Running head: REASEARCH MEATHODS AND PROJECT DESIGN
REASEARCH MEATHODS AND PROJECT DESIGN
Name of student
Name of university
Author’s note:
REASEARCH MEATHODS AND PROJECT DESIGN
Name of student
Name of university
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
REASEARCH MEATHODS AND PROJECT DESIGN
Table of Contents
Comment updates...........................................................................................................2
Table of weekly activities..............................................................................................2
Responsibilities and roles of team members..................................................................3
Gantt chart......................................................................................................................6
Project design.................................................................................................................9
Project individual research approach...........................................................................11
Budget..........................................................................................................................15
Bibliography.................................................................................................................16
REASEARCH MEATHODS AND PROJECT DESIGN
Table of Contents
Comment updates...........................................................................................................2
Table of weekly activities..............................................................................................2
Responsibilities and roles of team members..................................................................3
Gantt chart......................................................................................................................6
Project design.................................................................................................................9
Project individual research approach...........................................................................11
Budget..........................................................................................................................15
Bibliography.................................................................................................................16
2
REASEARCH MEATHODS AND PROJECT DESIGN
Comment updates
As per the feedback from the assignment 1, the page numbering was not done
properly which is majorly important for any document. The page number in the document
was required to be from the introduction that was the page number 1 and there was significant
feedback from the professor. The proper citation was missing from the introduction part
which has been briefly mentioned to practise to provide the proper recognition to the people
and the authors who have created the articles and the journals. In the research question
section there was another issue of the citation and the issue of citation missing. In the
research question section, the proper explanation of the research question was not provided
that is not acceptable as it does not provide the overview of what question is required for the
research and the reason why the document has been created. According to the professor, there
are several typing mistakes that are required to be corrected and it makes the document less
attractive and the credibility of the document is significantly decreased with constant
happening of the typing mistakes. Other than these sections, the document was above average
for presenting the report to the business manager.
Table of weekly activities
Weeks Activities
1 In the first week the groups had been formed. An approach was made to the
client regarding the various activities that would be included in the project.
2 All the team members were provided with the details of the client and the
introduction with client were done.
3 A meeting was conducted with the client. The evaluation of the background of
the project was done for the client.
4 The goal and the objective of the project was discussed and evaluated.
REASEARCH MEATHODS AND PROJECT DESIGN
Comment updates
As per the feedback from the assignment 1, the page numbering was not done
properly which is majorly important for any document. The page number in the document
was required to be from the introduction that was the page number 1 and there was significant
feedback from the professor. The proper citation was missing from the introduction part
which has been briefly mentioned to practise to provide the proper recognition to the people
and the authors who have created the articles and the journals. In the research question
section there was another issue of the citation and the issue of citation missing. In the
research question section, the proper explanation of the research question was not provided
that is not acceptable as it does not provide the overview of what question is required for the
research and the reason why the document has been created. According to the professor, there
are several typing mistakes that are required to be corrected and it makes the document less
attractive and the credibility of the document is significantly decreased with constant
happening of the typing mistakes. Other than these sections, the document was above average
for presenting the report to the business manager.
Table of weekly activities
Weeks Activities
1 In the first week the groups had been formed. An approach was made to the
client regarding the various activities that would be included in the project.
2 All the team members were provided with the details of the client and the
introduction with client were done.
3 A meeting was conducted with the client. The evaluation of the background of
the project was done for the client.
4 The goal and the objective of the project was discussed and evaluated.
3
REASEARCH MEATHODS AND PROJECT DESIGN
5 Work began on the requirements of the client and the analysis of the
requirements of the Pedestrian detection was done.
6 The project presentation and the functioning on the video presentation was done.
7 There was an efficient meeting with the discussion of assignment 2, and the
proper research methodology was determined.
Responsibilities and roles of team members
Name and student ID Week Responsibilities and the roles
Rajasekhar Polaka-
MIT173408
1
Initial activity of the group formation was done. Several
details of the client was gathered.
2 Worked on the individual topic of project.
3 Execution of the literature review was done.
4 Meeting with the client was done.
Name and student ID Week Responsibilities and the roles
Manisha Kolle-
MIT180076 1
The selection of the random group members was done
by subject coordinator and they were assigned to the
project.
