Mon 10-06-19 Mon 10-06-19
10 Planning and Des igning 14 days Tue 11-06-19 Fri 28-06-19
11 Creating Conceptual Design 1 day Tue 11-06-19 Tue 11-06-19
12 Create Login Des ign 6 days Wed 12-06-19 Wed 19-06-19
13 LG1 Weather Information System2 days Wed 12-06-19 Thu 13-06-19
14 LG1 Market Information System1 day Fri 14-06-19 Fri 14-06-19
15 F1 Farmer management System1 day Mon 17-06-19 Mon 17-06-19
16 WM1 Wholesale Management System2 days Tue 18-06-19 Wed 19-06-19
17 Create Implementation Plan 4 days Thu 20-06-19 Tue 25-06-19
18 Create Contengency Plan 3 days Wed 26-06-19 Fri 28-06-19
19 M2: Planning Phase Complete 0 days Fri 28-06-19 Fri 28-06-19
20 Phase 2: Developm ent of MBFSA 76 days Mon 01-07-19 Mon 14-10-19
21 Create Database 10 days Mon 01-07-19 Fri 12-07-19
22 Make Prototype 19 days Mon 01-07-19 Thu 25-07-19
23 Excute Project Management Plan 20 days Fri 26-07-19 Thu 22-08-19
24 Proje ct Im ple m entation 15 days Fri 23-08-19 Thu 12-09-19
25 LG2 Weather Information System6 days Fri 23-08-19 Fri 30-08-19
26 LG2 Market Information System5 days Fri 23-08-19 Thu 29-08-19
27 F2 Farmer management System4 days Mon 02-09-19 Thu 05-09-19
28 WM2 Wholesale Management System5 days Fri 06-09-19 Thu 12-09-19
29 Data Entry 4 days Fri 13-09-19 Wed 18-09-19
30 Develop Media Content 9 days Fri 23-08-19 Wed 04-09-19
31 Code Review 6 days Thu 19-09-19 Thu 26-09-19
32 Prepare Unit Test 5 days Fri 27-09-19 Thu 03-10-19
33 Developed Application Verification7 days Fri 04-10-19 Mon 14-10-19
34 Create Training Materials 8 days Thu 19-09-19 Mon 30-09-19
35 M3: Development Phase Complete 0 days Mon 30-09-19 Mon 30-09-19
36 Project De ploym e nt 5 days Tue 01-10-19 Mon 07-10-19
37 Finalise Implementation Plan 1 day Tue 01-10-19 Tue 01-10-19
38 Finalise Contingency Plan 1 day Wed 02-10-19 Wed 02-10-19
39 Prepare for Deployment 1 day Thu 03-10-19 Thu 03-10-19
40 Deploy Application 2 days Fri 04-10-19 Mon 07-10-19
41 M4: Deploy Phase Complete 0 days Mon 07-10-19 Mon 07-10-19
42 Project Handover 19 days Tue 08-10-19 Fri 01-11-19
43 Conduct-Post Project Review Meeting1 day Tue 08-10-19 Tue 08-10-19
44 Prepare Project Handover Documents7 days Tue 15-10-19 Wed 23-10-19
45 Conduct Performance Recognition4 days Thu 24-10-19 Tue 29-10-19
46 Prepare Feedback For Team 2 days Wed 30-10-19 Thu 31-10-19
47 Provide Feedback For Team 1 day Fri 01-11-19 Fri 01-11-19
48 Release Team 0 days Fri 01-11-19 Fri 01-11-19
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
10-06
Vineeth Reddy Anugu (System Analyst)
Naren Reddy Ennam (Project Manager)[25%],Vineeth
Naren Reddy Ennam (Project Manager)[25%],Vineeth
Naren Reddy Ennam (Project Manager)[25%],Vinee
Naren Reddy Ennam (Project Manager)[25%],Vine
Naren Reddy Ennam (Project Manager)
Naren Reddy Ennam (Project Manager)
28-06
Karumanchi Vamsi (Database Engi
Revanth Reddy Andru (So
Nare
W T F S S M T W T F S S M T W T
22 Apr '19 13 May '19 03 Jun '19 24 Jun '19 15 Jul '19 05 Aug '19 26 A
(Figure 1: The Gantt chart for the Project)
(Source: Created by author)

3DEVELOPING THE MBFSA APPLICATION BY GLOBEX
2. The High Level Work Breakdown Structure
(Figure 2: The Work Breakdown Structure for the Project)
(Source: Created by author)

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
BNV6047 Project Management
|19
|3818
|40

BNV6047 Project Management Assignment
|6
|1309
|304

Project Management Isn't Just For Project
|10
|1445
|19

Project Management for Music Event: Stakeholder Analysis, Risk Analysis, and Communication Strategies
|17
|2773
|60

Project Management: Benefits Administration Software
|4
|811
|299

Development of CRM System for Medium Organization
|5
|596
|58