2
The contacting to the group members was done for the
allocation of the specific time for the weekly client as
well as the supervisor meeting.
3 Commenced the preparation on the presentation on the
REASEARCH MEATHODS AND PROJECT DESIGN
5 Work began on the requirements of the client and the analysis of the
requirements of the Pedestrian detection was done.
6 The project presentation and the functioning on the video presentation was done.
7 There was an efficient meeting with the discussion of assignment 2, and the
proper research methodology was determined.
Responsibilities and roles of team members
Name and student ID Week Responsibilities and the roles
Rajasekhar Polaka-
MIT173408
1
Initial activity of the group formation was done. Several
details of the client was gathered.
2 Worked on the individual topic of project.
3 Execution of the literature review was done.
4 Meeting with the client was done.
Name and student ID Week Responsibilities and the roles
Manisha Kolle-
MIT180076 1
The selection of the random group members was done
by subject coordinator and they were assigned to the
project.
2
The contacting to the group members was done for the
allocation of the specific time for the weekly client as
well as the supervisor meeting.
3 Commenced the preparation on the presentation on the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4
REASEARCH MEATHODS AND PROJECT DESIGN
project and also worked on the video.
4
Started the work on the assignment 2. The selection of
the topics was done.
5
The literature review has been submitted for the
assignment 1.
6
The preparation of the slides was done with help from
the supervisor.
Name and student ID Week Responsibilities and the roles
Praneeth Kumar
Desai Karanam-
MIT175014
1
The division of topics of the projects was divided
mutually among group from the assistance with
supervisor
2
The collection of the all the individual literature review
was done from group members
3 Submitted for grading
4 Initiated the presentation for the week 8
5 The finalisation of the video was done
Name and student ID Week Responsibilities and the roles
Chandrahas Reddy 1 Assisted in the compiling and the submitting the
REASEARCH MEATHODS AND PROJECT DESIGN
project and also worked on the video.
4
Started the work on the assignment 2. The selection of
the topics was done.
5
The literature review has been submitted for the
assignment 1.
6
The preparation of the slides was done with help from
the supervisor.
Name and student ID Week Responsibilities and the roles
Praneeth Kumar
Desai Karanam-
MIT175014
1
The division of topics of the projects was divided
mutually among group from the assistance with
supervisor
2
The collection of the all the individual literature review
was done from group members
3 Submitted for grading
4 Initiated the presentation for the week 8
5 The finalisation of the video was done
Name and student ID Week Responsibilities and the roles
Chandrahas Reddy 1 Assisted in the compiling and the submitting the
5
REASEARCH MEATHODS AND PROJECT DESIGN
Bumireddy-
MIT174741
literature review
2 Participated in the project supervisor meeting
3 Attended the supervisor meeting
4 Started on the working on assignment 2
Name and student ID Week Responsibilities and the roles
Madhu Kumar
Vattepu-
MIT173378
1
Had the meeting with the supervisor, narrowed the area
of the research
2 Initiated the working on the week 8 task
3
Working on the estimation of the project budget and the
project diagram
4 Individual research approach has been done
5
Literature review of each of the individuals was
circulated among the team members for getting the
feedback prior final submission of the final report
6
The scheduling was conducted for the client and the
supervisor meetings.
Gantt chart
WBS Task Name Duratio Start Finish Predecessors
REASEARCH MEATHODS AND PROJECT DESIGN
Bumireddy-
MIT174741
literature review
2 Participated in the project supervisor meeting
3 Attended the supervisor meeting
4 Started on the working on assignment 2
Name and student ID Week Responsibilities and the roles
Madhu Kumar
Vattepu-
MIT173378
1
Had the meeting with the supervisor, narrowed the area
of the research
2 Initiated the working on the week 8 task
3
Working on the estimation of the project budget and the
project diagram
4 Individual research approach has been done
5
Literature review of each of the individuals was
circulated among the team members for getting the
feedback prior final submission of the final report
6
The scheduling was conducted for the client and the
supervisor meetings.
Gantt chart
WBS Task Name Duratio Start Finish Predecessors
6
REASEARCH MEATHODS AND PROJECT DESIGN
n
0 Gnatt chart
144
days
Tue 19-03-19
Thu 03-10-
19
1 Research initiation phase 28 days Tue 19-03-19
Wed 24-04-
19
1.1 Process identification 4 days Tue 19-03-19 Fri 22-03-19
1.2
Appropriate identification of
employee
14 days Mon 25-03-19
Thu 11-04-
19
2
1.3
Investigation of standards and
the policies
5 days Mon 25-03-19 Fri 29-03-19 2
1.4 Justification of need of research 7 days Fri 12-04-19 Fri 19-04-19 4,3
1.5 Execution of feasibility study 3 days Mon 22-04-19
Wed 24-04-
19
5
2 Planning phase 68 days Mon 22-04-19
Wed 24-07-
19
2.1
Scope statement has been
defined
4 days Mon 22-04-19
Thu 25-04-
19
5
2.2 Large deliverables are divided 10 days Fri 26-04-19
Thu 09-05-
19
8
2.3 Identification of required tasks
for the production of
16 days Fri 10-05-19 Fri 31-05-19 9
REASEARCH MEATHODS AND PROJECT DESIGN
n
0 Gnatt chart
144
days
Tue 19-03-19
Thu 03-10-
19
1 Research initiation phase 28 days Tue 19-03-19
Wed 24-04-
19
1.1 Process identification 4 days Tue 19-03-19 Fri 22-03-19
1.2
Appropriate identification of
employee
14 days Mon 25-03-19
Thu 11-04-
19
2
1.3
Investigation of standards and
the policies
5 days Mon 25-03-19 Fri 29-03-19 2
1.4 Justification of need of research 7 days Fri 12-04-19 Fri 19-04-19 4,3
1.5 Execution of feasibility study 3 days Mon 22-04-19
Wed 24-04-
19
5
2 Planning phase 68 days Mon 22-04-19
Wed 24-07-
19
2.1
Scope statement has been
defined
4 days Mon 22-04-19
Thu 25-04-
19
5
2.2 Large deliverables are divided 10 days Fri 26-04-19
Thu 09-05-
19
8
2.3 Identification of required tasks
for the production of
16 days Fri 10-05-19 Fri 31-05-19 9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7
REASEARCH MEATHODS AND PROJECT DESIGN
deliverables
2.4 Task duration are defined 3 days Wed 17-07-19 Fri 19-07-19 10
2.5 Forecast the cost 3 days Mon 22-07-19
Wed 24-07-
19
11
3 execution phase 14 days Thu 25-07-19
Tue 13-08-
19
3.1 Following the developed plan 2 days Thu 25-07-19 Fri 26-07-19 12
3.2
Allocation of the tasks to the
team members
2 days Mon 29-07-19
Tue 30-07-
19
14
3.3 Effective monitoring of process 3 days Wed 31-07-19 Fri 02-08-19 15
3.4
Management of the contract
that is secured in the project
7 days Mon 05-08-19
Tue 13-08-
19
16
4 monitor and control 15 days Wed 14-08-19 Tue 03-09-
19
4.1 Evaluate research progress 8 days Wed 14-08-19 Fri 23-08-19 17
4.2 Measurement of quality of
deliverables
7 days Mon 26-08-19 Tue 03-09-
19
19
5 project closure 22 days Wed 04-09-19 Thu 03-10-
19
5.1 Ensure completion of the 8 days Wed 04-09-19 Fri 13-09-19 20
REASEARCH MEATHODS AND PROJECT DESIGN
deliverables
2.4 Task duration are defined 3 days Wed 17-07-19 Fri 19-07-19 10
2.5 Forecast the cost 3 days Mon 22-07-19
Wed 24-07-
19
11
3 execution phase 14 days Thu 25-07-19
Tue 13-08-
19
3.1 Following the developed plan 2 days Thu 25-07-19 Fri 26-07-19 12
3.2
Allocation of the tasks to the
team members
2 days Mon 29-07-19
Tue 30-07-
19
14
3.3 Effective monitoring of process 3 days Wed 31-07-19 Fri 02-08-19 15
3.4
Management of the contract
that is secured in the project
7 days Mon 05-08-19
Tue 13-08-
19
16
4 monitor and control 15 days Wed 14-08-19 Tue 03-09-
19
4.1 Evaluate research progress 8 days Wed 14-08-19 Fri 23-08-19 17
4.2 Measurement of quality of
deliverables
7 days Mon 26-08-19 Tue 03-09-
19
19
5 project closure 22 days Wed 04-09-19 Thu 03-10-
19
5.1 Ensure completion of the 8 days Wed 04-09-19 Fri 13-09-19 20
8
REASEARCH MEATHODS AND PROJECT DESIGN
research deliverables
5.2
Close out the outstanding
contracts
7 days Mon 16-09-19
Tue 24-09-
19
22
5.3 Archive all paperwork 7 days Wed 25-09-19
Thu 03-10-
19
23
Figure: Gantt chart for the project
Source: (Created by author)
REASEARCH MEATHODS AND PROJECT DESIGN
research deliverables
5.2
Close out the outstanding
contracts
7 days Mon 16-09-19
Tue 24-09-
19
22
5.3 Archive all paperwork 7 days Wed 25-09-19
Thu 03-10-
19
23
Figure: Gantt chart for the project
Source: (Created by author)
9
REASEARCH MEATHODS AND PROJECT DESIGN
Project design
Figure: Project design using block diagram
Source: (Created by author)
REASEARCH MEATHODS AND PROJECT DESIGN
Project design
Figure: Project design using block diagram
Source: (Created by author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10
REASEARCH MEATHODS AND PROJECT DESIGN
In the initial stages of the system of the IoT, the thermal camera has been used for the
detection of any kind of pedestrians on the side of the road and prevent the collision. The GY
271 compass has been used in the system which is the compass module that has been
designed for the low field magnetic sensing with the digital interface and it is ideal for
providing the precise heading information [2]. Both of these devices has been connected with
the Arduino UNO that is the open source microcontroller board that is based on the
Microchip ATmega328P microcontroller and it is developed by the Arduino.cc [3]. The
Arduino UNO utilises the Microchip ENC28J60 stand-alone Ethernet controller IC that
features the host for handing the requirements of the network protocol [4]. This data from the
microchip is displayed in the LCD using the router and it is also stored in the Windows Azure
for the further use.
REASEARCH MEATHODS AND PROJECT DESIGN
In the initial stages of the system of the IoT, the thermal camera has been used for the
detection of any kind of pedestrians on the side of the road and prevent the collision. The GY
271 compass has been used in the system which is the compass module that has been
designed for the low field magnetic sensing with the digital interface and it is ideal for
providing the precise heading information [2]. Both of these devices has been connected with
the Arduino UNO that is the open source microcontroller board that is based on the
Microchip ATmega328P microcontroller and it is developed by the Arduino.cc [3]. The
Arduino UNO utilises the Microchip ENC28J60 stand-alone Ethernet controller IC that
features the host for handing the requirements of the network protocol [4]. This data from the
microchip is displayed in the LCD using the router and it is also stored in the Windows Azure
for the further use.
11
REASEARCH MEATHODS AND PROJECT DESIGN
Project individual research approach
Rajasekhar Polaka- MIT173408
Figure: project individual approach of Rajasekhar Polaka
Source: (Created by author)
REASEARCH MEATHODS AND PROJECT DESIGN
Project individual research approach
Rajasekhar Polaka- MIT173408
Figure: project individual approach of Rajasekhar Polaka
Source: (Created by author)
12
REASEARCH MEATHODS AND PROJECT DESIGN
In the starting phase, the process starts with the identification of the requirements,
then the literature review is done for the identification of the associated literature. After that
the proper testing of the system is done that creates the decision whether the testing process
was successful or not. If the testing process is successful then it moves to the next stage then
the analysis of the results is done and if the process is not successful then the configuration of
the system is checked again and the testing process is done again. With the proper analysis of
the results, the appropriate conclusion is derived, which is later used for the preparing of
report.
Manisha Kolle- MIT180076
Figure: Project individual approach for Manisha Kolle
REASEARCH MEATHODS AND PROJECT DESIGN
In the starting phase, the process starts with the identification of the requirements,
then the literature review is done for the identification of the associated literature. After that
the proper testing of the system is done that creates the decision whether the testing process
was successful or not. If the testing process is successful then it moves to the next stage then
the analysis of the results is done and if the process is not successful then the configuration of
the system is checked again and the testing process is done again. With the proper analysis of
the results, the appropriate conclusion is derived, which is later used for the preparing of
report.
Manisha Kolle- MIT180076
Figure: Project individual approach for Manisha Kolle
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13
REASEARCH MEATHODS AND PROJECT DESIGN
Source: Created by author
Windows Azure is used by the client. The data from the system is stored in the cloud
storage for the further use and the Azure provides the database platform for storing all the
data of the system. The literature review is done for the basic understanding of the working of
the system and the process of the working of the Azure is cleared.
Praneeth Kumar Desai Karanam
Figure: Project individual approach for Praneeth Kumar Desai Karanam
Source: (Created by author)
The extensive literature review of the working of the Microsoft Azure has been
conducted to understand how Azure works and how the storing of the data is done.
Chandrahas Reddy Bumireddy
REASEARCH MEATHODS AND PROJECT DESIGN
Source: Created by author
Windows Azure is used by the client. The data from the system is stored in the cloud
storage for the further use and the Azure provides the database platform for storing all the
data of the system. The literature review is done for the basic understanding of the working of
the system and the process of the working of the Azure is cleared.
Praneeth Kumar Desai Karanam
Figure: Project individual approach for Praneeth Kumar Desai Karanam
Source: (Created by author)
The extensive literature review of the working of the Microsoft Azure has been
conducted to understand how Azure works and how the storing of the data is done.
Chandrahas Reddy Bumireddy
14
REASEARCH MEATHODS AND PROJECT DESIGN
Figure: Project individual approach for Chandrahas Reddy Bumireddy
Source: (Created by author)
The complete process has been studied and the extensive conclusion has been
developed for understanding the proper working of complete system. It helps in
understanding the places where the damages might arise and how the mitigation plan could
be developed.
Madhu Kumar Vattepu
REASEARCH MEATHODS AND PROJECT DESIGN
Figure: Project individual approach for Chandrahas Reddy Bumireddy
Source: (Created by author)
The complete process has been studied and the extensive conclusion has been
developed for understanding the proper working of complete system. It helps in
understanding the places where the damages might arise and how the mitigation plan could
be developed.
Madhu Kumar Vattepu
15
REASEARCH MEATHODS AND PROJECT DESIGN
Figure: Project individual approach for Madhu Kumar Vattepu
Source: (Created by author)
This individual executed the processed working of the complete process of the
creation of the data to the storing of the data in the cloud for using later and use the data for
gaining valuable insight.
Budget
Hardware Manufacturer Price
Thermal Imaging Camera FLIR ONE Thermal $199.99
REASEARCH MEATHODS AND PROJECT DESIGN
Figure: Project individual approach for Madhu Kumar Vattepu
Source: (Created by author)
This individual executed the processed working of the complete process of the
creation of the data to the storing of the data in the cloud for using later and use the data for
gaining valuable insight.
Budget
Hardware Manufacturer Price
Thermal Imaging Camera FLIR ONE Thermal $199.99
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16
REASEARCH MEATHODS AND PROJECT DESIGN
Imaging Camera
GY 271 compass KOOKYE [1] $8.99
Arduino UNO Arduino $20.44
Microchip ENC28J60 Microchip $3.12
Router Cisco $369.00
ARDUINO MKR1000 WIFI Arduino $34.99
LCD
Windows azure cost
Service Cost (3 years) Annual cost
Server $2634567 $219567.5
Storage $235778 $196759.5
Total=$956863.667
Labour cost
Workforces Timeframe Overtime
(condition- after
38 hours)
Wages (contract
based)
Total cost
7 15 days (7 hours
day)
$5400 per person $37800
Bibliography
[1] S Talari, M Shafie-Khah, P Siano, V Loia, A Tommasetti, J Catalão. A review of
smart cities based on the internet of things concept. Energies. 2017;10(4):421.
REASEARCH MEATHODS AND PROJECT DESIGN
Imaging Camera
GY 271 compass KOOKYE [1] $8.99
Arduino UNO Arduino $20.44
Microchip ENC28J60 Microchip $3.12
Router Cisco $369.00
ARDUINO MKR1000 WIFI Arduino $34.99
LCD
Windows azure cost
Service Cost (3 years) Annual cost
Server $2634567 $219567.5
Storage $235778 $196759.5
Total=$956863.667
Labour cost
Workforces Timeframe Overtime
(condition- after
38 hours)
Wages (contract
based)
Total cost
7 15 days (7 hours
day)
$5400 per person $37800
Bibliography
[1] S Talari, M Shafie-Khah, P Siano, V Loia, A Tommasetti, J Catalão. A review of
smart cities based on the internet of things concept. Energies. 2017;10(4):421.
17
REASEARCH MEATHODS AND PROJECT DESIGN
[2] L Da Xu, W He, S Li. Internet of things in industries: A survey. IEEE
Transactions on industrial informatics. 2014 Nov;10(4):2233-43.
[3] N Rakesh. Performance analysis of anomaly detection of different IoT datasets
using cloud micro services. In2016 International Conference on Inventive
Computation Technologies (ICICT) 2016 Aug 26 (Vol. 3, pp. 1-5). IEEE.
[4] D Sangeetha, P Deepa. Efficient scale invariant human detection using histogram
of oriented gradients for IoT services. In2017 30th International Conference on
VLSI Design and 2017 16th International Conference on Embedded Systems
(VLSID) 2017 Jan 7 (pp. 61-66). IEEE.
[5] S Tomovic, K Yoshigoe, I Maljevic, I Radusinovic. Software-defined fog network
architecture for iot. Wireless Personal Communications. 2017 Jan 1;92(1):181-96.
[6] G De Angelis, A De Angelis, V Pasku, A Moschitta, P Carbone. A hybrid
outdoor/indoor positioning system for IoT applications. In2015 IEEE International
Symposium on Systems Engineering (ISSE) 2015 Sep 28 (pp. 1-6). IEEE.
[7] F Alam, R Mehmood, I Katib, NN Albogami, A Albeshri. Data fusion and IoT for
smart ubiquitous environments: A survey. IEEE Access. 2017;5:9533-54.
[8] D Wang, D Chen, B Song, N Guizani, X Yu, X Du. From IoT to 5G I-IoT: The
Next Generation IoT-Based Intelligent Algorithms and 5G Technologies. IEEE
Communications Magazine. 2018 Oct;56(10):114-20.
REASEARCH MEATHODS AND PROJECT DESIGN
[2] L Da Xu, W He, S Li. Internet of things in industries: A survey. IEEE
Transactions on industrial informatics. 2014 Nov;10(4):2233-43.
[3] N Rakesh. Performance analysis of anomaly detection of different IoT datasets
using cloud micro services. In2016 International Conference on Inventive
Computation Technologies (ICICT) 2016 Aug 26 (Vol. 3, pp. 1-5). IEEE.
[4] D Sangeetha, P Deepa. Efficient scale invariant human detection using histogram
of oriented gradients for IoT services. In2017 30th International Conference on
VLSI Design and 2017 16th International Conference on Embedded Systems
(VLSID) 2017 Jan 7 (pp. 61-66). IEEE.
[5] S Tomovic, K Yoshigoe, I Maljevic, I Radusinovic. Software-defined fog network
architecture for iot. Wireless Personal Communications. 2017 Jan 1;92(1):181-96.
[6] G De Angelis, A De Angelis, V Pasku, A Moschitta, P Carbone. A hybrid
outdoor/indoor positioning system for IoT applications. In2015 IEEE International
Symposium on Systems Engineering (ISSE) 2015 Sep 28 (pp. 1-6). IEEE.
[7] F Alam, R Mehmood, I Katib, NN Albogami, A Albeshri. Data fusion and IoT for
smart ubiquitous environments: A survey. IEEE Access. 2017;5:9533-54.
[8] D Wang, D Chen, B Song, N Guizani, X Yu, X Du. From IoT to 5G I-IoT: The
Next Generation IoT-Based Intelligent Algorithms and 5G Technologies. IEEE
Communications Magazine. 2018 Oct;56(10):114-20.
1 out of 18
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.